**Executive Summary**
This document is the Tamil Nadu Government Gazette, published on February 1, 2017. It includes notifications from Quasi-Government bodies and Public Sector Undertakings regarding the erection of transmission lines by the Tamil Nadu Transmission Corporation Limited (TANTRANSCO) in various districts. Interested parties can raise objections within the timeframe specified.
**Key Points / Main Content**
* **General Construction Circle - II, Chennai - Erection of Transmission Lines:**
* TANTRANSCO sanctioned the erection of a 110 KV Single Circuit line on Multi-Circuit/Double Circuit towers from Ottiyambakkam 400/230 KV substation to Perumbakkam Slum Clearance Board 110/11 KV substation, covering a route length of 6.539 km.
* **General Construction Circle - II, Chennai - Erection of Transmission Lines, various districts:**
* New 110 KV Valudur-Karaikudi double circuit transmission tower and double circuit transmission line to Uppur 110/33-11 KV sub station. Length 11.2KM
* New 110 KV Double Circuit to Nallamanayakkanpatti 110 KV from 110 KV Aruppukottai-Madurai-1 electric line. length 8.50km
* New 110 KV Double Circuit from 110 KV Sipkat-Everlasting-Kayatharu electric line to Arasadi 110/22 KV sub station. length 3.00km
* New 230 KV transmission line from Tiruchuzhi 230/110 KV substation to Kamuthi 400/230 KV substation. Length 29.00km
* 110 KV Double Circuit, install panther conductors in Then-Sembatti transmission tower and modify the existing T.Off system. New 110/22KV to periyakulam sub station. Length 6.22km
* Remove existing conductors and install Zebra conductors from electric tower no. 6-103 on 230KV Sembi-Checkanoorani transmission tower. Length 27.58km
* **Objections:**
* Individuals with grievances regarding the high-voltage power line schemes may submit their objections to the undersigned authority within two months from the date of publication, according to the Electricity Act of 2003.
* Individuals with grievances regarding the Chennai power lines erection should voice them within 1 month from the date of issue of the publication as per the Electricity Act, 2003.
**Impact Analysis**
**General Public**
* **Impact:** The public is affected as these projects involve high-voltage power lines potentially running through their areas.
* **Action Required:** Anyone with grievances regarding these projects can raise objections within the specified timeframes.
**Tamil Nadu Transmission Corporation Limited (TANTRANSCO)**
* **Impact:** TANTRANSCO is responsible for erecting the new transmission lines.
* **Action Required:** TANTRANSCO is expected to undertake the work shortly.
**Residents of Chennai and Kanchipuram Districts**
* **Impact:** Residents will benefit from improved power distribution to meet growing demands.
* **Action Required:** Individuals with grievances regarding the Chennai power lines erection should voice them within 1 month from the date of issue of the publication as per the Electricity Act, 2003.
Key Entities Referenced
Tamil Nadu Government Gazette: Official gazette publishing government notifications
Part VI-Section 3(b): Section of the Tamil Nadu Government Gazette containing notifications from quasi-government bodies and PSUs
Tamil Nadu Transmission Corporation Limited (TANTRANSCO): Entity responsible for sanctioning the erection of transmission lines.
Electricity Act, 2003: Law referenced for making representations regarding the schemes.
Chennai: Location where General Construction Circle - II, operates. Also, location of 400/230 KV sub-station in the description of Sl. No. 1