Skip to content
Home India Ministry of Power Notifications STATUS ON PUMPED STORAGE PROJECTS... (Official PDF)
Date: 20th July 2026 Category: Press Release Jurisdiction: India, Central Government

STATUS ON PUMPED STORAGE PROJECTS - 20th July 2026 - Ministry of Power - Gazette Notification PDF

Issued by Ministry of Power

Read or download the official PDF of this gazette notification issued by the Ministry of Power on 20th July 2026. Classified under Press Release.

Executive Summary & Key Takeaways

Executive Summary This report details the status of Pumped Storage Projects (PSPs) in India as of July 2026, highlighting 11 projects currently under construction (15,870 MW) and 6 awaiting construction (8,140 MW). It outlines significant regulatory reforms by the Ministry of Power, MoEF&CC, and CEA intended to streamline environmental clearances and provide financial incentives. A critical deadline is noted: construction must be awarded by June 30, 2028, to qualify for a 25-year waiver of Inter-State Transmission System (ISTS) charges.

Key Points / Main Content

Project Status and Capacity

  • Active Projects: 11 PSPs are under construction with a total capacity of 15,870 MW; the largest is the Saidongar-1 Karjat PSP (3,000 MW) targeted for December 2029.
  • Pending Projects: 6 PSPs totaling 8,140 MW have received CEA concurrence or appraisal but are yet to begin construction.

Environmental and Statutory Clearance Reforms

  • Simplified Appraisals: PSPs can now be appraised under the B2 category subject to specific conditions.
  • Baseline Data Requirements: Off-stream closed-loop PSPs require one season of baseline data (excluding monsoon), while off-stream open-loop PSPs require two seasons (pre- and post-monsoon).
  • Forest Area Surveys: Provisions for mining project surveys have been extended to PSPs, including an enhanced number of boreholes for exploration.

Regulatory and Administrative Streamlining

  • DPR Concurrence: The timeline for the Central Electricity Authority (CEA) to concur with Detailed Project Reports (DPR) has been reduced from 90 days to 50 days.
  • Exemptions: PSPs no longer require clearance for Inter-State Aspects. Off-stream closed-loop schemes are exempt from CEA concurrence regardless of capital expenditure.
  • CapEx Limits: The capital expenditure limit requiring CEA concurrence for other hydro schemes has been raised to ₹3,000 crore.

Financial Incentives and Private Participation

  • Infrastructure Support: Budgetary support is provided for enabling infrastructure such as roads, bridges, transmission lines, and communication systems.
  • ISTS Waiver: A 100% waiver of Inter-State Transmission System charges is available for 25 years for projects awarded on or before June 30, 2028.
  • Competitive Bidding: New guidelines for tariff-based competitive bidding (TBCB) were notified in February 2025 to standardize the procurement of storage capacity.

Impact Analysis

Project Developers Impact Developers benefit from significantly reduced administrative timelines, lower exploration restrictions in forest areas, and major cost savings through infrastructure subsidies and transmission charge waivers. Action Required Developers must ensure construction contracts are awarded by June 30, 2028, to secure the ISTS waiver and adhere to the new seasonal baseline data collection requirements for environmental clearances.

Central Electricity Authority (CEA) Impact The CEA’s workload is redirected toward larger projects (above ₹3,000 crore) and technical guidance, as they are now exempt from overseeing Inter-State Aspects and closed-loop schemes. Action Required The CEA must adhere to the accelerated 50-day timeline for DPR concurrence and provide technical guidance for projects in the exempted category upon request.

State Power Utilities and Private Executing Agencies Impact Agencies (such as APGENCO, KPCL, and Tata Power) are responsible for meeting specific commissioning targets ranging from 2026 to 2032 to support grid stability and renewable energy integration. Action Required Executing agencies must align project timelines with the target commissioning dates specified in the status report (e.g., Gandhi Sagar PSP by Dec '26).

Key Entities Referenced

Central Electricity Authority (CEA): The primary technical regulator responsible for the appraisal and concurrence of Detailed Project Reports (DPR) for Pumped Storage Projects. Ministry of Environment, Forest & Climate Change (MoEF&CC): The ministry responsible for environmental clearances, B2 category appraisals, and forest area survey permissions for hydro and storage projects. Guidelines to promote development of Pumped Storage Projects: The foundational policy notified by the Ministry of Power on April 10, 2023, to encourage and streamline PSP development in India. Central Electricity Regulatory Commission (CERC): The regulator that provided a 100% waiver of Inter-State Transmission System (ISTS) charges for Pumped Storage Projects for a 25-year period. Tariff Based Competitive Bidding (TBCB) Guidelines: The regulatory framework notified for the transparent and standardized procurement of storage capacity and energy from pumped storage plants.
Official Gazette PDF Record Download Official PDF (STATUS ON PUMPED STORAGE PROJECTS) →

Official Gazette Notification PDF Viewer

See Full Document Text & PDF Transcript
Ministry of Power STATUS ON PUMPED STORAGE PROJECTS प्रव तथ: 20 JUL 2026 3:45PM by PIB Delhi Presently, 11 Pumped Storage Projects (PSPs) with an aggregate installed capacity of 15,870 MW are under construction Table- I. In addition, 6 PSPs with an aggregate installed capacity of 8,140 MW have been concurred/appraised by the Central Electricity Authority (CEA) and are yet to be taken up for construction Table-II. The measures taken in respect of timely environmental and statutory clearances for Pumped Storage Projects (PSPs) include: i. Ministry of Environment, Forest & Climate Change (MoEF&CC), vide its notification dated 18.05.2023, has enabled appraisal of PSPs under B2 category subject to certain conditions. ii. The MoEF&CC on 14.08.2023, has issued specific Terms of Reference (TOR) for the proposals involving off stream PSPs wherein collection of baseline data for one season (other than monsoon) is prescribed for off stream closed loop PSPs and collection of baseline data for two seasons (pre- monsoon & post-monsoon) is prescribed for off stream open loop PSPs. iii. The MOEF&CC on 20.08.2024, has extended the provisions relating to survey in the forest areas for mining projects to other development projects including hydel/PSPs. iv. MOEF&CC vide letter dated 10.09.2025 has enhanced the number of boreholes for undertaking survey and explorations in the forest area for mining and developmental projects including hydel / PSPs. v. Central Electricity Authority (CEA) has revised Guidelines for formulation and concurrence of Detailed Project Report (DPR) of PSPs. Under the revised guidelines, the timeline for concurrence of DPR has been reduced from 90 days to 50 days for all type of PSPs. Further, the clearance of Inter-State Aspects is not required for PSPs. vi. The Government of India, vide Gazette notification dated 01.08.2025, has revised the capital expenditure limit for schemes related to setting up hydro generating stations to ₹3,000 crore, requiring the concurrence of the CEA. Further, the Government has exempted off-stream closed- loop pumped storage schemes, irrespective of the quantum of capital expenditure, from the requirement of concurrence by the CEA. However, Developers may seek technical guidance from the CEA for projects under exempted category. Pumped Storage Projects (PSPs) support the integration of renewable energy by storing surplus energy during off-peak periods and supplying power during peak demand. They provide long-duration energy storage, balancing power and ancillary grid services such as frequency regulation, voltage support and black start capability, thereby supporting grid stability, reliability and higher renewable energy penetration. Central Government has taken a number of measures to encourage greater private sector participation in the development of PSPs as listed below:i. Ministry of Power has notified Guidelines to promote development of Pumped Storage Projects in the country on 10.04.2023. ii. Budgetary Support to Cost of Enabling Infrastructure, i.e., roads/bridges, railway sidings, ropeways, communication infrastructure and transmission line from power house to nearest pooling point. iii. To provide a transparent, fair, standardized procurement framework based on open competitive bidding with appropriate risk-sharing between various stakeholders, MoP vide Gazette notification dated 06.02.2025, has notified tariff based competitive bidding (TBCB) guidelines for procurement of storage capacity/stored energy from pumped storage plants. iv. The Central Electricity Regulatory Commission (CERC), vide its Notification dated 26.06.2025, has provided for 100% waiver of Inter-State Transmission System (ISTS) charges for Pumped Storage Projects (PSPs) for a period of 25 years from the Commercial Operation Date (COD), in respect of projects for which the construction work is awarded on or before 30.06.2028. TABLE-I LIST OF UNDER CONTRUCTION PUMPED STORAGE PROJECTS Sl.No. Name of the Project State/UT Capacity Target for Commissioning (Executing Agency) (MW) 1 Upper Sileru PSP (APGENCO) Andhra 1350 Feb'29 Pradesh 2 Sharavathy PSP (KPCL) Karnataka 2000 May'32 3 Kundah PSP (Phase-I,II&III) Tamil Nadu 500 Feb’27 (TANGEDCO) 4 MP30GandhiSagarPSP(Greenko MP01 Madhya 1920 Dec'26 IREP Private Limited) Pradesh 5 Chitravathi PSP (Adani Renewable Andhra 500 Feb'27 Energy Forty-Two Limited) Pradesh 6 Bhivpuri PSP (Tata Power Company Maharashtra 1000 Feb'29 Limited) 7 Saundatti Karnataka 1600 Dec'27 PSP(GreenkoKA01IREPPrivateLimited) 8 BhavaliPSP(JSW Energy PSP Two Maharashtra 1500 Dec'28 Limited) 9 Gandikota PSP(Adani Renewable Energy Andhra 1000 Mar'29 Fifty-One Limited) Pradesh10 Tarali PSP(Adani Renewable Energy Maharashtra 1500 Jun'29 One Limited) 11 Saidongar-1KarjatPSP Maharashtra 3000 Dec'29 (Torrent Energy Storage Solutions) TOTAL 15,870 TABLE-II LIST OF PSP SCONCURRED/APPRAISED BY CEA AND ARE YET TO BE TAKEN UP FOR CONSTRUCTION Sl.No. Name of the project State/UT Capacity Date of Concurrence/ (Executing Agency) (MW) Appraisal 1 ChichlikPSP* Uttar Pradesh 1560 08.07.2026 (Avaada Water Battery Pvt.Ltd.) 2 Pane PSP Maharashtra 1500 09.10.2025 (JSW Neo Energy Ltd) 3 Shirawta PSP 1800 01.09.2025 (TataPower Company Maharashtra Ltd) 4 Kandhaura PSP Uttar Pradesh 1680 13.06.2025 (JSWEnergyPSPSix Ltd) 5 Upper Indravati PSP (Odisha Odisha 600 19.08.2024 Hydro Power Corporation Ltd.) 6 Turga PSP West Bengal 1000 05.10.2016 (West Bengal State Electricity Distribution Company Ltd.) TOTAL 8,140 *Appraised This information was given by The Minister of State in the Ministry of Power, Shri Shripad Naik, in a written reply in the Rajya Sabha today.**** NR/MD (रलीज़ आईडी: 2286558) आगंतुक पटल : 2124 इस वज्ञ को इन भाषाओ ंम पढ़: Urdu , ही , Tamil

Continue your research