Date: 2026-07-31Category: Extra OrdinaryState: Union GovernmentCountry: India
Publication of Notification in the Gazette of India 3(1) of the PMP Act, 1962 (50 of 1962) for acquisition of Right of User (RoU) in land for laying underground pipeline from QPS RAMOL TO RAMOL GGS (8 INCH DIA), ONGC WELL 28 TO QGPL (TP26) in the State of Gujarat.
**Executive Summary**
This notification, issued by the Ministry of Petroleum and Natural Gas on July 30, 2026, declares the Central Government's intention to acquire the "Right of User" in specific lands in Gujarat for the purpose of laying two 8-inch diameter pipelines by ONGC. The project covers segments between QPS Ramol, Ramol GGS, and ONGC Well-28 across the Ahmedabad district. Interested parties must submit any written objections to the designated Competent Authority within 21 days from the date the Gazette copies are made available to the public.
**Key Points / Main Content**
**Legal Authority and Purpose**
* The notification is issued under Section 3, Sub-section (1) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962.
* The acquisition is deemed necessary in the public interest for the transportation of crude oil and gas.
**Project Specifications**
* **Pipeline 1:** QPS Ramol to Ramol GGS (8" diameter).
* **Pipeline 2:** ONGC Well-28 to QGPL (TP 26) (8" diameter).
* The project is to be executed and managed by Oil and Natural Gas Corporation Limited (ONGC).
**Geographical Scope**
* The land subject to acquisition is located in the State of Gujarat, District of Ahmedabad.
* Impacted areas include lands within the Talukas of Daskroi and Vatva.
* Specific villages identified in the schedule include Harniyav, Vanch, Gerat Nagar, and Hathijan.
**Objection Procedures**
* Any person with an interest in the scheduled land has the right to object to the acquisition.
* Objections must be submitted in writing to the Competent Authority at the ONGC Ahmedabad Asset office.
**Impact Analysis**
**Landowners and Persons Interested in Scheduled Lands**
**Impact**
The Central Government intends to acquire the "Right of User" for the land parcels listed in the schedule to facilitate pipeline installation. This allows ONGC to lay and maintain underground infrastructure.
**Action Required**
Affected parties should review the Survey and Block numbers listed in the schedule. If they wish to object, they must submit a written objection to the Competent Authority (Ahmedabad Asset) within 21 days of the Gazette's public availability.
**Oil and Natural Gas Corporation Limited (ONGC)**
**Impact**
ONGC is authorized as the executing agency for the pipeline project and is responsible for the acquisition process through its Competent Authority.
**Action Required**
The office of the CGM (C&M) in Ahmedabad must receive, process, and address written objections submitted by the public within the statutory timeframe.
**Competent Authority (Ahmedabad Asset)**
**Impact**
Designated as the official recipient of legal challenges and objections related to this land acquisition.
**Action Required**
Must be available at the specified office in Avani Bhavan, Chandkheda, to receive and evaluate written objections according to the 1962 Act.
Key Entities Referenced
Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962: The primary legislation under which the Central Government acquires the right of user in land for laying pipelines.
Ministry of Petroleum and Natural Gas: The central ministry responsible for issuing this notification to declare intent for land acquisition.
Oil and Natural Gas Corporation Limited (ONGC): The primary entity authorized to lay the pipelines and for whose project the right of user in land is being acquired.
Ahmedabad, Gujarat: The primary location covering the villages in Daskroi and Vatwa talukas where the pipeline projects and land acquisition are situated.