Home India Joint Electricity Regulatory Commission for UT of Jammu & Kashmir and UT of Ladakh Whereas, in the exercise of powers conferred under Section 6...
Date: 12-Jun-2023 Category: Extra Ordinary State: Union Government Country: India

Whereas, in the exercise of powers conferred under Section 61 h, and Section 86 1 e read with sub section I and clause zd and zi of sub section 2 of Section 181 of the Electricity Act

Issued by Joint Electricity Regulatory Commission for UT of Jammu & Kashmir and UT of Ladakh · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

What it means

  • The gazette notification pertains to the regulations for Grid Interactive Renewable Energy (RE) systems in the Union Territories of Jammu & Kashmir and Ladakh.
  • It establishes a framework for connecting renewable energy systems to the grid, including net metering, net billing, and gross metering arrangements.
  • The regulations outline eligibility criteria, technical standards, metering arrangements, and billing procedures for prosumers (consumers who also generate electricity).
  • It also addresses third-party ownership of RE systems and capacity limits at the distribution transformer level.

Key Changes

  • The notification introduces the Joint Electricity Regulatory Commission (JERC) regulations for Grid Interactive Renewable Energy systems in Jammu & Kashmir and Ladakh, effective from the date of publication in the official gazette (June 12, 2023).
  • It defines various terms related to renewable energy systems, metering, and billing arrangements.
  • Eligible consumers of all categories can set up RE systems under net metering up to 500 kW capacity, net-billing above 500 kW and up to 1 MW, and gross metering up to 1 MW.
  • Cumulative capacity of RE systems connected to a distribution transformer is allowed up to 100% of its rated capacity.
  • The regulations specify metering requirements, including the use of net meters, renewable energy meters, and check meters (for systems above 20 kW).
  • It outlines billing procedures for net metering, net billing, group net metering, virtual net metering and gross metering arrangements, including provisions for carrying forward excess generation and settling unadjusted credits at the end of the financial year.
  • The regulations exempt RE projects from banking charges.
  • It specifies application and registration procedures for connecting RE systems to the grid, with timelines for various steps and compensation for delays by the distribution licensee (Rs. 100 per day).
  • Model connection agreements for net metering, net billing, and gross metering are included as annexures.

Impact Analysis

Prosumers (Consumers Generating Renewable Energy)

  • Action Item: Prosumers should evaluate the different metering and billing options and choose the one that best suits their needs. They should also ensure that their RE systems comply with the technical standards and safety requirements outlined in the regulations.

Distribution Licensees

  • Action Item: Distribution licensees should establish online portals for receiving applications, update their websites with relevant information, and ensure that their processes comply with the timelines outlined in the regulations. They should also prepare for increased RE generation on their grids and ensure grid stability.

Renewable Energy Project Developers

  • Action Item: RE project developers should explore opportunities to develop RE projects in Jammu & Kashmir and Ladakh, taking advantage of the clear regulatory framework and the potential for third-party ownership.

Government/Local Authorities

  • Action Item: Government/Local Authorities should explore opportunities to develop RE projects in Jammu & Kashmir and Ladakh, taking advantage of the Virtual Net Metering Framework.

Key Entities Referenced

Joint Electricity Regulatory Commission (JERC): The regulatory body responsible for setting tariffs and regulations for the electricity sector in the Union Territories of Jammu & Kashmir and Ladakh. Distribution Licensee: The entity responsible for distributing electricity to consumers in a specific area. Eligible Consumer: A consumer of electricity who intends to use a renewable energy system in their premises. Prosumer: A consumer who also generates electricity from a renewable energy system. Central Electricity Authority (CEA): A statutory body responsible for technical standards and safety regulations in the electricity sector. Electricity Act, 2003: The primary legislation governing the electricity sector in India. JAKEDA: Jammu and Kashmir Energy Development Agency
Official Source Record View Original Source →
See Full Document Text
रजजस्ट्री स.ं डी.एल.- 33004/99 REGD. No. D. L.-33004/99 सी.जी.-जे.के.-अ.-13062023-246490 xxxGIDHxxx CG-JK-E-13062023-246490 xxxGIDExxx ऄसाधारण EXTRAORDINARY भाग III—खण् ड 4 PART III—Section 4 प्राजधकार स ेप्रकाजित PUBLISHED BY AUTHORITY स.ं 375] नइ कदल्ली, सोमिार, जनू 12, 2023/ज्य ष्े ठ 22, 1945 No. 375] NEW DELHI, MONDAY, JUNE 12, 2023/JYAISHTHA 22, 1945 सयं क्तु जिद्यतु जिजनयामक अयोग जम्म ू और कश्मीर केंद्र िाजसत प्रदेि और लद्दाख केंद्र िाजसत प्रदेि के जलए ऄजधसचू ना जम् म,ू 29 मइ, 2023 स.ं जइे अरसी-जके ेएल/अरइजी/2023/11.—जबकक जिद्युत ऄजधजनयम 2003 (2003 का 36) की धारा 61(एच) और धारा 86(1)(इ) पठठत धारा 181 की ईपधारा की ईपधारा (अइ) और ऄनच्ु छेद (ज़ेडडी) और (ज़ेडअइ) और आस संबंध म ें सक्षम बनान ेिाली सभी िजक्तयों का प्रयोग करते हुए केंद्र िाजसत प्रदेि ‘जम्मू और कश्मीर ि केंद्र िाजसत प्रदेि लद्दाख’ के जलए सयं क्तु जिद्युत जिजनयामक अयोग जनम्नजलजखत जिजनयमों का जनमााण करता ह।ै केंद्र िाजसत प्रदेि ‘जम्म ू और कश्मीर ि केंद्र िाजसत प्रदिे लद्दाख के जलए सयं क्तु जिद्यतु जिजनयामक अयोग (जिड आंटरएजटटि निीकरणीय उजा ाप्रणाली और सबं जधधत मामल)े जिजनयमािली, 2023 1 संजक्षप्त नाम, जिस्ट्तार और प्रारंभ 1.1 आन जिजनयमों को “संयुक्त जिद्युत जिजनयामक अयोग, केंद्र िाजसत प्रदेि जम्मू और कश्मीर ि केंद्र िाजसत प्रदेि लद्दाख (जिड आंटरएजटटि निीकरणीय उजाा प्रणाली और संबजधधत मामले) जिजनयम, 2023” कहा जाएगा। 1.2 ये जिजनयम राजपत्र में ईनके प्रकािन की जतजथ से लाग ूहोंगे। 1.3 ये जिजनयम केंद्र िाजसत प्रदिे जम्मू और कश्मीर तथा केंद्र िाजसत प्रदेि लद्दाख में लागू होंगे। 2 पठरभाषाए,ं संजक्षप्ताक्षर और व्याख्याएं 3697 GI/2023 (1)2 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2.1. आन जिजनयमों में, जब तक कक संदभा से ऄधयथा ऄपेजक्षत न हो: (1) "ऄजधजनयम" का ऄथा ह ैजिद्युत ऄजधजनयम, 2003 (2003 का 36), और ईसके बाद के संिोधन; (2) "औसत जबजली खरीद लागत" (एपीपीसी) का ऄथ ा ह ै भाठरत औसत मल्ू य ह ै जजस पर जितरण लाआसेंसधारी न े संबंजधत खुदरा अपूर्तत टैठरफ अदेि या ककसी ऄधय सामाधय या जिजिष्ट अदेि में अयोग द्वारा ऄनुमोकदत स्ट्ि- ईत्पादन की लागत, यकद कोइ हो, सजहत जबजली (अरइ स्रोतों से खरीद को छोड़कर) की खरीद की ह ै या खरीदने की संभािना ह;ै (3) "प्राजधकरण" का ऄथ ाऄजधजनयम की धारा 70 की ईप-धारा (1) म ेंसंदर्तभत केंद्रीय जिद्युत प्राजधकरण ह;ै (4) "जबललग साआकल" का ऄथ ा ह ै िह ऄिजध ह ै जजसके जलए अयोग द्वारा लाआसेंसधारी द्वारा ईपभोक्ताओं की जिजभन्न श्रेजणयों के जलए जनर्ददष्ट जनयजमत जबजली जबल तैयार ककए जाते ह;ैं (5) "सीओडी" या "िाजणजज्यक सचं ालन जतजथ" या "िाजणजज्यक संचालन का कदन" का ऄथ ा िह जतजथ जजस पर निीकरणीय उजा ाप्रणाली जिड प्रणाली के साथ लसक्रोनाआज़ होती ह;ै (6) "चके मीटर" का ऄथा ह ै एक मीटर, जो करेंट रांसफामार (सीटी) और िोल्टेज रांसफामार (िीटी) के ईसी कोर से जुड़ा होगा, जजससे निीकरणीय उजाा मीटर जड़ु ा हुअ ह ै और मुख्य मीटर या निीकरणीय उजा ा मीटर के खराब होने की जस्ट्थजत म ेंआसका ईपयोग जबजली के लेखांकन और जबललग के जलए ककया जाएगा।; (7) "अयोग" का ऄथ ा ह ै जम्मू और कश्मीर के केंद्र िाजसत प्रदेि ि लद्दाख के केंद्र िाजसत प्रदेि के जलए संयुक्त जिद्युत जिजनयामक अयोग; (8) "कनटे िन ऄनबु धं " का ऄथा ह ै जितरण लाआसेंसधारी और ईपभोक्ता के बीच ककया गया सकल मीटररग या नेट- जबललग (नेट फीड-आन) या नेट-मीटररग आंटर-कनेटिन समझौता; (9) "ईपभोक्ता" का ऄथ ाऄजधजनयम में पठरभाजषत ईपभोक्ता से ह;ै (10) "ईपभोक्ता जिकायत जनिारण फोरम (सीजीअरएफ)" का ऄथ ा ह ै ऄजधजनयम की धारा 42(5) के तहत स्ट्थाजपत ईपभोक्ताओं की जिकायत के जनिारण के जलए मंच; (11) "ऄनबु जं धत लोड" या "ऄनुबंध मांग" का ऄथा ह ै केडब्लल्यू, केिीए या एचपी में ऄजधकतम मागं , जजसके जितरण के जलए लाआसेंसधारी द्वारा अपूर्तत की सहमजत दी ह ै और जैसा कक लाआसेंसधारी और ईपभोक्ता के बीच जनष्पाकदत समझौते में दिााया गया ह;ै (12) "जितरण लाआससें धारी" का ऄथ ा ह ैएक व्यजक्त जजसे ऄजधजनयम की धारा 14 (ख) के तहत लाआसेंस प्रदान ककया गया ह ै जो अपूर्तत के ऄपन े क्षत्रे म ें ईपभोक्ताओं को जितरण प्रणाली संचाजलत और बनाए रखन े और जबजली की अपूर्तत करन े के जलए ऄजधकृत करता ह;ै (13) "जिद्यतु अपर्तू त कोड" का ऄथा ह ै ऄजधजनयम की धारा 50 के तहत अयोग द्वारा जनर्ददष्ट जिद्युत अपूर्तत जनयमािली; (14) "पात्र ईपभोक्ता" का ऄथ ा ह ै जितरण लाआसेंसधारी की अपूर्तत के क्षेत्र में जबजली का ईपभोक्ता, जो ऄपन े पठरसर म ें निीकरणीय उजाा प्रणाली का ईपयोग करन े का आरादा रखता ह,ै जो स्ट्ियं की जिद्युत अिश्यकताओं के सभी या अंजिक या ककसी भी जहस्ट्से को ऑफसेट करता ह ै और ऐसी प्रणाजलयां स्ट्ियं के स्ट्िाजमत्ि िाली हो सकती ह ैंया तीसरे पक्ष को पत्त ेपर दी जा सकती ह;ै (15) "फीड-आन-टैठरफ" का ऄथ ा ह ै अयोग द्वारा जनधााठरत सामाधय टैठरफ जजसे निीकरणीय उजाा पठरयोजनाओं स े जबजली ईत्पादन के जलए सकल मीटररग या नेट-जबललग के जलए जनधााठरत ककया जाता है, जो अयोग द्वारा निीकरणीय उजा ास्रोत जिजनयमन से टैठरफ जनधाारण के जलए जनयम और ितों के ऄनुसार बनाया जाता है; (16) "जिड" का ऄथा ह ै जनम्न िोल्टेज जिद्युत नेटिका, जितरण और पारेषण नेटिका या आंटर-कनेटटेड रांसजमिन लाआनों, ईप-स्ट्टेिनों और उजा ा की जबक्री के जलए ईत्पादन सयं ंत्रों या आन जिजनयमों म ें पठरभाजषत उजा ा के व्हीललग के जलए ईच्च िोल्टेज बकै बोन जसस्ट्टम; (17) "िॉस-मीटररग" का ऄथा ह ै एक ऐसा तंत्र जजसके द्वारा एक प्रोज्यूमर की जिड आंटरएजटटि ठरधयूएबल एनजी जसस्ट्टम से ईत्पन्न कुल उजाा और प्रोज्यूमर द्वारा खपत की गइ कुल उजाा को ईपयक्तु मीटररग व्यिस्ट्था के[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 3 माध्यम से और जबललग ईद्देश्य के जलए ऄलग से अकलन ककया जाता है; जबकक, ईपभोक्ता द्वारा खपत की गइ कुल उजाा को लाग ू खुदरा टैठरफ में िाजमल ककया जाता ह ै और कुल निीकरणीय उजाा को अयोग द्वारा जनधााठरत फीड-आन टैठरफ के ऄनुसार अकलन ककया जाता ह।ै (18) “िपु नटे मीटररग" का ऄथ ा ह ैएक ऐसी व्यिस्ट्था जजसके द्वारा ऄजतठरक्त उजाा ईत्पन्न की जाती ह ैऔर नेट मीटर के माध्यम से निीकरणीय उजा ा प्रणाली से आंजेटट की जाती ह ै और जनयाात की गइ उजाा को एक ही ईपभोक्ता के एक स े ऄजधक जिद्युत सेिा कनेटिन (कनेटिनों) म ें ईसी जितरण लाआसेंसधारी के अपूर्तत क्षेत्र के भीतर जस्ट्थत ईसी या ऄलग पठरसर म ेंसमायोजजत ककया जाता है; (19) "स्ट्थाजपत क्षमता" का ऄथ ा ह ै निीकरणीय उजाा प्रणाली की सभी आकाआयों के केडबल्यूपी में व्यक्त नेम प्लेट क्षमताओं का योग या अयोग द्वारा ऄनुमोकदत अईटपुट टर्तमनलों पर अंकजलत की गइ निीकरणीय उजा ा प्रणाली की क्षमता; (20) "नटे जबललग/नटे मीटररग व्यिस्ट्था के जलए आंटरकनटे िन प्िाआंट " का ऄथा ह ै निीकरणीय उजाा ईत्पादन प्रणाली का प्रोज्यूमर के पठरसर में मीटर के अईटगोआंग टर्तमनल के साथ आंटरफेस: बिते कक, यकद ईपभोक्ता हाआ टेंिन (एचटी) स्ट्तर पर जड़ु ा हुअ ह,ै तो "आंटरकनेटिन प्िाआंट" का ऄथ ा होगा जितरण लाआसेंसधाठरयों के मीटररग ईपकरण के अईटगोआंग टर्तमनल के साथ निीकरणीय उजाा ईत्पादन प्रणाली का आंटरफेस। (21) " सकल मीटररग व्यिस्ट्था के जलए आंटरकनटे िन पॉआंट " का ऄथ ा ह ै निीकरणीय उजाा ईत्पादन प्रणाली का आंटरफेस, प्रोज्यूमर के पठरसर में मीटर के अने िाल े टर्तमनल के साथ आंटरफेस: बित े कक, यकद प्रोज्यूमर हाइ टेंिन (एचटी) स्ट्तर पर जुड़ा हो , "आंटरकनेटिन पॉआंट" का ऄथा होगा निीकरणीय उजाा ईत्पादन प्रणाली का आंटरफेस होगा; (22) "चालान" का ऄथा ह ै ईपभोक्ता को जितरण लाआसेंसधारी द्वारा एक अिजधक जबल / ऄनुपरू क जबल या एक चालान / परू क चालान; (23) "अआलालं डग" का ऄथा ह ै एक जिद्युत प्रणाली घटना जजसमें निीकरणीय उजाा प्रणाली के माध्यम से संचाजलत जितठरत जनरेटर, बाहरी जिड पािर या जिड अईटेज जस्ट्थजतयों के ऄभाि म ें ककसी साआट या स्ट्थान को जबजली देना जारी रखते ह।ैं (24) "माह" का ऄथ ा ह ै महीन े के पहले कदन / तारीख से िुरू होने िाला और महीन े के अजखरी कदन / तारीख के साथ समाप्त होने िाला ऄिं ेजी कैलडें र का महीना। भाग माह जिजिष्ट महीने म ें कदनों की कुल संख्या के ऄनुपात म ें कदनों की जिजिष्ट संख्या के जलए लागू होगा; (25) "नटे -जबललग या नटे फीड-आन" का ऄथा ह ै अपूर्तत के लबद ु पर नेट-जबललग या नेट फीड-आन के जलए ईपयोग ककया जाने िाला एकल जद्वकदि उजाा मीटर जजसमें जिड स े प्राप्त उजाा और जिड आंटरएजटटि निीकरणीय उजा ा प्रणाली स ेजनयाात की गइ उजा ाएक प्रोज्यूमर का मल्ू य दो ऄलग-ऄलग टैठरफ पर लगाया जाता ह,ै जहां- (i) अयाजतत उजाा का मौकद्रक मल्ू य लागू खुदरा िल्ु क पर अधाठरत होता ह;ै (ii) जनयााजतत निीकरणीय उजा ा का मौकद्रक मूल्य अयोग द्वारा जनधााठरत फीड-आन टैठरफ पर अधाठरत होता ह;ै (iii) जबल की जान े िाली िुद्ध राजि (या क्रेजडट / कैरीओिर) की गणना के जलए जनयााजतत उजाा के मौकद्रक मूल्य को अयाजतत उजाा के मौकद्रक मूल्य से घटाया जाता है; (26) "नटे मीटररग" का ऄथ ा ह ै एक ऐसा तंत्र जहा ं िुद्ध अयाजतत या जनयाात उजा ा की गणना करन े के जलए एक प्रोज्यूमर के जिड आंटरएजटटि ठरधयूएबल एनजी जसस्ट्टम से जिड को जनयाात की जाने िाली निीकरणीय उजा ा को यूजनट (केडबल्यूएच) में जिड से अयाजतत उजाा को घटाया जाता ह ै और अपूर्तत के लबद ुपर नेट-मीटररग के जलए एकल जद्वकदि उजाा मीटर का ईपयोग करके लागू खुदरा टैठरफ के अधार पर जितरण लाआसेंसधारी द्वारा िुद्ध उजा ाअयात या जनयाात का जबल भेजा जाता ह ैया क्रेजडट ककया जाता ह ैया कैरी ओिर ककया जाता है; (27) "नटे मीटर" का ऄथा ह ै एक ईपयुक्त जद्व-कदिात्मक उजाा मीटर जो जिड से अयात और निीकरणीय उजाा प्रणाली में ईत्पन्न जबजली के जनयाात दोनों को ठरकॉड ाकरन े में सक्षम ह;ै4 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (28) "दाजयत्ि जनकाय" का ऄथ ा ह ै जबजली के लाआसेंस प्राप्त अपूर्ततकताा, जितरण लाआसेंसधारी, कैजप्टि ईपयोगकताा और ओपन एटसेस ईपभोक्ता, जजधह ें अयोग द्वारा बने गए निीकरणीय उजाा खरीद जिजनयमािली के तहत पहचाना जाता ह;ै और जजसको ऄजधजनयम की धारा 86 की ईपधारा (1) के खंड (ड़) के तहत अयोग द्वारा समय-समय पर जनधााठरत निीकरणीय उजाा खरीद दाजयत्िों को पूरा करना ऄजनिाया होता है; (29) "लोकपाल" का ऄथ ाह ैऄजधजनयम की धारा 181 के साथ पठठत धारा 42 (6) के ऄनुसार जनयक्तु व्यजक्त; (30) "ओपन एटससे कंज्यमू र" का ऄथा ह ै एक व्यजक्त जजसे अपूर्तत के ऄपने क्षेत्र के जितरण लाआससें धारी के ऄलािा ककसी ऄधय व्यजक्त से जबजली की अपूर्तत प्राप्त करने के जलए आंरा-स्ट्टेट रांसजमिन जसस्ट्टम और / या जितरण प्रणाली का ईपयोग करने की ऄनुमजत ह,ै और आस ऄजभव्यजक्त में ईत्पादन कंपनी और एक लाआसेंसधारी िाजमल ह,ै जजसने ओपन एटससे का लाभ ईठाया ह ैया आरादा रखता ह;ै (31) “पठरयोजना जिकासकता”ा का ऄथ ा ह ै अरइ पठरयोजना का जिकासकताा, जो आस तरह की पठरयोजना को ऄपन े पठरसर म ेंया पट्टे या ककराए पर जलए गए पठरसर में जिकजसत करेंगे; (30) "प्रोज्यमू र" का ऄथा ह ैिह व्यजक्त जो जिड से जबजली का ईपभोग करता ह ैऔर अपूर्तत के ईसी लबद ुका ईपयोग करके जितरण लाआसेंसधारी के जलए जिड म ेंजबजली भी जितठरत कर सकता ह।ै (33) "पठरसर" का ऄथा ह ै कोइ भी क्षेत्र और आसमें छतों या भूजम, भिन या बुजनयादी ढांचे या ईसके जहस्ट्से या संयोजन भी िाजमल ह,ै जजसके संबंध म ें जितरण लाआसेंसधारी द्वारा जबजली की अपूर्तत के जलए एक ऄलग मीटर या मीटररग व्यिस्ट्था प्रदान की गइ ह।ै (34) "निीकरणीय उजा"ा का ऄथ ा ह,ै निीकरणीय उजाा स्रोतों से ईत्पन्न जिड से जड़ु ी और जिड गुणित्ता िाली जबजली जजसमें आस प्रकार के स्रोतों का संयोजन भी िाजमल ह;ै (35) "निीकरणीय उजा ाप्रमाणपत्र (अरइसी)" का ऄथ ा ह ैकेंद्रीय जिद्युत जनयामक अयोग द्वारा ऄनमु ोकदत जिजनयमों और प्रकक्रयाओं के ऄनुसार जारी ककया गया प्रमाण पत्र; (36) "निीकरणीय उजा ा ईत्पादन प्रणाली" का ऄथ ा ह ै निीकरणीय उजा ा जबजली प्रणाली जजसमें ईपभोक्ता के पठरसर म ें स्ट्थाजपत उजाा भडं ारण हो भी सकता ह ै या नहीं भी हो सकता, और ऐस े ईपभोक्ता या तीसरे पक्ष के स्ट्िाजमत्ि में होती ह ै और/या ईसके द्वारा संचाजलत की जाती है, जो जबजली म ें रूपांतरण के जलए निीकरणीय उजाा का ईपयोग करता ह;ै (37) "निीकरणीय उजा ा मीटर" का ऄथा ह ैलेखा और जबललग के ईद्देश्य के जलए अरइ पठरयोजना द्वारा ईत्पन्न सकल निीकरणीय उजा ाआकाआयों को मापने के जलए ईपयोग ककया जाने िाला मीटर; (38) "निीकरणीय उजा ा स्रोत" का ऄथ ा ह ै निीकरणीय स्रोत या ऐसे स्रोतों का संयोजन, जैसे कक जमनी, सूक्ष्म और लघ ु हाआड्रो, पिन, सौर, बायोमास जजसमें बायोगैस, जैि-ईंधन, िहरी या नगरपाजलका ठोस ऄपजिष्ट िाजमल ह,ैं जैसा कक अयोग द्वारा बनाए गए निीकरणीय उजाा स्रोत से टैठरफ जनधाारण के जलए जिजनयमन म ें पठरभाजषत जनयम और ितों में पठरभाजषत ककया गया ह ै और ऐसे ऄधय स्रोत जो निीन और निीकरणीय उजा ा मंत्रालय, भारत सरकार द्वारा माधयता प्राप्त या ऄनुमोकदत ह;ैं (39) "निीकरणीय उजा ा खरीद दाजयत्ि (अरपीओ)" का ऄथा ह ै अयोग द्वारा जनर्ददष्ट निीकरणीय उजाा खरीद दाजयत्ि; (40) "स्ट्िीकृत लोड" का ऄथा ह ै केडब्लल्य,ू केिीए या एचपी में लोड, जजसे लाआसेंसधारक समय-समय पर जितरण लाआसेंसधारी और ईपभोक्ता के बीच एक समझौते की ऄनुपजस्ट्थजत में िासी जनयमों और ितों के ऄधीन अपूर्तत करने के जलए सहमत होता ह;ै (41) "सम्झौता ऄिजध" का ऄथा ह ै ऄंिेजी कैलेंडर िषा के ऄनुसार 1 ऄप्रलै से िुरू होकर ऄगल े िषा 31 माचा तक ऄिजध; (42) "सौर जिड आधिटार" का ऄथ ा ह ै ऐसे ईपकरण जो डीसी (डायरेटट करंट) पािर को सोलर पािर मॉड्यलू स े जिड के ऄनुसार एसी (ऄल्टरनेरटग करंट) पािर में पठरिर्ततत करत ेहैं; (43) "राज्य नोडल एजसें ी" का ऄथ ा ह ै संबंजधत राज्य या केंद्र िाजसत प्रदेि म ें जस्ट्थत एजेंसी जजसे अयोग द्वारा माधयता के जलए एजेंसी के रूप में काया करने और पंजीकरण के जलए निीकरणीय उजाा पठरयोजनाओं की[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 5 जसफाठरि करने और ऐसे कायों को करन े के जलए नाजमत ककया जा सकता ह ै जैसा कक ऄजधजनयम की धारा 86 की ईप-धारा (1) के खडं (ड़) के तहत जनर्ददष्ट ककया जा सकता ह;ै (44) एक लाआसेंसधारी के संबंध में "टैठरफ अदेि" का ऄथ ा ह ै ईस लाआसेंसधारी के जलए अयोग द्वारा जारी ककया गया लागू खुदरा टैठरफ अदेि, जजसमें जिद्युत उजाा और सेिाओं की अपूर्तत के जलए ईपभोक्ताओं की जिजभन्न श्रेजणयों से लाआसेंसधारी द्वारा चाजा ककए जाने िाल ेटैठरफ को दिााया गया ह;ै (45) "ततृ ीय पक्ष के स्ट्िाजमत्ि" का ऄथा ह ै एक पठरयोजना डेिलपर के स्ट्िाजमत्ि िाली निीकरणीय उजाा प्रणाली पठरयोजना जो छत या पठरसर पर स्ट्थाजपत ह ै जैसा कक उपर 1(29) में पठरभाजषत ककया गया ह ै जजसके जलए प्रोजेटट डेिलपर द्वारा माजलक के साथ एक िाजणजज्यक पट्टा या राजस्ट्ि जहस्ट्सेदारी समझौता ककया गया है; (46) “िचऄुा ल नटे मीटररग" का ऄथ ा ह ै एक ऐसी व्यिस्ट्था जजसके द्वारा ईपभोक्ता पठरसर या ककसी ऄधय स्ट्थान पर स्ट्थाजपत निीकरणीय उजा ा ईत्पादन पठरयोजना स े ईत्पन्न संपणू ा उजा ा सौर उजाा मीटर के माध्यम स े आंजेटट की जाती ह।ै और जनयाात की गइ उजाा को एक ही जितरण लाआसेंसधारी के अपूर्तत क्षेत्र के भीतर जस्ट्थत प्रजतभागी ईपभोक्ता (ईपभोक्ताओं) के एक या एक स े ऄजधक जबजली सेिा कनेटिन (कनेटिनों) म ें समायोजजत ककया जाता ह;ै (47) "िष"ा या "जित्तीय िषा" का ऄथ ा ह ैएक ऄंिेजी कैलेंडर िष ा के 1 ऄप्रैल स े िुरू होन े िाली और ऄगल े कैलडें र िष ा के 31 माचा को समाप्त होन े िाली ऄिजध। 2.2. सजं क्षप्ताक्षर: आन जिजनयमों में जनम्नजलजखत की व्याख्या आस प्रकार की जाएगी: i. "इपीसी" का ऄथा ह ैआंजीजनयररग खरीद और जनमााण ठेकेदार द्वारा ऄजधकृत ह ैजितरण लाआससें धारी; ii. "केडबल्यपू ी" का ऄथ ाह ैककलो िाट पीक, सौर संयंत्र की रेरटग के रूप में आस्ट्तेमाल ककया जाने िाला िब्लद; iii. "एमएनअरइ" का ऄथा ह ैभारत सरकार का निीन और निीकरणीय उजा ामंत्रालय; 2.3 आन जिजनयमों में प्रयक्तु ऄधय सभी िब्लद और ऄजभव्यजक्तया यकद उपर जििेष रूप से पठरभाजषत नहीं हैं, लेककन ऄजधजनयम म ें पठरभाजषत ह,ैं ईनका िही ऄथा होगा जो ईधह ें ऄजधजनयम म ें कदया गया ह।ै यहां प्रयुक्त ऄधय िब्लद और ऄजभव्यजक्तयां लेककन आन जिजनयमों या ऄजधजनयम में जििेष रूप से पठरभाजषत नहीं हैं लेककन संसद द्वारा पाठरत ककसी ऄधय कानून में पठरभाजषत ह ैं जो राज्य या संघीय क्षेत्र में जबजली ईद्योग पर लागू हैं, का ऄथा ऐसे क़ानूनों के ऄनुसार होगा। 3. जिजनयमों का कायक्षा त्रे और प्रयोग की सीमा 3.1 ये जिजनयम आन पर लागू होंगे: क. सकल मीटररग व्यिस्ट्था ख. नेट जबललग (नेट फीड-आन) व्यिस्ट्था ग. िुप नेट मीटररग और िचुाऄल नटे मीटररग सजहत नेट-मीटररग व्यिस्ट्था बिते कक सकल मीटररग या नटे -जबललग या नेट-मीटररग व्यिस्ट्था, जैसा भी मामला हो पात्र ईपभोक्ताओं के जलए तकनीकी व्यिहायाता के ऄधीन ऄनुमजत दी जाएगी। बिते कक िुप नेट मीटररग फ्रेमिका सभी ईपभोक्ताओं पर लाग ू होगा, जबकक िचुाऄल नेट मीटररग फ्रेमिका अिासीय ईपभोक्ताओं, िुप हाईलसग सोसाआटी और सरकारी/स्ट्थानीय प्राजधकरणों के प्रजतष्ठानों पर लागू होगा। 3.2 ये जिजनयम सभी जिड आंटरएजटटि जितठरत निीकरणीय उजाा ईत्पादन जसस्ट्टम पर लागू होंगे जो आन जिजनयमों की ऄजधसूचना के बाद चालू ककए गए ह।ैं 4. पात्रता मानदडं 4.1 सभी श्रेजणयों के पात्र ईपभोक्ता 500 ककलोिाट क्षमता तक की नेट मीटररग व्यिस्ट्था के ऄतं गात निीकरणीय उजा ा ईत्पादन प्रणाली स्ट्थाजपत कर सकते ह:ैं6 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] बिते कक 500 ककलोिाट से ऄजधक रेरटग की निीकरणीय उजाा जनरेरटग प्रणाली पर जितरण लाआसेंसधारी द्वारा जिचार ककया जा सकता ह ै यकद ईच्च रेरटग िाली निीकरणीय उजाा पठरयोजना के साथ जितरण प्रणाली जस्ट्थर रहती ह ैऔर जिड से जुड़ जाती ह।ै 4.2 सभी श्रेजणयों के पात्र ईपभोक्ता 500 ककलोिाट से ऄजधक और ऄजधकतम 1 मेगािाट तक की नेट-जबललग व्यिस्ट्था के तहत निीकरणीय उजाा ईत्पादन प्रणाली स्ट्थाजपत कर सकत े ह।ैं 4.3 सभी श्रेजणयों के पात्र ईपभोक्ता सकल मीटररग व्यिस्ट्था ऄजधकतम 1 मगे ािाट निीकरणीय उजाा ईत्पादन प्रणाली स्ट्थाजपत कर सकत े ह।ैं बिते कक जितरण यूठटजलटीज नेट-जबललग या िॉस मीटररग के तहत 1 मगे ािाट से ऄजधक रेरटग की निीकरणीय उजा ा ईत्पादन प्रणाली को लोड फ्लो ऄध्ययन करने और यह सुजनजित करन े के बाद ऄनुमजत द े सकती ह ैं कक निीकरणीय उजाा ईत्पादन प्रणाजलयों की ऐसी ईच्च क्षमता की स्ट्थापना का जिड पर कोइ प्रजतकूल प्रभाि नहीं पड़ता ह।ै 4.4 बिते कक पात्र ईपभोक्ता या आन जिजनयमों में जनर्ददष्ट केिल एक व्यिस्ट्था ऄथाात नेट मीटररग या नेट-जबललग या सकल मीटररग व्यिस्ट्था का जिकल्प चनु सकता ह।ै 4.5 निीकरणीय उजा ा ईत्पादन प्रणाली का धयूनतम अकार 1 ककलोिाट होगा जजसे नेट मीटररग या नेट-जबललग या िॉस मीटररग व्यिस्ट्था के ऄंतगात स्ट्थाजपत ककया जा सकता ह।ै 4.6 िुप नेट मीटररग या िचुाऄल नटे मीटररग फ्रेमिका के तहत स्ट्थाजपत ककए जाने िाल े अरइ जनरेरटग जसस्ट्टम की क्षमता 5 ककलोिाट से कम और 500 ककलोिाट से ऄजधक नहीं होगी। 4.7 पात्र ईपभोक्ता के पठरसर में नेट मीटररग/िपु नेट मीटररग/िचुाऄल नेट मीटररग या नेट-जबललग या िॉस मीटररग व्यिस्ट्था के तहत स्ट्थाजपत की जाने िाली निीकरणीय उजा ा ईत्पादन प्रणाली की क्षमता, ईपभोक्ता के स्ट्िीकृत भार (ककलोिाट में) या ईपभोक्ता के ऄनुबंध की मांग (केिीए में), जो लाग ूहो से ऄजधक नहीं होगी। 4.8 जितरण लाआसेंसधारी के पास लंजबत बकाया िाले ईपभोक्ता आन जिजनयमों के तहत नेट मीटररग या िुद्ध जबललग या सकल मीटररग व्यिस्ट्था के जलए पात्र नहीं होंगे। 4.9 ईन पात्र ईपभोक्ताओं को िुप नेट मीटररग और िचुाऄल नेट मीटररग सजहत नेट-मीटररग या नेट-जबललग या िॉस मीटररग व्यिस्ट्था, जैसा भी मामला हो, की जितरण लाआसेंसधारी द्वारा ऄनुमजत गैर-भेदभािपूणा और जितरण रांसफामार-िार 'पहल े अओ, पहल े पाओ' के अधार पर होगी, जजधहोंने ऐस े जितरण लाआसेंसधारी के नेटिका स े जुड़ी एक निीकरणीय उजाा ईत्पादन प्रणाली को स्ट्थाजपत ककया ह ैया स्ट्थाजपत करन े का आरादा रखते ह;ैं बिते कक जितरण लाआसेंसधारी के नेटिका के साथ ऐसी प्रणाली का ऄंतर-संयोजन केंद्रीय जिद्युत प्राजधकरण (सीइए) (जितठरत ईत्पादन संसाधनों की कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम, 2013 म ें जनर्ददष्ट मानकों और मानदंडों के ऄनुसार या जैसा भजिष्य में जनर्ददष्ट ककया जा सकता है, के ऄनुसार ककया जाएगा। 5. तीसरे पक्ष के स्ट्िाजमत्ि िाली निीकरणीय उजा ाप्रणाली 5.1 तृतीय पक्ष के स्ट्िाजमत्ि िाली निीकरणीय उजाा प्रणाली म,ें जनम्नजलजखत ित ें लागू होंगी: क. ईपभोटत ा ककसी पठरयोजना जिकासकताा को िुप नेट मीटररग और िचुाऄल नेट मीटररग सजहत नेट-मीटररग या नेट जबललग या सकल जमटररग ढांचे के ऄंतगात निीकरणीय उजाा प्रणाली स्ट्थाजपत करने के जलए अपसी िाजणजज्यक सहमजत से रूफटॉप स्ट् पेस को पट्टे पर/ककराये पर दे सकता ह।ै ईपभोक्ता पठरयोजना डेिलपर को अपसी सहमजत के ऄनुसार निीकरणीय उजा ा जसस्ट्टम द्वारा ईत्पाकदत उजाा के जलए सभी टैठरफ का भुगतान करेगा। पठरयोजना जिकासकताा और प्रोज्यूमर के बीच की िाजणजज्यक व्यिस्ट्था ठरकॉडा के जलए लाआसेंसधारी को प्रस्ट्तुत की जाएगी और जितरण लाआसेंसधारी की ऐसे िाजणजज्यक व्यिस्ट्था में कोइ भूजमका नहीं होगी। नेट मीटररग या नेट जबललग या िॉस मीटररग फ्रेमिका के सभी प्रािधान एक पठरयोजना जिकासकताा द्वारा स्ट्थाजपत निीकरणीय उजा ाप्रणाली के जलए लाग ूहोंगे। ख. जितरण लाआसेंसधारी / नोडल एजेंसी ऄधय व्यिसाय मॉडल का पता लगा सकती ह ै जो जिड से जुड़ी निीकरणीय उजाा प्रणाली के प्रसार में सुजिधा प्रदान कर सकते ह ैं। आन जिजनयमों में नहीं कदये गए ककसी नए जबजनेस मॉडल के जलए अयोग आस संबंध म ेंदायर याजचका के अधार पर रूपरेखा को ऄनुमजत दगे ा।[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 7 6. जितरण रासं फामरा स्ट्तर पर क्षमता सीमाएं 6.1 जितरण लाआसेंसधारी आन जिजनयमों में जनर्ददष्ट पात्र ईपभोक्ताओं को सकल मीटररग/नेट जबललग/ िुप नेट मीटररग और िचुाऄल नेट मीटररग सजहत नेट-मीटररग व्यिस्ट्था की ऄनुमजत देगा, जो भी मामला हो। 6.2 नेट मीटररग, िुप नेट मीटररग, िचुाऄल नेट मीटररग व्यिस्ट्था, और/या लाआसेंसधारी के जििेष जितरण रांसफामार/ फीडर से जड़ु े नेट जबललग व्यिस्ट्था के तहत सभी निीकरणीय उजाा ईत्पादन प्रणाजलयों की संचयी क्षमता को ईसकी जनधााठरत क्षमता के 100% तक की ऄनुमजत दी जाएगी। 6.3 जितरण लाआसेंसधारी प्रत्येक जितरण रांसफामार के जलए निीकरणीय उजा ा प्रणाली को जोड़ने के जलए ईपलब्लध जितरण रांसफामार क्षमता को िार्तषक अधार पर ऄद्यतन करेगा और ऄपनी िेबसाआट के साथ-साथ अयोग को भी जानकारी प्रदान करेगा। 6.4 जितरण लाआसेंसधारी को जनयजमत अधार पर डीटी की क्षमता सीमा की जनगरानी करनी चाजहए और डीटी क्षमता ऄपनी 100% की सीमा तक पहुचं ने के बाद नए अरइ जसस्ट्टम कनेटिन या व्यिस्ट्था को कनेटट करन े से माना कर देना चाजहए। 7. मीटररग व्यिस्ट्था 7.1 मीटररग प्रणाली समय-समय पर संिोजधत केधद्रीय जिद्युत प्राजधकरण (मीटर स्ट्थापना और सचं ालन) जिजनयम, 2006 के ऄनुसार होगी। 7.2 सभी मीटरों में 485 रुपय े (या ऄजधक) के संचार पोटा या ककसी ऄधय ईन्नत संचार सुजिधा के साथ मीटररग आंफ्रास्ट्रटचर (एएमअइ) की सुजिधा होगी। 7.3 निीकरणीय उजा ा प्रणाली के चालू होन े स े पहल े मौजूद ईपभोक्ता के मीटर के समान सटीकता िग ा के नेट मीटर को मौजूदा मीटर के स्ट्थान पर स्ट्थाजपत ककया जाएगा: बिते कक, यकद प्रोज्यूमर टाआम-ऑफ-डे ('टीओडी') टैठरफ के दायरे म ें ह,ै तो नेट मीटर स्ट्थाजपत टीओडी खपत और ईत्पादन को ठरकॉड ाकरन े में सक्षम होगा: परंत ु बित े कक ऐसे मीटर अपर्तू तकतााओं की ऄनुमोकदत सूची से ईसी के ऄधीन जितरण लाआसेंसधारी या ईपभोक्ता द्वारा ईपलब्लध कराए जा सकत े ह:ैं परधत ु बित े कक यकद जितरण लाआसेंसधारी द्वारा मीटर स्ट्थाजपत ककया जाता ह ै तो ईसकी लागत की िसूली पठरयोजना के सीओडी से पहल ेईपभोक्ता से की जायेगी । 7.4 निीकरणीय उजाा मीटर (एक यूजनडायरेटिनल मीटर) को नटे मीटररग या नेट जबललग या िॉस मीटररग व्यिस्ट्था के ऄजभन्न ऄगं के रूप में ईस जबधद ुपर स्ट्थाजपत ककया जाना है, जैसा भी मामला हो, जजस लबद ु पर जबजली निीकरणीय उजाा प्रणाली द्वारा ईत्पन्न होती ह ैऔर मख्ु य पैनल को दी जाती ह।ै निीकरणीय उजाा मीटर में मीटर रीलडग ईपकरण (एमअरअइ) या िायरलेस ईपकरण का ईपयोग करके मीटर रीलडग ठरकॉडा करने की सुजिधा होगी। 7.5 20 ककलोिाट से ऄजधक क्षमता िाली निीकरणीय उजाा प्रणाली के जलए चेक मीटर ऄजनिाया होंगे। चेक मीटर 20 ककलोिाट से कम या ईसके बराबर क्षमता िाले प्रजतष्ठानों के जलए िैकजल्पक होंग:े बिते कक चेक मीटर की लागत ईपभोक्ता द्वारा िहन की जाएगी और ऐस े मीटर का परीक्षण जितरण लाआसेंसधारी द्वारा ककया जाएगा और स्ट्थाजपत ककया जाएगा। 7.6 जितरण लाआसेंसधारी मीटररग ईपकरण / प्रणाली की स्ट्थापना, परीक्षण और रखरखाि के जलए जजम्मेदार होगा और लाग ूमानकों और जिजिष्टताओं का पालन करेगा। 7.7 स्ट्थाजपत मीटर, यकद ईपभोक्ता द्वारा व्यिस्ट्था की जाती ह,ै का जनरीक्षण जितरण लाआसेंसधारी द्वारा ककया जाएगा, सटीकता के जलए सत्याजपत ककया जाएगा और ईपभोक्ता या ईसके प्रजतजनजध की ईपजस्ट्थजत में सीलबंद (यकद िह परीक्षण के समय ईपजस्ट्थत होता ह)ै ककया जाएगा। 7.8 स्ट्थाजपत मीटरों का दोनों पक्षों की और से संयुक्त रूप से जनरीक्षण ककया जाएगा और सील ककया जाएगा और केिल ईपभोक्ता और जितरण लाआसेंसधारी के प्रजतजनजधयों की ईपजस्ट्थजत म ेंपरीक्षण या जांच की जाएगी। बिते कक प्रोज्यूमर लाआसेंसधारी द्वारा समय-समय पर ईपलब्लध कराए गए मीटररग जिजनदेिों और मीटर प्लेसमेंट के प्रािधानों का पालन करेगा।8 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 7.9 जितरण लाआसेंसधारी द्वारा ली गइ मीटर रीलडग िाजणजज्यक समझौते का अधार होगी। 8. जितरण नटे िका, मानकों और सरु क्षा के साथ ऄतं सबं धं 8.1 जितरण लाआसेंसधारी यह सुजनजित करेगा कक निीकरणीय उजाा प्रणाली का जितरण नेटिका के साथ ऄंतर-संयोजन सीइए म ें (जितठरत ईत्पादन ससं ाधनों की कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम, 2013, सीइए (जिड स े कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम, 2007, सीइए (सुरक्षा और जिद्युत अपूर्तत से संबंजधत ईपाय) जिजनयम, 2010, जजसमें संिोधन िाजमल ह,ैं और जिद्युत अपूर्तत संजहता जिजनयमों और अयोग द्वारा बनाए गए राज्य जिड कोड जिजनयम में जनर्ददष्ट जिजनदेिों, मानकों और ऄधय प्रािधानों के ऄनरूु प ह ै। 8.2 िुप नेट मीटररग और िचुाऄल नेट मीटररग सजहत नेट मीटररग या नेट जबललग या िॉस मीटररग व्यिस्ट्था के साथ निीकरणीय उजा ा ईत्पादन की ऄनुमजत बैटरी बैक-ऄप के साथ/जबना अयोग के क्षेत्राजधकार म ें जितरण लाआसेंसधारी के सभी पात्र ईपभोक्ताओं को दी जानी चाजहए; बिते कक, यकद कोइ पात्र ईपभोक्ता बैटरी बैक-ऄप के साथ कनेजटटजिटी का जिकल्प चुनता ह,ै तो आधिटार म ें बैटरी/जिकेंद्रीकृत ईत्पादन (डीजी) को जिड अपूर्तत के ऄभाि में जिड म ें प्रिाजहत होने िाली जबजली को रोकने के जलए एक ऄलग बैक-ऄप िायररग होगी, और यह कक एक स्ट्िचाजलत के साथ-साथ मैनऄु ल अआसोलिे न जस्ट्िच भी ईपलब्लध कराया जाएगा। बिते कक आधिटरा म ेंऄनलु गनक I जनधााठरत मानकों का पालन करेगा: 8.3 नेट मीटर तक निीकरणीय उजाा प्रणाली में ककसी भी दोष के सुरजक्षत संचालन, रखरखाि और सुधार के जलए प्रोज्यूमर जजम्मेदार होगा, जजसके बाद नेट मीटर के संबंध में ऐसी जजम्मेदारी जितरण लाआसेंसधारी की होगी। : बिते कक निीकरणीय उजा ामीटर जितरण लाआसेंसधारी द्वारा ऄनुरजक्षत ककया जाएगा। बिते कक दोषपूण ा नेट मीटर या निीकरणीय उजा ा मीटर के प्रजतस्ट्थापन के मामल े में, यह प्रोज्यूमर द्वारा प्रदान ककया जाएगा, जैसा कक उपर जिजनयम 7.3 के प्रािधान म ें ईजल्लजखत ह ै और ईपरोक्त जिजनयम 7.1 में ईजल्लजखत प्रासंजगक जनयमों के ऄनुसार स्ट्थाजपत ककया जाएगा। 8.4 ऄजभयोक्ता जिड या अपूर्तत की जिफलता की जस्ट्थजत म ें जितरण लाआसेंसधारी के नेटिका स े निीकरणीय उजाा प्रणाली में अआलांलडग के जलए ईपयुक्त सुरक्षा प्रदान करेगा। 8.5 जिड की अपूर्तत बंद होन े पर निीकरणीय उजाा प्रणाली से बैक फीलडग के कारण होन े िाली ककसी भी दघु ाटना (घातक/गैर-घातक/जिभागीय/गरै -जिभागीय) के जलए प्रोज्यूमर पूरी तरह से जजम्मेदार होगा: बिते कक आस तरह की पठरयोजना से आसकी जितरण प्रणाली को ककसी भी तरह की दघु ाटना या क्षजत के खतरे की जस्ट्थजत म ें जितरण लाआसेंसधारी को ककसी भी समय ऄपन े जितरण नेटिका से निीकरणीय उजाा प्रणाली को जडस्ट्कनेटट करने का ऄजधकार होगा ताकक ककसी भी तरह से दघु ाटना या ईसे नुकसान बचा जा सके। बिते यह भी कक ईपभोक्ता ऄपने स्ट्िय ं के ईपभोग के जलए ऄपनी निीकरणीय उजाा प्रणाली का ईपयोग अआलैंलडग मोड में कर सकता ह।ै 8.6 जितरण लाआसेंसधारी और प्रोज्यूमर ऄपन े संबंजधत कताव्यों और जजम्मेदाठरयों का जनिाहन करेंगे जैसा कक केंद्रीय जिद्युत प्राजधकरण के प्रासंजगक जिजनयमों में जनर्ददष्ट ह।ै 8.7 नेट मीटररग का जिकल्प चनु न े िाले एचटी ईपभोक्ताओं को एलटी स्ट्तर पर खपत के जलए एचटी िोल्टेज स्ट्तर पर निीकरणीय उजा ाप्रणाली के जलए ऄलग से कनेजटटजिटी प्रदान करने की अिश्यकता नहीं होगी। 9 सचं ार सजु िधाएं 9.1 सभी जिड आंटरएजटटि निीकरणीय उजाा प्रणाली में आन जिजनयमों के तहत प्रदान ककए गए उजाा मीटर के माध्यम स े जिड म ेंआंजेटिन के जलए डेटा भंडारण के जलए उजाा ठरकॉड ाकरने की सुजिधाओं िाले जबजली मीटर होंग:े बिते कक सभी पठरयोजनाओं म ेंजितरण लाआसेंसधारी के साथ िास्ट्तजिक समय की जानकारी के अदान-प्रदान के जलए संचार पोटा होगा: बिते यह भी कक सभी मीटरों में एडिांस मीटररग आंफ्रास्ट्रटचर (एएमअइ) सुजिधा होगी।[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 9 10 जबललग, उजा ालखे ा और जनपटान 10.1 नटे मीटररग व्यिस्ट्था क. निीकरणीय उजाा प्रणाली स े जनयाात की गइ और प्रोज्यूमर द्वारा जिड स े अयात की गइ जबजली का लेखा, जितरण नेटिका के साथ निीकरणीय उजा ाप्रणाली की कनेजटटजिटी की तारीख से प्रभािी हो जाएगा। ख. जितरण लाआसेंसधारी, सभी ईपभोक्ताओं के जलए, जनयजमत जबललग चक्र के ऄनुसार, निीकरणीय उजा ा ईत्पादन मीटर और नेट मीटर दोनों की मीटर रीलडग दज ाकरेगा। ग. प्रत्येक जबललग ऄिजध के जलए, जितरण लाआसेंसधारी जनम्न को ऄलग स ेकदखाएगा: - i. जबललग ऄिजध म ें निीकरणीय उजाा ईत्पादन मीटर म ें दजा निीकरणीय उजाा ईत्पादन की मात्रा, जजसमें प्रारंजभक और ऄंजतम िषे िाजमल ह ै ii. प्रारंजभक और िेष सजहत, प्रोज्यूमर द्वारा जनयाात की गइ जबजली आकाआयों की मात्रा; iii. प्रारंजभक और ऄंजतम िषे सजहत, प्रोज्यूमर द्वारा अयाजतत जबजली आकाआयों की मात्रा; iv. ईपभोक्ता द्वारा भुगतान के जलए जबल की गइ जबजली आकाआयों की िुद्ध मात्रा; तथा v. ऄगली जबललग ऄिजध में लाइ गइ जबजली आकाआयों की िुद्ध मात्रा (यकद ऄजधिषे ह)ै ; vi. अरपीओ ऄनपु ालन के जलए जितरण लाआसेंसधारी द्वारा निीकरणीय उजाा ईत्पादन स े ईपयोग की जान े िाली आकाआयां। घ. निीकरणीय उजाा ईत्पादन स्ट्टेिन द्वारा ईत्पन्न उजाा को जितरण लाआसेंसधारी से ईपभोक्ता की उजाा खपत के जिरुद्ध जनम्नजलजखत तरीके से ऑफसेट ककया जाएगा: i. यकद जनयाात की गइ जबजली की मात्रा जबललग ऄिजध के दौरान अयाजतत मात्रा से ऄजधक है, तो ऄजतठरक्त मात्रा को जबजली की क्रेजडट यूजनट के रूप म ेंऄगली जबललग ऄिजध के जलए अगे बढाया जाएगा; ii. यकद ककसी जबललग ऄिजध के दौरान ईपभोक्ता द्वारा अयात की गइ जबजली आकाआयों की मात्रा जनयाात की गइ मात्रा से ऄजधक ह,ै तो जितरण लाआसेंसधारी लागू टैठरफ अदेि के ऄनुसार क्रेजडट की गइ आकाआयों को समायोजजत करने के बाद िुद्ध जबजली खपत के जलए ऄपना जबल प्रदान करेगा। iii. यकद प्रोज्यूमर टाआम ऑफ डे (टीओडी) टैठरफ के दायरे में है, तो ककसी भी समय ब्ललॉक में जबजली की खपत, ऄथाात पीक ऑिसा, ऑफ-पीक ऑिसा अकद को पहले जबजली की मात्रा की भरपाइ की जाएगी। iv. बिते कक जबललग चक्र में ककसी ऄधय टाआम ब्ललॉक म ें खपत के उपर और ऄजधक आंजेटिन का जहसाब लगाया जाएगा यह मानत ेहुए की ऄजतठरक्त आंजेटिन ऑफ-पीक घंटों के दौरान हुअ ह ै। ङ. प्रत्येक जित्तीय िषा के ऄंत म ें जबजली की ऄसमायोजजत जनिल क्रेजडट यूजनटों को जितरण लाआसेंसधारी द्वारा संबंजधत जितरण लाआसेंसधारी की औसत जबजली खरीद लागत या ईस िष ा के जलए जनधााठरत फीड-आन-टैठरफ, जो भी कम हो, पर खरीदी गइ आकाआयों के रूप में माना जाएगा। बिते कक, प्रत्येक जनपटान ऄिजध की िरुु अत म,ें अग े ल े जाने िाली ऄंतःक्षेजपत जबजली की सचं यी मात्रा को िूधय पर कफर से सेट ककया जाएगा। च. जितरण लाआसेधसधारी जिजनयम 10.1(ड़) म ें जिजनर्ददष्ट जित्तीय िषा के दौरान ईसके द्वारा खरीदी गइ ऄसमायोजजत जनिल जमा आकाआयों के जलए ऄगल े िष ा की 30 ऄप्रलै तक देय राजि की गणना करेगा और ऄगल े िषा 31 मइ तक पात्र ईपभोक्ता को राजि का भगु तान करेगा। छ. ईपभोक्ता िल्ु क के ऄजतठरक्त जितरण लाआसेंसधारी को अयोग द्वारा ऄनुमत ककसी ऄधय पात्र िल्ु क और सरकार द्वारा लगाए गए ककसी भी कर/िुल्क/ईपकर के जलए जबल सर्तजत ककया जाएगा। ज. जजस ईपभोक्ता का लाआसेंस के ईपभोक्ता के रूप म ें ऄजधकार समाप्त हो जाता ह ै या िह लाआसेंसधारी को ऄपनी बकाया राजि का भुगतान नहीं कर रहा है, िह समायोजन/क्रेजडट की देय राजि प्राप्त करने का हकदार नहीं होगा।10 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] झ. जबललग के संबंध म ें जितरण लाआसेंसधारी के साथ ककसी भी जििाद के मामल े म ें प्रोज्यूमर जिकायत के जनिारण के जलए ऄजधजनयम की धारा 42 (5) से (7) के तहत अयोग द्वारा जनर्ददष्ट तंत्र का सहारा लगे ा। 10.2 िपु नटे मीटररग के मामल ेम,ें जबललग और उजा ालखे ाकं न के साथ जनम्नानसु ार व्यिहार ककया जाएगा: क. जहां ककसी जबललग ऄिजध के दौरान आकाआयों का जनयाात ईस कनेटिन पर आकाआयों के अयात स े ऄजधक हो जाता ह ै जहां निीकरणीय उजाा ईत्पादन पठरयोजना जस्ट्थत ह,ै जिड म ें आंजेटट की गइ ऐसी ऄजधिेष आकाआयों को ईपभोक्ता द्वारा प्रदान की गइ प्राथजमकता सूची म ें दिााए गए क्रम में सेिा कनटे िन (कनेटिनों) के माजसक जबल म ें खपत उजाा के जिरुद्ध समायोजजत ककया जाए। समायोजन के जलए प्राथजमकता का क्रम सेिा कनेटिन के साथ िुरू हुअ माना जाए जहां निीकरणीय उजाा ईत्पादन पठरयोजना जस्ट्थत ह;ै ख. ईपभोक्ता द्वारा प्रत्येक जित्तीय िषा की िरुु अत म ें एक बार दो महीने की ऄजिम सूचना के साथ िषे ऄजधिेष उजाा के समायोजन के जलए प्राथजमकता सूची को ऄधय जबजली कनेटिन (नों) के जिरुद्ध संिोजधत ककया जा सकता है; ग. ककसी भी समय ब्ललॉक (जैसे व्यस्ट्ततम समय, गैर व्यस्ट्ततम समय अकद) में जबजली की खपत की भरपाइ पहले ईपभोक्ता के ईसी जबललग चक्र में समान समय ब्ललॉकों में जबजली ईत्पादन से की जाएगी जहां निीकरणीय उजा ा ईत्पादन पठरयोजना जस्ट्थत ह,ै और आंजेटट की गइ कोइ भी ऄजतठरक्त यूजनट ईपभोक्ता द्वारा प्रदान की गइ प्राथजमकता सूची में दिााए गए क्रम म ें सेिा कनेटिन (नों) के माजसक जबल में खपत की गइ उजाा के जिरुद्ध समायोजजत की जाएगी, जैसे कक कदन के समय (टीओडी) ईपभोक्ताओं के जलए गैर व्यस्ट्ततम समय ब्ललॉक और गैर- टीओडी ईपभोक्ता के जलए सामाधय समय ब्ललॉक के दौरान ऄजधिेष ईत्पादन/उजाा क्रेजडट हुअ; घ. जहां ककसी भी जबललग ऄिजध के दौरान, गैर-टीओडी टैठरफ या टीओडी टैठरफ में आकाआयों का जनयाात जबजली सेिा कनेटिन (नों) द्वारा आकाआयों के अयात से ऄजधक ह,ै ईपभोक्ता द्वारा आंजेटट की गइ ऐसी ऄजधिेष आकाआयों को ऄगली जबललग ऄिजध के जलए उजाा क्रेजडट के रूप में अग े बढाया जाए और िरीयता सूची में दिााए गए क्रम म ें जनपटान ऄिजध के भीतर बाद की जबललग ऄिजधयों म ें खपत उजाा के जिरुद्ध समायोजन के जलए ईपभोक्ता द्वारा जनयाात की गइ उजाा के रूप में कदखाया जाए; ङ. प्रत्येक जित्तीय िषा के ऄंत म ें जबजली की ऄसमायोजजत जनिल क्रेजडटेड आकाआयों के जलए खंड 10.1 (ड) के प्रािधान ईस कनेटिन के जलए लाग ूहोंगे जहा ंनिीकरणीय उजाा ईत्पादन पठरयोजना जस्ट्थत ह।ै 10.3 िचऄुा ल नटे मीटररग के मामल ेमें, जबललग और उजा ालखे ाकं न को जनम्नानसु ार जनपटाया जाएगा: क. निीकरणीय उजाा ईत्पादन पठरयोजना स े ईत्पन्न उजा ा को प्रत्येक सहभागी ईपभोक्ता (ईपभोक्ताओं) के माजसक जिद्युत जबल में निीकरणीय उजाा ईत्पादन पठरयोजना से ईपाजान के ऄनुपात के ऄनुसार ईपभोक्ता (ओं) द्वारा स्ट्टाम्प पेपर पर ककए गए करार/एमओयू के ऄतं गता दिााए गए तथा जितरण ऄनुज्ञजप्तधारी को प्रस्ट्तुत ककए गए ऄनुपात में जमा ककया जाए; ख. ईपभोक्ता (ओं) के पास दो महीने की ऄजिम सूचना के साथ जित्तीय िषा की िुरुअत में एक बार ईपभोक्ता (ओं) द्वारा ककए गए समझौते/एमओयू के तहत आंजगत निीकरणीय उजाा ईत्पादन पठरयोजना से; खरीद के ऄनुपात के ऄधीन स्ट्टाम्प पेपर पर एक नया समझौता/एमओयू जमा करके निीकरणीय उजाा ईत्पादन पठरयोजना से जबजली के क्रेजडट के जहस्ट्स ेको बदलने का जिकल्प होगा। ग. जहां ककसी भी समय लाग ू ककसी भी कानून के तहत ककसी भी कारण स े ककसी भी भाग लेन े िाले ईपभोक्ता (ओं) का सेिा कनेटिन काट कदया जाता ह,ै ईस ईपभोक्ता(ओं) की ऄसमायोजजत आकाआयों/िषे क्रेजडट का भुगतान जितरण लाआसेंसधारी द्वारा जित्तीय िषा के ऄतं म ेंककया जाएगा; घ. ककसी भी समय ब्ललॉक (जैसे व्यस्ट्ततम समय, गैर व्यस्ट्ततम समय अकद) में जबजली की खपत की भरपाइ पहले सहभागी ईपभोक्ता ((ओं)) के समान जबललग चक्र में समान समय ब्ललॉकों में जबजली ईत्पादन से की जाएगी। ककसी जबललग चक्र म ें ककसी भी समय ब्ललॉक म ें खपत स े ऄजधक ईत्पादन का जहसाब आस तरह लगाया जाएगा जैस े कक ऄजधिेष ईत्पादन/उजाा क्रेजडट गैर व्यस्ट्ततम समय ब्ललॉक के दौरान हुअ हो; ङ. जहां ककसी भाग लेन े िाले ईपभोक्ता (ओं) की ककसी जबललग ऄिजध के दौरान जमा की गइ आकाआयां ईस ईपभोक्ता(ओं) द्वारा आकाआयों के अयात से ऄजधक हो जाती हैं, ऐसी ऄजधिेष जमा की गइ आकाआयों को ऄगल े जबललग ऄिजध में उजाा क्रेजडट के रूप में अगे ले जाया जाएगा ताकक प्रत्येक भाग लने े िाले ईपभोक्ता (ओं) की जनपटान ऄिजध के भीतर बाद की जबललग ऄिजधयों में खपत की गइ उजाा के जिरुद्ध समायोजन ककया जा सके;[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 11 च. प्रत्येक जित्तीय िषा के ऄंत म ें जबजली की ऄसमायोजजत जनिल जमा आकाआयों के जलए, खंड 10.1 (ड) के प्रािधान प्रत्येक भाग लेन े िाले ईपभोक्ता (ओं) के जलए लाग ूहोंगे। 10.4 िद्धु जबललग व्यिस्ट्था क. नेट जबललग िह व्यिस्ट्था ह ैजहां निीकरणीय उजाा ईत्पादन प्रणाली: i. नेट मीटर के ईपभोक्ता पक्ष से जुड़ी ह,ै ii. अयोग द्वारा ऄनुमोकदत फीड-आन टैठरफ पर जितरण लाआसेंसधारी को ऄपनी अिश्यकता (जबजली का जनयाात) को परू ा करने के बाद ऄजतठरक्त जबजली की जबक्री की जाती ह:ै iii. जबजली का अयात, यकद कोइ हो, जितरण लाआसेंसधारी से लागू टैठरफ अदिे के ऄनुसार प्रभाठरत ककया जाएगा। ख. जितरण लाआसेधसधारी जबललग चक्र के ऄनुसार निीकरणीय उजाा ईत्पादन मीटर और नेट मीटर, दोनों की, जो भी लाग ूहो, जनयजमत रूप से मीटर रीलडग करेगा। ग. जितरण लाआसेंसधारी पात्र ईपभोक्ता को प्रत्येक जबललग ऄिजध के जलए ऄपने जबल पर जनम्नजलजखत जानकारी ईपलब्लध कराएगा: i. निीकरणीय उजाा ईत्पादन मीटर में दजा निीकरणीय उजाा ईत्पादन की मात्रा, जजसमें प्रारजम्भक और ऄंजतम िषे िाजमल ह;ै ii. जबललग ऄिजध में प्रोज्यूमर द्वारा जिड को जनयाात की गइ जबजली आकाआयों की मात्रा, जजसमें प्रारजम्भक और ऄंजतम िेष िाजमल ह;ै iii. जबललग ऄिजध में प्रोज्यूमर द्वारा जिड से अयात की गइ जबजली आकाआयों की मात्रा, जजसमें प्रारजम्भक और ऄंजतम िेष िाजमल ह;ै iv. जबललग ऄिजध में जबललग क्रेजडट की राजि, यकद कोइ हो, प्रारंजभक और ऄंजतम िेष सजहत; v. अरपीओ ऄनुपालन के जलए जितरण लाआसेंसधारी द्वारा ईपयोग की जाने िाली निीकरणीय उजा ा ईत्पादन से आकाआयां। घ. जितरण लाआसेंसधारी, अयोग द्वारा ऄनुमोकदत फीड-आन टैठरफ पर निीकरणीय उजाा जिकासकताा द्वारा जनयाात की गइ आकाआयों के जलए लेखांकन के बाद और लाग ू टैठरफ अदेि पर जिड से अयाजतत आकाआयों के जलए लेखांकन के बाद जबललग चक्र के ऄनुसार िुद्ध जबल तैयार करेगा। ङ. जितरण लाआसेंसधारी जनम्नजलजखत समीकरण के ऄनुसार ईपभोक्ता को जबल प्रस्ट्तुत करेगा: ईपभोक्ता का जबजली जबल = स्ट्थायी िल्ु क + ऄधय लाग ू िल्ु क और प्रिल्ु क + (𝐄𝐃𝐋x 𝐓𝐑𝐒𝐓) - (𝐄𝐑𝐄 * 𝐓𝐏𝐏𝐀) - जबललग क्रेजडट (जपछल ेजबललग चक्र स ेअग ेल ेजाया गया); जहा:ं i. स्ट्थायी िल्ु क का ऄथा ह ै कफटस्ट्ड / जडमांड चाजा, जैसा कक लागू ठरटेल सप्लाइ टैठरफ ऑडार के ऄनुसार ईपभोक्ता श्रेणी पर लागू होता ह;ै ii. ऄधय लाग ूिल्ु क और लेिी का ऄथ ाह ैकोइ ऄधय िल्ु क जैसे ड्यटू ी, ईपकर, अकद; iii. 𝐄𝐃𝐋 का ऄथ ा ह ै जितरण लाआसेंसधारी से अयाजतत उजा ा आकाआया , जैसा कक जबललग ऄिजध के जलए जद्वकदि मीटर म ेंदजा ककया गया ह ै iv. 𝐓𝐑𝐒𝐓 का ऄथा ह ै अयोग के लाग ू टैठरफ अदेि के ऄनुसार संबंजधत ईपभोक्ता श्रणे ी का लाग ू ठरटेल अपूर्तत िुल्क; v. 𝐄𝐑𝐄 का ऄथा ह ैजद्वकदि मीटर द्वारा जबललग ऄिजध के जलए ठरकॉडा की गइ जनयाात उजा ाआकाआयां; vi. 𝐓𝐏𝐏𝐀 का ऄथ ा ह ै ईपभोक्ता और जितरण लाआसेंसधारी के बीच जिजनयम 16 के ऄनुसार ककए गए समझौते के ऄनुसार अयोग द्वारा ऄनुमोकदत फीड-आन टैठरफ;12 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] vii. जबललग क्रेजडट िह राजि ह ै जजसके द्वारा ककसी जििेष महीने में जनयााजतत निीकरणीय उजाा ईत्पादन का मूल्य ईपभोक्ता जबल के ऄधय सभी घटकों सजहत जितरण लाआसेंसधारी से अयाजतत आकाआयों के मूल्य स े ऄजधक ह।ै च. यकद ईपभोक्ता समय-समय पर टैठरफ के ऄधीन ह,ै तो उजाा जबल (𝐄𝐃𝐋 x 𝐓 𝐒𝐓) की गणना तदनुसार की जाएगी। छ. यकद (𝐄𝐑𝐄 * 𝐓𝐏𝐏) {कफटस्ट्ड चाजा + ऄधय लागू िुल्क और लेिी + ((𝐄𝐃𝐋 x 𝐓𝐑𝐒𝐓)} से ऄजधक ह,ै तो यूठटजलटी ऄंतर (जबललग क्रेजडट) के बराबर राजि का क्रेजडट दगे ी, जजसे ऄगल े जबललग चक्र म ें जोड़ा जाएगा। जितरण लाआसेंसधारी द्वारा अगे लाइ गइ ऐसी क्रेजडट राजि पर कोइ ब्लयाज देय नहीं होगा। ज. जबललग ऄिजध के जलए जनिल जबल राजि, यकद प्रोज्यूमर द्वारा देय ह,ै तो ईसका भुगतान जबल की जनयत तारीख के ऄदं र प्रोज्यूमर द्वारा ककया जाएगा। झ. प्रत्येक जित्तीय िषा के ऄंत म,ें जितरण लाआसेंसधारी द्वारा जित्तीय िषा के दौरान देय ऄसमायोजजत िेष रहन े िाली ककसी भी राजि का भुगतान प्रोज्यूमर को ऄगल े जित्तीय के मइ के ऄंत तक निीनतम रूप से ककया जाएगा ञ. जजस ईपभोक्ता का लाआसेंसधारक के ईपभोक्ता के रूप में ऄजधकार समाप्त हो गया ह ै या िह लाआसेंसधारी के साथ ऄपनी बकाया राजि का जनपटान नहीं कर रहा ह,ै तो िह समायोजन/क्रेजडट की देय राजि प्राप्त करने का हकदार नहीं होगा। ट. यकद जितरण लाआसेंसधारी के साथ जबललग के संबंध म ें कोइ जििाद ह ै तो ईपभोक्ता को ऄजधजनयम की धारा 42 (5) से (7) के ऄंतगात अयोग द्वारा जिकायत जनिारण के जलए जनर्ददष्ट तंत्र का सहारा लेना होगा। 10.5 सकल मीटररग व्यिस्ट्था क जितरण लाआसेंसधारी जनयजमत जबललग चक्र के ऄनुसार सभी ईपभोक्ताओं के जलए निीकरणीय उजा ा ईत्पादन मीटर और ईपभोक्ता मीटर दोनों की मीटर रीलडग करेगा। ख प्रत्येक जबललग ऄिजध के जलए, जितरण लाआसेंसधारी ऄपन े जबल पर जनम्नजलजखत जानकारी ऄजभयोक्ता को ईपलब्लध कराएगा: i. निीकरणीय उजाा ईत्पादन मीटर म ें दज ानिीकरणीय उजा ा ईत्पादन की मात्रा, जजसमें प्रारजम्भक और ऄंजतम िेष िाजमल ह;ै ii. जबललग ऄिजध में प्रोज्यूमर द्वारा जिड से खपत की गइ जबजली यूजनटों की मात्रा, जजसमें ओपलनग और टलोलजग बलै ेंस िाजमल ह;ै iii. अरपीओ ऄनुपालन के जलए जितरण लाआसेंसधारी द्वारा ईपयोग की जान े िाली निीकरणीय उजाा ईत्पादन से आकाआयां ग सकल मीटररग व्यिस्ट्था के तहत निीकरणीय उजाा प्रणाली स्ट्थाजपत करने और संचाजलत करने िाले ईपभोक्ताओं के जलए उजाा लेखांकन और समझौता प्रकक्रया जनम्नजलजखत प्रकक्रया के ऄनुसार होगी: i. प्रत्येक जबललग ऄिजध के जलए, लाआसेंसधारक को जबललग ऄिजध में प्रोज्यूमर के पठरसर में स्ट्थाजपत निीकरणीय उजा ाप्रणाली द्वारा आंजेटट की गइ जबजली की मात्रा को कदखाना होगा। ii. जितरण लाआसेंसधारी ईस िष ा के जलए अयोग द्वारा जनधााठरत फीड-आन-टैठरफ पर जबललग ऄिजध के दौरान निीकरणीय उजाा प्रणाली द्वारा आंजेटटेड जबजली की मात्रा के जलए ऄजभयोजक को प्रजतपूर्तत करेगा। बित े कक, ईपरोक्त टैठरफ समझौते की पूरी ऄिजध के जलए लागू होगा। iii. प्रत्येक जबललग ऄिजध के जलए, लाआसेंसधारी को जबललग ऄिजध में प्रोज्यूमर द्वारा जिड से खपत की गइ जबजली की मात्रा दिाानी होगी। iv. जितरण लाआसेंसधारी अयोग द्वारा ऄनुमोकदत टैठरफ अदेि के ऄनुसार जिड से खपत उजाा के जलए जबल तैयार करेगा जजसमें लागू टैठरफ अदेि के ऄनुसार ईपभोक्ता श्रेणी पर लाग ू होने िाल े स्ट्थायी िुल्क/मागं िुल्क और ऄधय लाग ूिल्ु क और लेिी िाजमल ह;ैं[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 13 v. जितरण लाआसेंसधारी, लाआसेंसधारी द्वारा प्रोज्यूमर को देय राजि तथा जिड से ईपभोग की गइ उजा ा और प्रोज्यूमर द्वारा लाआसेंसधारी को देय राजि के ऄनुसार िुद्ध जबल तैयार करेगा। vi. लाआसेंसधारी या प्रोज्यूमर द्वारा देय िुद्ध राजि, जैसा भी मामला हो, जबल में ईजल्लजखत जनयत तारीख के ऄंदर भुगतान ककया जाएगा। घ जजस ईपभोक्ता का लाआसेंसधारी के ईपभोक्ता के रूप म ें ऄजधकार समाप्त हो गया ह ै या िह लाआसेंसधारी के साथ ऄपनी बकाया राजि का जनपटान नहीं कर रहा ह,ै िह देय राजि प्राप्त करन े का हकदार नहीं होगा। ङ जबललग के संबंध में जितरण लाआसेंसधारी के साथ ककसी भी जििाद के मामले में, प्रोज्यूमर को जिकायत के जनिारण के जलए ऄजधजनयम की धारा 42(5) से (7) के तहत अयोग द्वारा जनर्ददष्ट तंत्र में जिकायत करनी होगी। 11. जमु ाना ा या मअु िजा - मीटररग जसस्ट्टम म ेंजिफलता 11.1 मीटररग प्रणाली की जिफलता के मामले में, दंड या मअु िजे के प्रािधान जितरण लाआसेंसधारी के जलए अयोग द्वारा बनाए गए जितरण लाआसेंसधाठरयों के प्रदिान के मानकों के जनयमों के प्रािधानों के ऄनुसार होंगे। 11.2 आन जिजनयमों के तहत जनधााठरत समय सीमा को परू ा करने में जिफलता के मामले म,ें जितरण लाआसेंसधारी ईपभोक्ता को नीचे जिजनयम 15.1 (ठ) के तहत जनर्ददष्ट मअु िजे का भगु तान करने के जलए ईत्तरदायी होगा। 12. जिलबं स ेभगु तान के जलए सरचाज ा यकद ईपरोक्त जिजनयम 10.1 (ड़) और जिजनयम 10.2(क) के तहत जितरण लाआसेंसधारी द्वारा भुगतान के मामले म ें िषा की 31 मइ स े ऄजधक जिलंजबत हो जाती ह,ै तो जितरण लाआसेंसधारी पर 31 मइ के बाद की देरी से 1.25% प्रजत माह की दर स ेदेरी के जलए सरचाजा लगाया जाएगा। 13. अरइ पािर की बकैं कग के जलए प्रभार निीकरणीय उजाा पठरयोजनाए,ं चाह े ि े स्ट्िय ं के स्ट्िाजमत्ि िाली हों या आन जिजनयमों के ऄतं गात स्ट्थाजपत तृतीय पक्ष के स्ट्िाजमत्ि िाली हों जबजली की बैंककग के संबंध म ेंिल्ु क से छूट दी जाएगी। 14. निीकरणीय खरीद दाजयत्ि और अरइसी तत्रं के ऄतं गता भाग लने ेकी पात्रता 14.1 नेट मीटररग व्यिस्ट्था के तहत निीकरणीय उजाा पठरयोजना से प्रोज्यूमर द्वारा खपत की गइ जबजली की मात्रा अरपीओ के ऄनपु ालन योग्य होगी, यकद ऐसा ऄजभयोजक एक बाध्यकारी आकाइ ह।ै 14.2 नेट मीटररग व्यिस्ट्था के ऄंतगता स्ट्िाजमत्ि िाली और स्ट्थाजपत निीकरणीय उजा ा पठरयोजना स े ईपभोक्ता द्वारा खपत की गइ जबजली की मात्रा, यकद ऐसा ईपभोक्ता एक बाध्यकारी आकाइ नहीं ह,ै तो ईसे जितरण लाआसेंसधारी के अरपीओ को परू ा करना होगा। 14.3 ईपरोक्त जिजनयम 10.1 (ड़) के प्रािधानों के तहत जितरण लाआसेंसधारी द्वारा खरीदी गइ निीकरणीय उजाा की गैर-समायोजजत िुद्ध क्रेजडट यूजनट भी ऄपने अरपीओ को पूरा करने के जलए योग्य होंगी। 14.4 िुद्ध जबललग या सकल मीटररग व्यिस्ट्था के मामल े में, ईत्पादन मीटर द्वारा दज ा की गइ जबजली की पूरी मात्रा को जितरण लाआसेंसधारी के अरपीओ को परू ा करना होगा। 14.5 आन जिजनयमों के तहत ककसी भी ईपभोक्ता द्वारा ईत्पन्न निीकरणीय उजाा अरइसी के जलए पात्र नहीं होगी। 15. अिदे न और पजं ीकरण की प्रकक्रया 15.1. जितरण लाआसेंसधारी ईपभोक्ताओं के पठरसरों में निीकरणीय उजाा ईत्पादन प्रणाली स्ट्थाजपत करने की प्रकक्रया को सुगम बनाएगा। आस संबंध म,ें लाआसेंसधारी जनम्न काया करेगा: क ईपभोक्ताओं के पठरसरों में जितठरत निीकरणीय उजाा प्रणाजलयों या ईपकरणों की स्ट्थापना, आंटरकनेटिन और मीटररग के जलए ईपभोक्ताओं अिेदन प्राप्त करने के जलए एक ऑनलाआन पोटाल बनाएं और आसे जनयजमत अधार पर ऄपडेट करें। ख ऄपनी िेबसाआट और ऄपन ेसभी कायाालयों में जनम्नजलजखत को प्रमुखता से प्रदर्तित करें:-14 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (i) सकल मीटररग/नेट जबललग/नेट मीटररग व्यिस्ट्था के ऄतं गता निीकरणीय उजाा प्रणाली की स्ट्थापना और चाल ू करने के जलए जििरण म ेंजिस्ट्ततृ मानकीकृत प्रकक्रया; (ii) अिेदन पत्र जमा करने से लेकर कमीिलनग तक ऐसी निीकरणीय उजाा प्रणाली की स्ट्थापना में ईपभोक्ताओं की सुजिधा के जलए संपका का एक लबद;ु (iii) कायाालयों का पता और टेलीफोन नंबर जहां भरे हुए अिेदन पत्र जमा ककए जा सकते ह;ैं (iv) ऐसे अिेदनों के साथ प्रस्ट्तुत ककए जाने िाल ेऄपेजक्षत दस्ट्तािेजों की पूरी सूची; (v) अिेदक द्वारा जमा ककए जाने िाले लागू िुल्क; (vi) ईन ईपभोक्ताओं के लाभ के जलए सेिा प्रदाताओं की सूची जो सेिा प्रदाताओं के माध्यम से ऐसी निीकरणीय उजाा प्रणाली स्ट्थाजपत करना चाहते हैं; तथा (vii) केंद्र और राज्य सरकारों की जिजभन्न योजनाओं और कायाक्रमों के तहत ईपभोक्ताओं को जित्तीय प्रोत्साहन। ग जितरण लाआसेंसधारी फॉमा को ऄपनी िेबसाआट पर और हाडा कॉपी के माध्यम से ऄपने स्ट्थानीय कायाालयों म ें ईपलब्लध कराएगा। घ पठरसर के ईपभोक्ता को ऄपनी निीकरणीय उजा ा प्रणाली को लाआसेंसधारी की जितरण प्रणाली स े जोड़न े के जलए जिजनयम के ऄनुलग्नक-2 के रूप में जनर्ददष्ट प्रपत्र में प्रसंस्ट्करण िुल्क के साथ रु. 500 (पांच सौ रुपये मात्र) संबंजधत जितरण लाआसेंसधारी के स्ट्थानीय कायाालय में या जितरण लाआसेंसधाठरयों के िेब पोटाल के माध्यम से ऑनलाआन जमा करेगा। ङ यकद अिेदन पत्र हाडा कॉपी में जमा ककया जाता है, तो ईसे प्राप्त ककया जाएगा, और ईस अिेदन के जलए पंजीकरण संख्या के साथ पािती तैयार की जाएगी। आसे प्राप्त होते ही स्ट्कैन कर िेबसाआट पर ऄपलोड कर कदया जाएगा। यकद जितरण लाआसेंसधारी के िेब पोटला के माध्यम से अिेदन पत्र ऑनलाआन प्राप्त होता है, तो अिेदन जमा करन े पर पंजीकरण संख्या के साथ पािती तैयार की जाएगी। अिेदन पंजीकरण संख्या के साथ पािती के सृजन की तारीख को प्राप्त माना जाएगा; और जितरण लाआसेंसधारी द्वारा ऄजद्वतीय पंजीकरण संख्या के अधार पर िेब-अधाठरत एजप्लकेिन या ककसी ऄधय माध्यम से प्रदान ककया जाएगा ताकक अिेदन की रसीद, साआट जनरीक्षण, मीटर स्ट्थापना और कमीिलनग अकद जैसे अिेदन के प्रसंस्ट्करण की जस्ट्थजत की जनगरानी की जा सके। च लाआसेंसधारी 20 कदनों के ऄंदर तकनीकी व्यिहायाता ऄध्ययन पूरा करेगा और अिेदक को इमले /एसएमएस/पोस्ट्ट के माध्यम से, अिेदन की स्ट्िीकृजत/ऄस्ट्िीकृजत, जैसा भी मामला हो, जमा की जाने िाली ऄनुमाजनत राजि और ईपभोक्ता द्वारा जनष्पाकदत ककए जाने िाल ेऄनुबंध की प्रजत के साथ सूजचत करेगा। छ पूणा भुगतान प्राप्त होने पर, जितरण लाआसेंसधारी अिेदन को स्ट्िीकृजत देगा और अिेदन की पािती जारी होने के तीस (30) कदनों के ऄंदर इमले /एसएमएस/पोस्ट्ट के माध्यम से स्ट्िीकृजत पत्र (एलओए) प्रदान करके अिेदक को आसकी सूचना देगा। ज व्यिहायाता ऄध्ययन से स्ट्थापना के पूरा होने तक की समय ऄिजध के दौरान, यकद निीकरणीय उजाा प्रणाली की अिश्यक क्षमता की स्ट्थापना के जलए जितरण बुजनयादी ढाचं े के ईन्नयन जैस े सर्तिस लाआन, जितरण रांसफामार क्षमता अकद के ईन्नयन की अिश्यकता होती ह,ै तो ऐसा जितरण लाआसेंसधारी या ईपभोक्ता, जैसा भी मामला हो, द्वारा ककया जाएगा। झ निीकरणीय उजाा प्रणाली की स्ट्थापना के बाद, प्रोज्यूमर जितरण लाआसेंसधारी को स्ट्थापना प्रमाण पत्र प्रस्ट्ततु करेगा। लाआसेंसधारी स्ट्थापन प्रमाण पत्र प्रस्ट्ततु करने की जतजथ से तीस कदनों के ऄंदर कनेटिन ऄनुबंध पर हस्ट्ताक्षर, मीटर की स्ट्थापना और निीकरणीय उजाा प्रणाली की सफल कमीिलनग को परू ा करेगा। आन जिजनयमों की ऄजधसूचना के तीस कदनों के ऄंदर कनेटिन ऄनुबंध और स्ट्थापना प्रमाण पत्र के प्रारूप जितरण लाआसेंसधारी के िेब पोटाल पर डाल कदए जाएगं ।े ञ प्रोसुमेर के पास अिश्यक मीटर स्ट्ियं खरीदन े का जिकल्प होगा, जजसे जितरण लाआसेंसधारी द्वारा जांच और स्ट्थाजपत ककया जाएगा। ट आन जिजनयमों म ेंउपर जनर्ददष्ट समय-सीमा का जितरण लाआससें धारी द्वारा पालन ककया जाएगा। जिलम्ब के मामले म,ें लाआसेंसधारी जिजिष्ट मामलों में अयोग स ेईसके औजचत्य सजहत ऄनुमोदन ले सकता ह।ै[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 15 ठ जितरण लाआसेंसधारी की ओर से जबना ककसी ईजचत कारण के जिलंब होन े की जस्ट्थजत में, लाआसेंसधारी, ईपभोक्ता को चूक के प्रत्येक कदन के जलए प्रजतकदन 100 रुपय े (एक सौ रुपये मात्र) की दर स े मुअिजे का भुगतान करने के जलए ईत्तरदायी होगा। ड जितरण लाआसेंसधारी, केंद्र और राज्य सरकारों की जिजभन्न योजनाओं और कायाक्रमों के तहत प्रदान ककए जान े िाले जित्तीय प्रोत्साहनों को ईपभोक्ताओं को प्रदान करेगा। ढ ककसी भी जबललग जििाद के मामले म,ें ऄजभयोजक संबंजधत जितरण लाआसेंसधारी के जिद्युत ईपभोक्ता जिकायत जनिारण फोरम से संपका कर सकता ह।ै जिजिध 16. कनटे िन ऄनबु धं जितरण नेटिका के साथ निीकरणीय उजाा ईत्पादन प्रणाली की कनेजटटजिटी के ऄनुमोदन के बाद लेककन ितामान ईत्पादन की िरुु अत स े पहल े जितरण लाआसेंसधारी और पात्र ईपभोक्ता नेट मीटररग या नेट जबललग या सकल मीटररग कनटे िन ऄनुबंध, जैसा भी मामला हो, जनष्पाकदत करेंगे। नेट मीटररग, नेट जबललग और िॉस मीटररग व्यिस्ट्था के जलए मॉडल कनेटिन एिीमेंट क्रमिः ऄनबु धं 3, ऄनलु ग्नक 4 और ऄनलु ग्नक 5 में कदया गया ह।ै जितरण लाआसेंसधारी जेएकेइडीए के परामिा स े िुप नेट मीटररग या िचुाऄल नेट मीटररग सुजिधा का लाभ ईठाने के आच्छुक ईपभोक्ताओं के जलए एक समान कनेटिन समझौता जिकजसत करेगा, जैसा कक आन जिजनयमों के तहत ऄनुमजत दी गइ ह ै और आसमें प्रििे करन े से पहले अयोग की पूिा स्ट्िीकृजत प्राप्त करें। आस संबंध म ें निीन और निीकरणीय उजा ा मंत्रालय, भारत सरकार (एफ संख्या 318/13/2022-जीसीअरटी) कदनांक 04.08.2022 द्वारा जिकजसत मॉडल जिजनयमों का संदभा जलया जा सकता ह।ै 17. अराम करन ेकी िजक्त अयोग सामाधय या जििेष अदेि द्वारा, जलजखत रूप में दज ा ककए जाने िाल े कारणों के जलए, और प्रभाजित होन े की संभािना िाले पक्षों को सुनिाइ का ऄिसर दने े के बाद, आन जिजनयमों के ककसी भी प्रािधान में स्ट्ियं के प्रस्ट्ताि पर या ककसी व्यजक्त द्वारा पहले ककए गए अिेदन पर छूट द े सकता ह।ै 18. सिं ोधन करन ेकी िजक्त अयोग ककसी भी समय आन जिजनयमों के ककसी भी प्रािधान को जोड़ सकता है, बदल सकता ह,ै संिोजधत कर सकता ह,ै जनलंजबत कर सकता ह,ै या जनरस्ट्त कर सकता ह।ै 19.जनरसन और छूट आन जिजनयमों में ऄधयथा प्रािधान को छोड़ कर, गोिा राज्य और केंद्र िाजसत प्रदेिों के जलए जेइअरसी (नेट मीटररग पर अधाठरत सोलर पीिी जिड आंटरएजटटि जसस्ट्टम) जिजनयम, 2019, समय-समय पर ककए गए संिोधनों के साथ, आसके द्वारा जनरस्ट्त ककया जाता ह:ै बिते कक सभी ईद्देश्यों के जलए, जजसमें आन जिजनयमों की ऄजधसूचना तक की ऄिजध स े संबंजधत मामलों की समीक्षा करना, नेट मीटररग से संबंजधत मुद्दे िाजमल ह,ैं गोिा राज्य और केंद्र िाजसत प्रदिे ों के जलए जेइअरसी (नेट मीटररग पर अधाठरत सोलर पीिी जिड आंटरएजटटि जसस्ट्टम) जिजनयम, 2019, संिोधनों सजहत ईस पर, जैसा लागू हो सकता ह,ै के प्रािधान लाग ूहोंगे। 20. कठठनाआयों को दरू करन ेकी िजक्त आन जिजनयमों के प्रािधानों को प्रभािी करते समय ईत्पन्न होने िाली ककसी भी कठठनाइ के मामले म,ें अयोग या तो स्ट्ि-प्रेरणा से या एक याजचका पर, एक अदिे द्वारा, ऐसे प्रािधान बना सकता ह ै जो ऄजधजनयम के प्रािधानों स े ऄसंगत न हों, जो अिश्यक प्रतीत हो सकते ह।ैं अयोग के अदेि द्वारा । िीके धर, (जेकेएएस) सजचि [जिज्ञापन-III/4/ऄसा./157/2023-24]16 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] ऄनलु ग्नक 1 िोल्टेज स्ट्तर हामोजनटस, मानक: हामोजनटस और आधिटार हामोजनटस अइइइइ 519 मानकों के ऄनुसार होगा। ऄनुमजतप्राप्त व्यजक्तगत हामोजनटस स्ट्तर 3% (िोल्टेज और करंट हामोजनटस दोनों के जलए) से कम होगा और जिड जसस्ट्टम के िोल्टेज और करंट हामोजनटस दोनों के जलए टोटल हामोजनटस जडस्ट्टॉिान (टीएचडी) 5% से कम होगा। आधिटार के जलए मानक आधिटार दक्षता और माप के जलए अइइसी 61683/अइएस 61683 की ऄनपु ालन म ें होना चाजहए और पयाािरण परीक्षण के जलए अइइसी 60068-2 (1, 2, 14, 30)/समतुल्य बीअइएस मानक का पालन करना चाजहए। आधिटार को लगातार जिड की जस्ट्थजत की जनगरानी करनी चाजहए और जिड की जिफलता (या) कम िोल्टेज (या) ऄजधक िोल्टेज की जस्ट्थजत में, सोलर प्लांट को आधिटरा म ेंकदए गए सर्दकट ब्रेकर / ऑटो जस्ट्िच द्वारा काट कदया जाना चाजहए। जिजभन्न ऄधय मानक क्र.स.ं मापदंड सदं भ ा अिश्यकताए 1 सेिा की समि ित ें राज्य जितरण/अपूर्तत कोड राज्य जितरण/अपूर्तत कोड 2 सम्पणू ाजिड केंद्रीय जिद्युत प्राजधकरण (जिड मानक) केंद्रीय जिद्युत प्राजधकरण (जिड मानक) जिजनयम 2010 जिजनयम 2010 मानक 3 ईपकरण बीअइएस / अइइसी / अइइइइ बीअइएस / अइइसी / अइइइइ 4 मीटर समय-समय पर संिोजधत केंद्रीय जिद्युत समय-समय पर संिोजधत केंद्रीय जिद्युत प्राजधकरण (मीटर की स्ट्थापना और प्राजधकरण (मीटर की स्ट्थापना और संचालन) जिजनयम 2006 संचालन) जिजनयम 2006 5 सरु क्षा और केंद्रीय जिद्युत प्राजधकरण (सरु क्षा और केंद्रीय जिद्युत प्राजधकरण (सुरक्षा और जबजली अपूर्तत से संबंजधत ईपाय) जबजली अपूर्तत से संबंजधत ईपाय) अपर्तू त जिजनयम, 2010 जिजनयम, 2010 6 हामोजनक अइइइइ 519 अइइइइ 519 अिश्यकताए सीइए (जितठरत ईत्पादन संसाधनों की सीइए (जितठरत ईत्पादन ससं ाधनों की हामोजनक करेंट कनेजटटजिटी के जलए तकनीकी मानक) कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम 2013 जिजनयम 2013 7 लसक्रोनाआजिे न अइइइइ 519 सोलर प्लांट को जिड फ्रीक्वेंसी लसक्रोनाआज़ेिन जडिाआस से लैस होना सीइए (जितठरत ईत्पादन संसाधनों की चाजहए। हर बार जनरेरटग स्ट्टेिन को कनेजटटजिटी के जलए तकनीकी मानक) जबजली व्यिस्ट्था के साथ लसक्रोनाआज़ ककया जिजनयम 2013 जाता ह।ै यह कनेटिन के लबद ुपर +/- 5% से ऄजधक िोल्टेज में ईतार-चढाि का कारण नहीं बनेगा। 8 िोल्टेज अइइइइ 519 िोल्टेज-ऑपरेरटग लिडो को समस्ट्यात्मक ठरलपग को कम करना चाजहए और सीइए (जितठरत ईत्पादन संसाधनों की नोमीनल कनेटटेड िोल्टेज के 80% से कनेजटटजिटी के जलए तकनीकी मानक) 110% की ऑपरेरटग रेंज के तहत होना जिजनयम 2013 चाजहए। 2 सेकंड के जटलयररग समय के बाद, सौर संयंत्र को खुद को जिड स े ऄलग करने म ेंसक्षम होना चाजहए।[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 17 9 जफ्लकर अइइइइ 519 सौर संयंत्र के संचालन से अइइसी 61000 मानकों या ऄधय समकक्ष भारतीय मानकों, सीइए (जितठरत ईत्पादन संसाधनों की यकद कोइ हो, में बताइ गइ सीमा से ऄजधक कनेजटटजिटी के जलए तकनीकी मानक) िोल्टेज जफ्लकर नहीं होनी चाजहए। जिजनयम 2013 10 अिजृ त्त अइइइइ 519 जब जितरण प्रणाली की अिृजत्त जनर्ददष्ट ितों के बाहर चली जाती ह ै (उपरी तरफ सीइए (जितठरत ईत्पादन संसाधनों की 50.5 हर्टजा और जनचली तरफ 47.5 कनेजटटजिटी के जलए तकनीकी मानक) हर्टजा), तो 0.2 सेकंड के जटलयररग समय के जिजनयम 2013 साथ अिृजत्त ठरप फंटिन ऄजधक और कम होना चाजहए। 11 डीसी आंजटे िन अइइइइ 519 आंटरकनेटिन लबद ु पर पणू ा रेटेड अईटपुट के 0.5% से ऄजधक डीसी पािर या ककसी सीइए (जितठरत ईत्पादन संसाधनों की भी ऑपरेरटग जस्ट्थजत के तहत जितरण कनेजटटजिटी के जलए तकनीकी मानक) प्रणाली म ें रेटेड आधिटार अईटपुट करंट का जिजनयम 2013 1% से ऄजधक आंजेटट नहीं करना चाजहए। 12 पािर फैटटर अइइइइ 519 जबकक आधिटार का अईटपुट 50% से ऄजधक ह,ै 0.9 से ऄजधक का लैलगग पािर सीइए (जितठरत ईत्पादन संसाधनों की फैटटर संचाजलत होना चाजहए। कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम 2013 13 अआललैं डग और अइइइइ 519 फॉल्ट, िोल्टेज या फ़्रीक्वेंसी जभन्नता की जडस्ट्कनटे िन जस्ट्थजत में सौर पठरयोजना को जनधााठरत सीइए (जितठरत ईत्पादन संसाधनों की ऄिजध पर अइइसी मानक के ऄंदर कनेजटटजिटी के जलए तकनीकी मानक) अआलांलडग/जडस्ट्कनटे ट करना चाजहए जिजनयम 2013 14 ओिरलोड और अइइइइ 519 आधिटार म ें ओिरलोड या ओिरहीरटग के ओिरहीट मामले में स्ट्िचाजलत रूप से जस्ट्िच ऑफ सीइए (जितठरत ईत्पादन संसाधनों की करन े की सुजिधा होनी चाजहए और कनेजटटजिटी के जलए तकनीकी मानक) सामाधय जस्ट्थजत बहाल होने पर कफर से जिजनयम 2013 िुरू करना चाजहए। 15 समानातं र जडिाआस अइइइइ 519 सौर मंडल का समानांतर ईपकरण आंटरकनेटिन लबद ु पर सामाधय िोल्टेज के सीइए (जितठरत ईत्पादन संसाधनों की 220% का सामना करने म ेंसक्षम होगा। कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम 2013 16 नोट: मानक/जिजनदेि जितरण लाआसेंसधारी और राज्य एजसें ी द्वारा समय-समय पर संबजं धत िेबसाआटों पर संिोधन/पठरितना के ऄधीन होंगे। ऄनलु ग्नक-2 नटे मीटररग/नटे जबललग/सकल मीटररग व्यिस्ट्था के तहत निीकरणीय उजा ाप्रणाली की स्ट्थापना के जलए अिदे न पत्र का नमनू ा जितरण लाआसेंसधारी का नाम [ ] प्रिासजनक कायाालय का नाम [ ] (अिदे क द्वारा बड़े ऄक्षरों म ेंभरा जाना ह)ै18 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 1. अिेदक का परू ा नाम: 2. ईस पठरसर का पता जहां निीकरणीय ह ैउजाा प्रणाली/पठरयोजना स्ट्थाजपत की जानी ह।ै 3. टेलीफोन/मोबाआल नंबर: 4. इ-मेल अइडी (यकद ईपलब्लध हो): 5. संचार के जलए िैकजल्पक पता (यकद कोइ हो): 6. मौजदू ा जबजली कनेटिन की श्रेणी: 7. ईपभोक्ता संख्या: 8. स्ट्िीकृत भार/ऄनुबंध मांग: (ककलोिाट/केिीए/एचपी में) 9. िोल्टेज जजस पर मौजूदा अपूर्तत दी गइ ह ै(िोल्ट में): 10. स्ट्थाजपत की जाने िाली निीकरणीय उजाा प्रणाली की प्रस्ट्ताजित एसी क्षमता (ककलोिाट में): 11. सोलर आधिटार के अईटपुट पर िोल्टेज: (िोल्ट म)ें , यकद लागू हो। 12. भुगतान ककए गए पंजीकरण िल्ु क का जििरण (रुपय े500/-) कदनांक: _____________ अिेदक के हस्ट्ताक्षर। अिेदन संख्या। _____________________________________ प्राजप्त की जतजथ: ____________________________________________ अिदे न पत्र के साथ सलं ग्न दस्ट्तािजे ों की सचू ी 1. भुगतान ककए गए निीनतम जबजली जबल की प्रजत। 2. साझेदारी फमों के मामले में हस्ट्ताक्षरकताा के पक्ष म ें सामाधय पािर ऑफ ऄटॉनी; कंपजनयों के मामले में जनदेिक मंडल द्वारा पाठरत संबंजधत जितरण लाआसेंसधारी स े जनपटन े के जलए हस्ट्ताक्षरकता ा को ऄजधकृत करने िाल े प्रस्ट्ताि की प्रमाजणत प्रजत (जैसा लाग ू हो) । 3. पीिी मॉड्यूल, आधिटार और जसस्ट्टम के ऄधय ईपकरणों को स्ट्थाजपत करने के जलए तकनीकी जििरण स्ट्थाजपत करने का प्रस्ट्ताि। 4. पंजीकरण िुल्क के भुगतान का प्रमाण। पािती नीचे कदए गए जििरण के ऄनसु ार ................ ककलोिाट क्षमता की निीकरणीय उजाा प्रणाली की कनेजटटजिटी/स्ट्थापना के जलए ……………………… से एक अिेदन प्राप्त हुअ। प्राजप्त की जतजथ अिेदक का नाम एप्लीकेिन नंबर मौजूदा ईपभोक्ता निीकरणीय उजा ा प्रणाली संख्या की क्षमता (1) (2) (3) (4) (5) कदनांक: (ऄजधकृत ऄजधकारी के हस्ट्ताक्षर और पदनाम)।[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 19 ऄनलु ग्नक – 3 नटे मीटररग कनटे िन व्यिस्ट्था का नमनू ा यह ऄनुबधं .................... (स्ट्थान) पर ........................ (तारीख) को पात्र ईपभोक्ता ....................................(नाम) जजसके पास ............................................... (पता) पठरसर ह ै और जजसका ईपभोक्ता नंबर ...........................ह,ै जो प्रथम पक्ष ह ै और जितरण लाआसेंसधारी __________________________________ (आसके बाद 'लाआसेंसधारी' के रूप म ें संदर्तभत) जजसका पर आसका पंजीकृत कायाालय _____________________ पर जस्ट्थत ह;ै जो दसू रा पक्ष ह ै के बीच जनष्पाकदत हुअ ह।ै जबकक, पात्र ईपभोक्ता न े केंद्र िाजसत प्रदेि ‘जम्म ू और कश्मीर ि केंद्र िाजसत प्रदिे लद्दाख के जलए संयुक्त जिद्युत जिजनयामक अयोग (जिड आंटरएजटटि ठरधयूएबल एनजी जसस्ट्टम और आससे संबंजधत मामले) जिजनयम, 2023 (आसके बाद 'नेट मीटररग जिजनयम' के रूप में संदर्तभत) के प्रािधानों ऄंतगता नेट मीटररग व्यिस्ट्था के ऄनमु ोदन के जलए लाआसेंस के जलए अिेदन ककया ह ैऔर लाआसेंसधारक के जितरण नेटिका से आसकी कनेजटटजिटी की मांग की ह;ै और जबकक, लाआसेंसधारी ऄपनी __________ ककलोिाट की निीकरणीय उजाा प्रणाली से ईत्पन्न जबजली के आंजेटिन के जलए पात्र ईपभोक्ता को नेटिका कनेजटटजिटी प्रदान करन े के जलए सहमत हो गया ह;ै दोनों पक्ष एतद्द्वारा जनम्नानुसार सहमत ह:ैं- 1. पात्रता निीकरणीय उजा ा पठरयोजना जितरण नेटिका म ें एकीकृत होने के जलए लाग ू मानदंडों को पूरा करती है, और पात्र ईपभोक्ता आस समझौते की ऄिजध के जलए तदनुसार पठरयोजना का रखरखाि करेगा। 2. तकनीकी और आंटर-कनटेिन अिश्यकताए 2.1. मीटररग व्यिस्ट्था और लाआसेंसधारी के नेटिका के साथ निीकरणीय उजाा पठरयोजना का आंटर-कनैटिन नेट मीटररग और जितठरत ईत्पादन संसाधनों की कनेजटटजिटी और स्ट्थापना के जलए केंद्रीय जिद्युत प्राजधकरण द्वारा जमटर की स्ट्थापना और संचालन के जलए जनर्ददष्ट तकनीकी मानकों और मानदंडों के प्रािधानों के ऄनुसार होगा। 2.2. पात्र ईपभोक्ता सहमत ह,ै कक िह लाआसेंसधारी के नेटिका में निीकरणीय उजाा पठरयोजना के कनेटिन से पहले, एक अआसोलेिन जडिाआस (स्ट्िचाजलत और आनिटरा और बाहरी मैनुऄल ठरले के ऄंदर जनर्तमत दोनों) स्ट्थाजपत करेगा; और यकद जितरण नेटिका की मरम्मत और रखरखाि के जलए अिश्यक हो तो लाआसेंसधारी की ईस तक पहुचं होगी। 2.3. लाआसेंसधारी आंटरफेस/आंटर-कनेटिन प्िाआंट और मीटररग प्िाआंट को जनर्ददष्ट करेगा। 2.4. पात्र ईपभोक्ता ऄपन े जसस्ट्टम म ें सभी प्रासंजगक डेटा, जैसे िोल्टेज, फ्रीक्वेंसी, सर्दकट ब्रेकर, अआसोलेटर जस्ट्थजत, लाआसेंसधारी द्वारा अिश्यक होने पर प्रस्ट्तुत करेगा। 3. सरुक्षा 3.1. लाआसेंसधारी की जितरण प्रणाली से जड़ु े ईपकरण प्रासंजगक ऄंतराष्ट्रा ीय (अइइइइ/अइइसी) या भारतीय मानकों (बीअइएस) के ऄनुरूप होंग,े जैसा भी मामला हो, और जिद्युत ईपकरण की स्ट्थापना सुरक्षा और जबजली की अपूर्तत के मामले म ेंकेंद्रीय जिद्युत प्राजधकरण द्वारा जनर्ददष्ट अिश्यकताओं का ऄनुपालन करेगी। 3.2. निीकरणीय उजाा पठरयोजना के जडजाआन, स्ट्थापना, रखरखाि और संचालन निीकरणीय उजाा पठरयोजना के साथ- साथ लाआसेंसधारक के नेटिका की सुरक्षा के ऄनुकूल तरीके से ककया जाएगा। 3.3. यकद, ककसी भी समय, लाआसेंसधारी यह जनधााठरत करता ह ै कक पात्र ईपभोक्ता की निीकरणीय उजा ा पठरयोजना लाआसेंसधारी के ऄधय ईपभोक्ताओं या ईसकी संपजत्तयों को नुकसान पहुचं ा रही ह ै या नुकसान पहुचं ा सकती ह ैऔर/या ऐसा पठरणाम हो सकता ह,ै तो योग्य ईपभोक्ता लाआसेंसधारी से प्राप्त जनदेि पर जितरण नेटिका से निीकरणीय उजा ा पठरयोजना को जडस्ट्कनेटट कर देगा और पुन: जोड़ने स ेपहले ऄपन ेस्ट्ियं के खचा पर सुधारात्मक ईपाय करेगा।20 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 3.4. लाआसेंसधारी ककसी भी दघु ाटना के जलए जजम्मेदार नहीं होगा जजसके पठरणामस्ट्िरूप मानि या जानिरों को चोट लगी हो या जिड की अपूर्तत बंद होने पर निीकरणीय उजाा पठरयोजना से बैक-फीलडग के कारण संपजत्त को नुकसान हो सकता ह।ै ऐसी दघु ाटना को रोकने के जलए लाआसेंसधारी ऐसी अकजस्ट्मकताओं की जस्ट्थजत म ें ककसी भी समय आंस्ट्टॉलेिन को जडस्ट्कनेटट कर सकता ह।ै 4. ऄधय मजं रूी और स्ट्िीकृजतया ं निीकरणीय उजाा पठरयोजना को जितरण नेटिका से जोड़ने स े पहले पात्र ईपभोक्ता को ककसी भी िैधाजनक ऄनुमोदन और मंजूरी की अिश्यकता हो सकती ह,ै जैसे कक जिद्युत जनरीक्षक या नगरपाजलका या ऄधय प्राजधकरणों से। 5. समझौत ेकी ऄिजध और समापन यह समझौता 20 साल की ऄिजध के जलए होगा, लेककन जनम्न के द्वारा समय से पहल े समाप्त ककया जा सकता है, क अपसी सहमजत स;े या ख योग्य ईपभोक्ता द्वारा, लाआसेंसधारी को 30 कदनों का नोठटस देकर; ग लाआसेंसधारी द्वारा, 30 कदनों का नोठटस देकर, यकद पात्र ईपभोक्ता आस समझौते की ककसी भी ितों या नेट मीटररग जिजनयमों के प्रािधानों का ईल्लघं न करता ह ैऔर 30 कदनों के ऄंदर या ऐसी ऄधय ईजचत ऄिजध के ऄंदर आस तरह के ईल्लंघन का समाधान नहीं करता ह,ै या आस तरह के ईलंघन की सूचना प्राप्त होन े के बाद ऐसी ऄिजध के ऄंदर जैसा कक प्रािधान ककया जा सकता है, या लाआसेंसधारी द्वारा जलजखत रूप म ें सूजचत ककसी ऄधय िैध कारण के जलए। 6. ईपलब्लधता और जडस-कनटैिन 6.1. पात्र ईपभोक्ता, ईसके द्वारा लाआसेंसधारी को मीटररग ईपकरण और निीकरणीय उजाा पठरयोजना के स्ट्िचाजलत और मैनुऄल दोनों जडस्ट्कनेलटटग ईपकरणों तक पहुचं प्रदान करेगा; 6.2. एक अकजस्ट्मक या अईटेज जस्ट्थजत में यकद लाआसेंसधारी निीकरणीय उजाा पठरयोजना के स्ट्िचाजलत और मनै ुऄल दोनों जडस्ट्कनेलटटग ईपकरणों का ईपयोग नहीं कर सकता ह,ै तो यह पठरसर म ें जबजली की अपूर्तत को जडस्ट्कनेटट कर सकता ह।ै 6.3. खंड 5 के तहत आस समझौते को समाप्त करने पर, पात्र ईपभोक्ता लाआसेंसधारी के नेटिका से निीकरणीय उजाा पठरयोजना को तरु ंत जडस्ट्कनेटट कर देगा। 7. दाजयत्ि 7.1 पक्ष निीकरणीय उजाा पठरयोजना की स्ट्थापना, जितरण नेटिका के साथ कनेजटटजिटी और जसस्ट्टम के संचालन के दौरान ककसी भी पाटी की लापरिाही या कदाचार के नुकसान या प्रजतकूल प्रभािों के जलए एक-दसू रे की क्षजतपूर्तत करेंगे। 7.2. दोनों पक्ष लाभ या राजस्ट्ि की ककसी भी हाजन, व्यापार में रुकािट, ऄनुबंध या सद्भािना की हाजन, या ऄप्रत्यक्ष, पठरणामी, अकजस्ट्मक या जििेष क्षजतयों के जलए एक-दसू रे के प्रजत ईत्तरदायी नहीं होंगी, जजनमें ऄधय के साथ साथ दंडात्मक या कठोर क्षजत, िाजमल ह,ैं चाह ेये देनदाठरया , नुकसान या क्षजत ऄनुबधं म,ें या ऄधयथा ईत्पन्न होती ह।ै 8. िाजणजज्यक समझौता 8.1. आस समझौते के तहत िाजणजज्यक जनपटान नेट मीटररग जिजनयमों के ऄनुसार होंगे। 8.2. लाआसेंसधारी पात्र ईपभोक्ता को क्षजतपूर्तत करने के जलए ईत्तरदायी नहीं होगा यकद ईसकी निीकरणीय उजा ा पठरयोजना जिड/नेटिका में जबजली अपूर्तत की जिफलता के कारण लाआसेंसधारी के नेटिका म ें ईत्पन्न ऄजधिेष जबजली को आंजेटट करन े में ऄसमथ ाह।ै 8.3. मौजूदा मीटररग जसस्ट्टम, यकद नेट मीटररग जिजनयमों के ऄनुसार नहीं ह,ै तो एक जद्व-कदिा मीटर (संपणू ा ितामान/सीटी संचाजलत) द्वारा प्रजतस्ट्थाजपत ककया जाएगा, और निीकरणीय उजाा ईत्पादन को मापन े के जलए एक ऄलग ईत्पादन[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 21 मीटर प्रदान ककया जा सकता ह।ै उजा ा के जनयाात और अयात को ठरकॉड ा करन े के जलए लाआसेंसधारी के नेटिका के आंटर-कनेटिन लबद ुपर जद्व-कदि मीटर (संपूण ा करेंट / सीटी संचाजलत) स्ट्थाजपत ककया जाएगा। 8.4. एक-कदि और जद्व-कदि मीटर एक ही जनकटता में ऄलग-ऄलग मीटर बॉटस में लगाए जाएगं े। 8.5. लाआसेंसधारी मीटर रीलडग की जनधााठरत जतजथ पर नेट मीटडा उजाा के जलए माजसक जिद्युत जबल जारी करेगा। यकद जनयाात की गइ उजा ा अयाजतत उजा ा से ऄजधक ह,ै तो लाआससें धारी को जनयाात की गइ िद्धु उजा ा को जबजली की क्रेजडट यूजनट के रूप में कदखाना होगा जैसा कक नेट मीटररग जिजनयमों म ें जनर्ददष्ट ह।ै यकद जनयाात की गइ उजा ा अयाजतत उजाा से कम ह,ै तो पात्र ईपभोक्ता को ईस ईपभोक्ता श्रेणी के जलए अयोग द्वारा ऄनुमोकदत प्रचजलत टैठरफ पर अयाजतत िुद्ध उजाा के जलए जितरण लाआसेंसधारी को भगु तान करना होगा, जजससे िह संबंजधत ह।ै 9. कनटेिन की लागत पात्र ईपभोक्ता नेट मीटर के बाद नेट मीटररग व्यिस्ट्था लागत को छोड़कर निीकरणीय उजाा पठरयोजना की स्ट्थापना से संबंजधत सभी लागतों को िहन करेगा। 10. जििादों का जनपटान 10.1. आस समझौते के ऄंतगात ईत्पन्न होने िाले ककसी भी जििाद को दोनों पक्षों द्वारा सद्भािपूिाक और धयायसंगत तरीके से तुरंत हल ककया जाएगा। 10.2 जबललग/भगु तान और मीटररग से संबंजधत जििादों को ईपभोक्ता जिकायत जनिारण फोरम (सीजीअरएफ) और कफर जनपटान के जलए ऄजधजनयम की धारा 42 की ईप-धारा 6 के तहत जनयक्तु लोकपाल को भजे ा जाएगा, यकद आसका समाधान सीजीअरएफ म ेंनहीं ककया जाता ह।ै साक्ष्य के रूप म,ें पात्र ईपभोक्ता की ओर स े_________________________________(नाम) और लाआसेंसधारी की और से ________________________________ आस समझौते से सहमत ह।ैं ऄनलु ग्नक-4 नटे जबललग कनटे िन व्यिस्ट्था का नमनू ा यह समझौता _______ (स्ट्थान) पर कदनांक ___________ (कदन) ________ (महीना) _________ (िषा) को पात्र ईपभोक्ता ____________ (नाम)) ____________________________________________ (पता) ईपभोक्ता संख्या _______________ , जो प्रथम पक्ष ह ै और जितरण लाआसेंसधारी _________ (यहा पर 'लाआसेंसधारी' के रूप में संदर्तभत), जजसका पंजीकृत कायाालय __________________ (पता ) पर जस्ट्थत ह,ै जो दसू रा पक्ष ह ैके बीच जनष्पाकदत ककया गया ह।ै जबकक पात्र ईपभोक्ता ने केंद्र िाजसत प्रदिे ‘जम्मू और कश्मीर ि केंद्र िाजसत प्रदेि लद्दाख के जलए संयुक्त जिद्युत जिजनयामक अयोग (जिड आंटरएजटटि ठरधयूएबल एनजी जसस्ट्टम और आससे संबंजधत मामले) जिजनयम, 2023 के प्रािधानों के तहत एक नेट जबललग व्यिस्ट्था के ऄनुमोदन के जलए लाआसेंसधारी को अिेदन ककया ह ै और लाआसेंसधारी के जितरण नेटिका से आसकी कनेजटटजिटी की मांग की ह;ै और जबकक लाआसेंसधारी ऄपनी ________ ककलोिाट की निीकरणीय उजाा ईत्पादन प्रणाली से ईत्पन्न जबजली के आंजेटिन के जलए पात्र ईपभोक्ता को नेटिका कनेजटटजिटी प्रदान करन े के जलए सहमत हो गया है; दोनों पक्ष एतद्द्वारा जनम्नानुसार सहमत ह:ैं 1. पात्रता निीकरणीय उजाा ईत्पादन प्रणाली जितरण नेटिका में एकीकृत होने के जलए लागू मानदंडों को पूरा करती ह,ै और पात्र ईपभोक्ता आस समझौते की ऄिजध के जलए तदनुसार जसस्ट्टम का रखरखाि करेगा। 2. तकनीकी और आंटर-कनटे िन अिश्यकताए22 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] 2.1 मीटररग व्यिस्ट्था और लाआसेंसधारी के नेटिका के साथ निीकरणीय उजा ा पठरयोजना का आंटर-कनैटिन नेट मीटररग और जितठरत ईत्पादन संसाधनों की कनेजटटजिटी और स्ट्थापना के जलए केंद्रीय जिद्युत प्राजधकरण द्वारा जमटर की स्ट्थापना और संचालन के जलए जनर्ददष्ट तकनीकी मानकों और मानदंडों के प्रािधानों के ऄनुसार होगा। पात्र ईपभोक्ता सहमत ह,ै कक िह लाआसेंसधारी के नेटिका म ें निीकरणीय उजाा पठरयोजना के कनेटिन स े पहल,े एक अआसोलेिन जडिाआस (स्ट्िचाजलत और आनिटार और बाहरी मैनऄु ल ठरल े के ऄदं र जनर्तमत दोनों) स्ट्थाजपत करेगा; और यकद जितरण नेटिका की मरम्मत और रखरखाि के जलए अिश्यक हो तो लाआसेंसधारी की ईस तक पहुचं होगी। 2.2 लाआसेंसधारी आंटरफेस/आंटर-कनेटिन प्िाआंट और मीटररग प्िाआंट को जनर्ददष्ट करेगा। 2.3 पात्र ईपभोक्ता ऄपने जसस्ट्टम में सभी प्रासंजगक डेटा, जैसे िोल्टेज, अिृजत्त, सर्दकट ब्रेकर, अआसोलेटर जस्ट्थजत, लाआसेंसधारी को अिश्यक होन े पर प्रस्ट्तुत करेगा। 3 सरु क्षा 3.1 लाआसेंसधारी की जितरण प्रणाली से जुड़े ईपकरण प्रासंजगक ऄंतराष्ट्रा ीय (अइइइइ/अइइसी) या भारतीय मानकों (बीअइएस) के ऄनुरूप होंग,े जैसा भी मामला हो, और जिद्युत ईपकरण की स्ट्थापना सुरक्षा और जबजली की अपूर्तत के मामले म ेंकेंद्रीय जिद्युत प्राजधकरण द्वारा जनर्ददष्ट अिश्यकताओं का ऄनुपालन करेगी। 3.2 निीकरणीय उजाा पठरयोजना के जडजाआन, स्ट्थापना, रखरखाि और संचालन निीकरणीय उजाा पठरयोजना के साथ- साथ लाआसेंसधारक के नेटिका की सुरक्षा के ऄनुकूल तरीके से ककया जाएगा। 3.3 यकद, ककसी भी समय, लाआसेंसधारी यह जनधााठरत करता ह ै कक पात्र ईपभोक्ता की निीकरणीय उजाा पठरयोजना लाआसेंसधारी के ऄधय ईपभोक्ताओं या ईसकी संपजत्तयों को नुकसान पहुचं ा रही ह ै या नुकसान पहुचं ा सकती ह ैऔर/या ऐसा पठरणाम हो सकता ह,ै तो योग्य ईपभोक्ता लाआसेंसधारी से प्राप्त जनदेि पर जितरण नेटिका से निीकरणीय उजा ा पठरयोजना को जडस्ट्कनेटट कर देगा और पुन: जोड़ने स ेपहले ऄपन ेस्ट्ियं के खचा पर सुधारात्मक ईपाय करेगा। 3.4 लाआसेंसधारी ककसी भी दघु ाटना के जलए जजम्मेदार नहीं होगा जजसके पठरणामस्ट्िरूप मानि या जानिरों को चोट लगी हो या जिड की अपूर्तत बंद होने पर निीकरणीय उजाा पठरयोजना से बैक-फीलडग के कारण संपजत्त को नुकसान हो सकता ह।ै ऐसी दघु ाटना को रोकने के जलए लाआसेंसधारी ऐसी अकजस्ट्मकताओं की जस्ट्थजत म ें ककसी भी समय आंस्ट्टॉलेिन को जडस्ट्कनेटट कर सकता ह।ै 4 ऄधय मजं रू ी और स्ट्िीकृजतया ं निीकरणीय उजाा पठरयोजना को जितरण नेटिका से जोड़ने स े पहले पात्र ईपभोक्ता को ककसी भी िैधाजनक ऄनुमोदन और मंजूरी की अिश्यकता हो सकती ह,ै जसै े कक जिद्युत जनरीक्षक या नगरपाजलका या ऄधय प्राजधकरणों से। 5 समझौत ेकी ऄिजध, और समाजप्त 5.1 यह समझौता 20 साल की ऄिजध के जलए होगा, लेककन जनम्न के द्वारा समय से पहल े समाप्त ककया जा सकता है, क अपसी सहमजत स;े या ख योग्य ईपभोक्ता द्वारा, लाआसेंसधारी को 30 कदनों का नोठटस देकर; ग लाआसेंसधारी द्वारा, 30 कदनों का नोठटस देकर, यकद पात्र ईपभोक्ता आस समझौते की ककसी भी ितों या नेट मीटररग जिजनयमों के प्रािधानों का ईल्लघं न करता ह ैऔर 30 कदनों के ऄंदर या ऐसी ऄधय ईजचत ऄिजध के ऄंदर आस तरह के ईल्लंघन का समाधान नहीं करता ह,ै या आस तरह के ईलंघन की सूचना प्राप्त होन े के बाद ऐसी ऄिजध के ऄंदर जैसा कक प्रािधान ककया जा सकता है, या लाआसेंसधारी द्वारा जलजखत रूप म ें सूजचत ककसी ऄधय िैध कारण के जलए। घ लाआसेंसधारी द्वारा, 30 कदनों का नोठटस देकर, यकद योग्य ईपभोक्ता समय पर ऄपने बकाया का भुगतान करने म ें जिफल रहता ह ैया ककसी भी कदाचार में जलप्त होता ह।ै 6. एटसेस और जडसकनटे िन 6.1 पात्र ईपभोक्ता, ईसके द्वारा लाआसेंसधारी को मीटररग ईपकरण और निीकरणीय उजाा पठरयोजना के स्ट्िचाजलत और मैनुऄल दोनों जडस्ट्कनेलटटग ईपकरणों तक पहुचं प्रदान करेगा;[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 23 6.2 एक अकजस्ट्मक या अईटेज जस्ट्थजत में यकद लाआसेंसधारी निीकरणीय उजाा पठरयोजना के स्ट्िचाजलत और मनै ुऄल दोनों जडस्ट्कनेलटटग ईपकरणों का ईपयोग नहीं कर सकता ह,ै तो यह पठरसर म ें जबजली की अपूर्तत को जडस्ट्कनेटट कर सकता ह।ै 6.3 खंड 5 के तहत आस समझौत े को समाप्त करन े पर, पात्र ईपभोक्ता लाआसेंसधारी के नेटिका से निीकरणीय उजा ा पठरयोजना को तरु ंत जडस्ट्कनेटट कर देगा। 7. दाजयत्ि 7.1 दोनों पक्ष निीकरणीय उजाा पठरयोजना की स्ट्थापना, जितरण नेटिका के साथ कनेजटटजिटी और जसस्ट्टम के संचालन के दौरान ककसी भी पक्ष की लापरिाही या कदाचार के नुकसान या प्रजतकूल प्रभािों के जलए एक-दसू रे की क्षजतपूर्तत करेंगे। 7.2 दोनों पक्ष लाभ या राजस्ट्ि की ककसी भी हाजन, व्यापार म ें रुकािट, ऄनुबंध या सद्भािना की हाजन, या ऄप्रत्यक्ष, पठरणामी, अकजस्ट्मक या जििेष क्षजतयों के जलए एक-दसू रे के प्रजत ईत्तरदायी नहीं होंगी, जजनमें ऄधय के साथ साथ दंडात्मक या कठोर क्षजत, िाजमल ह,ैं चाह ेये देनदाठरया , नुकसान या क्षजत ऄनुबधं म,ें या ऄधयथा ईत्पन्न होती ह।ै 8. िाजणजज्यक समझौता 8.1 आस समझौते के तहत िाजणजज्यक जनपटान नेट मीटररग जिजनयमों के ऄनुसार होंगे। 8.2 निीकरणीय उजाा ईत्पादन स्ट्टेिन द्वारा जबललग ऄिजध में जनयाात की गइ आकाआयों को जितरण लाआसेंसधारी द्वारा समझौते की पूरी ऄिजध के जलए ऄनुमोकदत फीड-आन टैठरफ के ऄनुसार _____ रुपये प्रजत ककलोिाट घंटा म ें खरीदा जाएगा। 8.3 लाआसेंसधारी पात्र ईपभोक्ता को क्षजतपूर्तत करन े के जलए ईत्तरदायी नहीं होगा यकद ईसकी निीकरणीय उजा ा ईत्पादन प्रणाली जिड/नेटिका में जबजली अपूर्तत की जिफलता के कारण लाआसेंसधारी के नेटिका में ईत्पन्न ऄजधिषे जबजली को आंजेटट करन े में ऄसमथ ाह।ै 8.4 लाआसेंसधारी, अयोग द्वारा ऄनुमोकदत फीड-आन टैठरफ पर निीकरणीय उजाा जिकासकताा द्वारा जनयाात की गइ आकाआयों के जलए लेखांकन के बाद और लाग ू टैठरफ अदेि पर जिड से अयाजतत आकाआयों के जलए लेखांकन के बाद जबललग चक्र के ऄनुसार िुद्ध जबल जारी करेगा। 9 कनटे िन लागत पात्र ईपभोक्ता निीकरणीय उजाा ईत्पादन प्रणाली की स्ट्थापना से संबंजधत सभी लागतों को िहन करेगा जजसम ें निीकरणीय उजा ाईत्पादन मीटर की लागत िाजमल ह।ै 10 जििादों का समाधान 10.1 आस समझौते के तहत ईत्पन्न होन े िाल े ककसी भी जििाद को दोनों पक्षों द्वारा सद्भािपूिाक और धयायसंगत तरीके स े तुरंत हल ककया जाएगा। 10.2 पात्र ईपभोक्ता जबललग के संबंध में ककसी भी जिकायत को, जजसका समाधान लाआसेंसधारी द्वारा नहीं ककया गया ह,ै संबंजधत जिजनयमों के तहत गठठत संबंजधत ईपभोक्ता जिकायत जनिारण फोरम में भेजगे ा। साक्ष्य के रूप म,ें पात्र ईपभोक्ता की ओर स े_________________________________(नाम) और लाआसेंसधारी की और से ________________________________ आस समझौते से सहमत ह।ैं ऄनलु ग्नक-5 िोस मीटररग कनटे िन व्यिस्ट्था का नमनू ा यह समझौता _______ (स्ट्थान) पर कदनांक ___________ (कदन) ________ (महीना) _________ (िषा) को पात्र ईपभोक्ता या तीसरे पक्ष स्ट्िामी ____________ (नाम) जजसके पास या लीज पर_______________________(पता) जस्ट्थत पठरसर ह,ै जो प्रथम पक्ष ह ै और24 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] जितरण लाआसेंसधारी _________ (यहा पर 'लाआसेंसधारी' के रूप म ें संदर्तभत), और जजसका प्रजतजनजधत्ि _______________ (नाजमत ऄजधकारी का नाम) कर रह े ह ैं और जजसका पंजीकृत कायाालय __________________ (पता ) पर जस्ट्थत ह,ै जो दसू रा पक्ष ह,ै के बीच जनष्पाकदत ककया गया ह।ै और जबकक आस समझौते के जनयम एिं ितों और केंद्र िाजसत प्रदेि ‘जम्मू और कश्मीर ि केंद्र िाजसत प्रदेि लद्दाख के जलए संयुक्त जिद्युत जिजनयामक अयोग ((जिड आंटरएजटटि ठरधयएू बल एनजी जसस्ट्टम और आससे संबंजधत मामले) जिजनयम, 2023 के प्रािधानों के ऄनुसार, ………………………………….. (लाआसेंसधारी का नाम) ________ ककलोिाट क्षमता के ऄपने निीकरणीय उजाा संयंत्र से ईत्पन्न जबजली को लाआसेंसधारी की जबजली प्रणाली म ें आंजेटट करने के जलए पात्र ईपभोक्ता को जिड कनेजटटजिटी प्रदान करन े के जलए सहमत ह ै दोनों पक्ष एतद्द्वारा जनम्नानुसार सहमत ह:ैं 1 पात्रता 1.1 निीकरणीय उजा ा ईत्पादन प्रणाली जितरण नेटिका में एकीकृत होने के जलए लागू मानदडं ों को पूरा करती है, और पात्र ईपभोक्ता आस समझौते की ऄिजध के जलए तदनुसार जसस्ट्टम को बनाए रखगे ा। 2 तकनीकी और आंटरकनटे िन की अिश्यकताए 2.1 िोस मीटररग प्रणाली के तहत निीकरणीय उजाा ईत्पादन संयंत्र समय-समय पर संिोजधत केंद्र िाजसत प्रदेि ‘जम्म ू और कश्मीर ि केंद्र िाजसत प्रदेि लद्दाख के जलए संयुक्त जिद्युत जिजनयामक अयोग (जिड आंटरएजटटि निीकरणीय उजाा निीकरणीय उजाा प्रणाली और आससे संबंजधत मामल)े जिजनयम, 2023 में जनर्ददष्ट मानकों और जनम्नजलजखत जिजनयमों और जनयमों की ऄनुपलना करेगा: i. केंद्रीय जिद्युत प्राजधकरण (जितठरत ईत्पादन संसाधनों की कनेजटटजिटी के जलए तकनीकी मानक) जिजनयम, 2013 और ईसके बाद के संिोधन; ii. केंद्रीय जिद्युत प्राजधकरण (मीटर की स्ट्थापना और संचालन) जिजनयम 2006 और ईसके बाद के संिोधन; iii. केंद्रीय जिद्युत प्राजधकरण (सुरक्षा और जबजली अपूर्तत के ईपाय) जिजनयम, 2010 और ईसके बाद के संिोधन; iv. अयोग द्वारा तैयार जिड कोड जिजनयम; v. अयोग द्वारा तैयार अपूर्तत संजहता जिजनयम; vi. जितरण लाआसेंसधारी के जिद्युत ईपभोक्ता पर लाग ूकोइ ऄधय प्रािधान। 2.2 पात्र ईपभोक्ता सहमत ह,ै कक िह लाआसेंसधारी के नेटिका में निीकरणीय उजाा पठरयोजना के कनेटिन से पहले, एक अआसोलेिन जडिाआस (स्ट्िचाजलत और आनिटरा और बाहरी मैनुऄल ठरले के ऄंदर जनर्तमत दोनों) स्ट्थाजपत करेगा; और यकद जितरण नेटिका की मरम्मत और रखरखाि के जलए अिश्यक हो तो लाआसेंसधारी की ईस तक पहुचं होगी। 2.3 पात्र ईपभोक्ता आस बात से सहमत ह ै कक जबजली बंद होने की जस्ट्थजत म ें लाआसेंसधारी की फोटोिोजल्टक प्रणाली स्ट्िचाजलत रूप स े जडस्ट्कनेटट/अआसोलेट हो जाएगी और ईसका संयंत्र लाआसेंसधारी की जितरण प्रणाली म ें जबजली नहीं डालेगा। 2.4 जितरण प्रणाली से जुड़े सभी ईपकरण प्रासंजगक ऄंतराष्ट्रा ीय (अइइइइ/अइइसी) या भारतीय मानकों (बीअइएस) के ऄनुरूप होन े चाजहए और जिद्युत ईपकरणों की स्ट्थापना को केंद्रीय जिद्युत प्राजधकरण (सुरक्षा और जबजली अपूर्तत के ईपाय) जिजनयम, 2010 का ऄनुपालन करना चाजहए। 2.5 पात्र ईपभोक्ता सहमत ह ैकक लाआसेंसधारी आंटरफेस/आंटरकनेटिन प्िाआंट और मीटररग प्िाआंट जनर्ददष्ट करेगा 2.6 पात्र ईपभोक्ता और जितरण लाआसेंसधारी, संबंजधत सीइए और जम्मू और कश्मीर के जेइअरसी यूटी और लद्दाख के यूटी जिजनयमों के संचालन और रखरखाि के संबंध म ें संयंत्र, ड्राआंग और डायिाम, साआट जजम्मेदारी ऄनुसूची, हामोजनटस, लसक्रोनाआज़ेिन, िोल्टेज, फ़्रीक्वेंसी, जफ्लकररग का पालन करन े के जलए सहमत ह।ैं[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 25 2.7 जितरण प्रणाली को सरु जक्षत और जिश्वसनीय बनाए रखन े के जलए लाआसेंसधारी के दाजयत्ि के कारण, पात्र ईपभोक्ता सहमत ह ै कक यकद लाआसेंसधारी द्वारा यह जनधााठरत ककया जाता ह ै कक संबंजधत माजलक की फोटोिोजल्टक प्रणाली या तो ऄधय ईपभोक्ताओं या लाआसेंसधारी की संपजत्त को नुकसान पहुचं ाती ह ै और/या प्रजतकूल प्रभाि पैदा करती है, तो पात्र ईपभोक्ता को लाआसेंसधारी के जनदेि पर तुरंत फोटोिोजल्टक प्रणाली को जितरण प्रणाली से जडस्ट्कनेटट करना होगा और पनु : संयोजन से पहले ऄपन ेखचा पर समस्ट्या को ठीक करना होगा। 3 मजं रू ी और ऄनमु ोदन 3.1 पात्र ईपभोक्ता फोटोिोजल्टक प्रणाली को जितरण प्रणाली से जोड़ने स े पहल े सभी अिश्यक ऄनुमोदन और मंजरू ी (पयाािरण और जिड कनेटिन से संबंजधत) प्राप्त करन े के जलए सहमत ह।ैं 4 एटसेस और जडसकनटे िन 4.1 लाआसेंसधारी के पास हर समय स्ट्िचाजलत और मैनुऄल दोनों तरह के निीकरणीय उजाा प्रणाली के मीटररग ईपकरण और जडस्ट्कनेलटटग साधनों तक पहुचं होगी। 4.2 अपातकालीन या अईटेज की जस्ट्थजत में, जहां जस्ट्िच या ब्रेकर जैसे स्ट्िचाजलत और मैनुऄल दोनों प्रकार के जडस्ट्कनेलटटग साधनों तक पहुचं नहीं ह,ै िहा लाआसेंसधारी पात्र ईपभोक्ता के पठरसर म ेंजबजली को काट सकता ह।ै 5 दाजयत्ि 5.1 पात्र ईपभोक्ता और लाआसेंसधारी फोटोिोजल्टक प्रणाली या लाआसेंसधारी की जितरण प्रणाली के कनेटिन और संचालन म ें ककसी भी पक्ष की लापरिाही या जानबूझकर कदाचार से होन े िाल े नुकसान या प्रजतकूल प्रभािों के जलए एक-दसू रे की क्षजतपूर्तत करेंगे। 5.2 दोनों पक्ष लाभ या राजस्ट्ि की ककसी भी हाजन, व्यापार म ें रुकािट, ऄनुबंध या सद्भािना की हाजन, या ऄप्रत्यक्ष, पठरणामी, अकजस्ट्मक या जििेष क्षजतयों के जलए एक-दसू रे के प्रजत ईत्तरदायी नहीं होंगी, जजनमें ऄधय के साथ साथ दंडात्मक या कठोर क्षजत, िाजमल ह,ैं चाह ेये देनदाठरया , नुकसान या क्षजत ऄनुबधं म,ें या ऄधयथा ईत्पन्न होती ह।ै 5.3 लाआसेंसधारी अयोग द्वारा ऄपने प्रासंजगक अदेि म ें जनर्ददष्ट दायरे स े बाहर केंद्र/राज्य सरकार द्वारा प्रदान ककए गए ककसी भी जित्तीय या ऄधय प्रोत्साहन के जलए पात्र ईपभोक्ता द्वारा जितरण या िसूली के जलए ईत्तरदायी नहीं होगा। 5.4 लाआसेंसधारी ऄपन े अरपीओ को पूरा करन े के जलए निीकरणीय उजाा प्रणाली से जबजली ईत्पादन की मात्रा पर जिचार कर सकता ह।ै 6 िाजणजज्यक समझौता 6.1 आस समझौते के तहत सभी िाजणजज्यक जनपटान अयोग द्वारा जारी पूिोक्त जिजनयमों का पालन करेंगे। 7 कनटे िन की लागत 7.1 पात्र ईपभोक्ता फोटोिोजल्टक प्रणाली की स्ट्थापना से संबंजधत सभी लागतों को िहन करेगा जजसमें मीटररग और आंटरकनेटिन लागत िाजमल ह।ै प्रथम पक्ष फोटोिोजल्टक प्रणाली को जिड से जोड़ने के जलए अिश्यक सर्तिस लाआन म ें संिोधनों और ईन्नयन की िास्ट्तजिक लागत का भुगतान करने के जलए सहमत ह,ै यकद यह अिश्यक ह।ै 8 समापन 8.1 पात्र ईपभोक्ता लाआसेंसधारी को 30 कदन की पूिा सूचना देकर ककसी भी समय ऄनुबंध समाप्त कर सकता ह।ै 8.2 लाआसेंसधारी को 30 कदनों की पूिा जलजखत सूचना पर समझौते को समाप्त करने का ऄजधकार है, यकद योग्य ईपभोक्ता आस समझौते की ककसी भी िता का ईल्लंघन करता ह ै और ईल्लंघन के लाआसेंसधारी से जलजखत नोठटस प्राप्त करने के 30 कदनों के ऄंदर ईल्लघं न का समाधान नहीं करता ह।ै 8.3 पात्र ईपभोक्ता आस ऄनुबंध की समाजप्त पर, लाआसेंस जितरण प्रणाली से निीकरणीय उजाा प्रणाली को समयबद्ध तरीके से और लाआसेंसधारी की संतुजष्ट के जलए जडस्ट्कनेटट कर दगे ा। आसके साक्ष्य में, (पात्र ईपभोक्ता या तृतीय पक्ष स्ट्िामी) की और से श्री …………………………………… और26 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (लाआसेंसधारक) की ओर स े श्री …………………………………… दो मूल प्रजतयों में आस समझौते पर हस्ट्ताक्षर करत े ह।ैं पात्र ईपभोक्ता/ततृ ीय पक्ष नाम: पता: सार्तिस कनटे िन सख्ं या जितरण लाआससें धारी नाम: पद: कायाला य का पता: JOINT ELECTRICITY REGULATORY COMMISSION FOR THE UT OF JAMMU AND KASHMIR AND THE UT OF LADAKH. NOTIFICATION Jammu, the 29th May, 2023 No. JERC-JKL/REG/2023/11.—Whereas, in the exercise of powers conferred under Section 61(h), and Section 86(1) (e) read with sub-section (I) and clause (zd) and (zi) of sub-section (2) of Section 181 of the Electricity Act, 2003 (No. 36 of 2003) and all powers enabling it in that behalf, the Joint Electricity Regulatory Commission for UT of Jammu & Kashmir and UT of Ladakh hereby makes the following Regulations, namely: Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and the UT of Ladakh (Grid Interactive Renewable Energy system and its related matters) Regulations, 2023 1. Short Title, Commencement, and extent 1.1 These Regulations may be called the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and UT of Ladakh (Grid Interactive Renewable Energy system and its related matters) Regulations, 2023. 1.2 These Regulations shall come into force from the date of publication in the official gazette. 1.3 These Regulations shall extend to the UT of Jammu & Kashmir and the UT of Ladakh. 2. Definitions, Abbreviations, and Interpretations 2.1. In these Regulations, unless the context otherwise requires: (1) ―Act‖ means the Electricity Act, 2003 (36 of 2003), and subsequent amendments thereof; (2) ―Average Power Purchase Cost‖ (APPC) means the weighted average price at which the Distribution Licensee has purchased or is expected to purchase electricity (excluding procurement from RE sources), including the cost of self-generation, if any, as approved by the Commission in the relevant Retail Supply Tariff Order or any other general or specific Order; (3) ―Authority‖ means the Central Electricity Authority referred to in sub-section (1) of Section 70 of the Act; (4) ―Billing cycle‖ means the period for which regular electricity bills as specified by the Commission, are prepared for different categories of consumers by the Licensee; (5) ―COD‖ or ―Commercial Operation Date‖ or ―Date of commercial operation‖ mean the date on which the Renewable Energy system is synchronized with the grid system; (6) ―Check Meter‖ means a meter, which shall be connected to the same core of the current transformer (CT) and voltage transformer (VT) to which the Renewable Energy Meter is connected and shall be used for accounting and billing of electricity in case of failure of the main meter or Renewable Energy Meter;[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 27 (7) “Commission” means the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and UT of Ladakh constituted under the Act; (8) “Connection Agreement” means the Gross metering or net-billing (net feed-in) or net- metering inter-connection Agreement entered into between the Distribution Licensee and the Consumer; (9) “Consumer‖ means a consumer as defined in the Act; (10) ―Consumer Grievances Redressal Forum (CGRF)‖ means the forum for redressal of grievances of Consumers, established under section 42(5) of the Act; (11) "Contracted Load‖ or "Contract Demand‖ means the maximum demand in kW, kVA, or HP, agreed to be supplied by the Distribution Licensee and as indicated in the Agreement executed between the Licensee and the Consumer; (12) "Distribution Licensee‖ means a person granted a License under Section 14 (b) of the Act authorizing him to operate and maintain a distribution system and supply electricity to the consumers in his area of supply; (13) "Electricity Supply Code" means the Electricity Supply code specified by the Commission under section 50 of the Act; (14) ―Eligible Consumer‖ means a consumer of electricity in the area of supply of the Distribution Licensee, who intends to use a renewable energy system in his premises to offset all or part or no part of the own ‟s electrical requirements, given that such systems can be self- owned or third party leasing such system to the consumer; (15) ―Feed-in-Tariff‖ means the Generic Tariff determined by the Commission for the generation of electricity from Renewable Energy projects for Gross Metering or net-billing in accordance with the Terms and Conditions for Tariff determination from Renewable Energy Sources Regulation framed by the Commission; (16) “Grid” means the low voltage electrical network, the distribution, and transmission network, or the high voltage backbone system of inter-connected transmission lines, sub-stations, and generating plants, for the sale of energy or wheeling of energy as defined in these Regulations; (17) “Gross-metering” means a mechanism whereby the total energy generated from the Grid Interactive Renewable Energy system of a Prosumer and the total energy consumed by the Prosumer is accounted separately through appropriate metering arrangements and for the billing purpose; whereas, the total energy consumed by the Prosumer is accounted at the applicable retail tariff and total renewable energy generated is accounted for at feed-in tariff determined by the Commission. (18) Group Net Metering‖ means an arrangement whereby surplus energy is generated and injected from a Renewable Energy System through Net Meter and the exported energy is adjusted in more than one electricity service connection(s) of the same consumer either at the same or different premise located within the same Distribution Licensee‟s area of supply; (19) “Installed Capacity” means the summation of the nameplate capacities expressed in kWp of all the units of the Renewable Energy system or the capacity of the Renewable Energy system reckoned at the output terminals, approved by the Commission; (20) “Interconnection Point for net billing / net metering arrangement” means the interface of the Renewable Energy generating system with the outgoing terminal of the meter in the premises of the prosumer: Provided that, in case the prosumer is connected at the High Tension (HT) level, the “Interconnection Point” shall mean the interface of the Renewable Energy Generating System with the outgoing terminal of the Distribution Licensees‟ metering equipment. (21) “Interconnection Point for Gross metering arrangement” means the interface of the Renewable Energy Generating System with the incoming terminal of the meter in the premises of the prosumer: Provided that, in case the prosumer is connected at the High Tension (HT) level, the “Interconnection Point” shall mean the interface of the Renewable Energy Generating System; (22) ―Invoice‖ means a periodical Bill/Supplementary Bill or an Invoice/ Supplementary Invoice by the Distribution Licensee to the Consumer;28 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (23) ―Islanding‖ means an electrical system phenomenon in which distributed generators, powered through Renewable Energy System, continue to power a site or location in the absence of external grid power or grid outage situations. (24) ―Month‖ means English calendar month starting with 1st day/date of the month and ending with the last day/date of the month. Part Month will be applicable for a number of days in proportion to the total number of days in the specific month; (25) ―Net-billing or Net feed-in‖ means a single bidirectional energy meter used for net-billing or net feed-in at the point of supply wherein the energy imported from the Grid and energy exported from Grid Interactive Renewable Energy system of a Prosumer is valued at two different tariffs, where- (i) the monetary value of the imported energy is based on the applicable retail tariff; (ii) the monetary value of the exported Renewable energy is based on a feed-in tariff determined by the Commission; (iii) the monetary value of the exported energy is deducted from the monetary value of the imported energy to arrive at the net amount to be billed (or credited/carried over); (26) ―Net metering‖ means a mechanism whereby renewable energy exported to the grid from Grid Interactive Renewable Energy system of a Prosumer is deducted from energy imported from the Grid in units (kWh) to arrive at the net imported or exported energy and the net energy import or export is billed or credited or carried-over by the distribution licensee on the basis of the applicable retail tariff by using a single bidirectional energy meter for net- metering at the point of supply; (27) ―Net Meter‖ means an appropriate bi-directional energy meter capable of recording both imports from the grid and export of electricity generated at Renewable Energy system; (28) ―Obligated Entity‖ means the licensed Supplier of Power, Distribution Licensee(s), Captive user(s), and Open Access Consumer(s), identified under Procurement of Renewable Energy Regulations framed by the Commission; and mandated under clause (e) of subsection (1) of Section 86 of the Act to fulfill the Renewable Purchase Obligations as determined by the Commission from time to time; (29) ―Ombudsman‖ means the person appointed in accordance with Section 42 (6) read with Section 181 of the Act; (30) ―Open Access Consumer‖ means a person permitted to use an Intra-State Transmission System and /or Distribution System to receive a supply of electricity from a person other than the Distribution Licensee of his area of supply, and the expression includes a Generating Company and a Licensee, who has availed of or intends to avail of Open Access; (31) “Project Developer” means the developer of the RE Project, who shall develop such a project on his own premises or on premises taken on lease or rent; (32) “Prosumer” means a person who consumes electricity from the grid and can also inject electricity into the grid for distribution licensee, using the same point of supply. (33) ―Premises‖ means and includes roof-tops or any areas on the land, building or infrastructure, or part or combination thereof in respect of which a separate meter or metering arrangement has been provided by the distribution licensee for the supply of electricity. (34) ―Renewable Energy’’ means the grid-connected and grid-quality electricity generated from Renewable Energy sources, including a combination of such sources; (35) ―Renewable Energy Certificate (REC)‖ means the certificate issued in accordance with the Regulations and the procedures approved by the Central Electricity Regulatory Commission; (36) ―Renewable Energy Generating System‖ means the Renewable Energy power system with or without energy storage installed on a Consumer‟s premises, and owned and/or operated by such Consumer or a third party, that uses Renewable Energy for conversion into electricity; (37) ―Renewable Energy Meter‖ means the meter used for measuring the gross Renewable energy units generated by the RE Project for the purpose of accounting and billing;[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 29 (38) ―Renewable Energy sources‖ means the renewable sources or combination of such sources, such as Mini, Micro and Small Hydro, Wind, Solar, Biomass including bagasse, bio-fuel, urban or Municipal Solid Waste as defined in the Terms and Conditions for Tariff Determination from Renewable Energy Sources regulation framed by the Commission and such other sources as are recognized or approved by the Ministry of New and Renewable Energy, Government of India; (39) ―Renewable Purchase Obligations (RPO)‖ means renewable power purchase obligations specified by the Commission; (40) ―Sanctioned Load‖ means the load in kW, kVA, or HP, which the Licensee has agreed to supply from time to time subject to the governing terms and conditions in the absence of an Agreement between the Distribution Licensee and the consumer; (41) ―Settlement Period‖ means the period beginning from the first day of April as per the English calendar year and ending with the thirty-first day of March of the next year; (42) ―Solar Grid Inverter‖ means equipment that converts the DC (direct current) power from Solar Power modules to Grid-compatible AC (alternating current) power; (43) ―State Nodal Agency‖ means the agency in the concerned State or Union Territory as may be designated by the Commission to act as the agency for accreditation and recommending the renewable energy projects for registration and to undertake such functions as may be specified under clause (e) of sub-section (1) of Section 86 of the Act; (44) "Tariff Order‖ in respect of a Licensee means the applicable retail Tariff Order issued by the Commission for that Licensee indicating the tariff to be charged by the Licensee from various categories of Consumers for the supply of electrical energy and services; (45) "Third Party Owned‖ means a Renewable Energy system Project owned by a Project Developer that is installed on the roof or the Premises as defined in 1(29) above for which a commercial lease or revenue share agreement has been entered into by the Project Developer with the owner; (46) Virtual Net Metering‖ means an arrangement whereby entire energy generated from a renewable energy generation project installed at Consumer premise or any other location is injected through Solar Energy Meter and the energy exported is adjusted in either one or more than one electricity service connection(s) of participating Consumer(s) located within the same Distribution Licensee‟s area of supply; (47) ―Year‖ or ―Financial Year‖ means a period commencing on 1st April of an English calendar year and ending on 31st March of the subsequent calendar year. 2.2. Abbreviations: In these Regulations, the following shall be interpreted as: i. ―EPC‖ means Engineering Procurement & Construction Contractor authorized by the Distribution Licensee; ii. ―kWp‖ means kilo Watt peak, a term used as a rating of the Solar Plant; iii. “MNRE” means the Ministry of New and Renewable Energy of the Government of India; 2.3. All other words and expressions used in these Regulations if not specifically defined herein above, but defined in the Act, shall have the meaning assigned to them in the Act. The other words and expressions used herein but not specifically defined in these Regulations or in the Act but defined under any other law passed by the Parliament applicable to the electricity industry in the State or Union Territory shall have the meaning assigned to them in such law. 3. Scope of Regulations and Extent of Application 3.1 These Regulations would apply to: a. Gross Metering Arrangements b. Net Billing (net feed-in) Arrangements c. Net - Metering arrangements including Group Net Metering & Virtual Net Metering Provided that the gross metering or net-billing or net-metering arrangement, as the case may be for the eligible consumers shall be allowed subject to technical feasibility.30 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Provided that the Group Net Metering Framework shall be applicable to all Consumers, whereas the Virtual Net Metering Framework shall be applicable to residential consumers, Group Housing Societies, and establishments of Government/Local Authorities. 3.2 These Regulations shall be applicable to all Grid Interactive Distributed Renewable Energy generating systems that are commissioned after notification of these Regulations. 4. Eligibility Criteria 4.1 The Eligible Consumer of all categories may set up the Renewable Energy Generating System under the Net Metering Arrangement up to 500 kW capacity. Provided that the RE generating system of a rating higher than 500 kW can be considered by the Distribution Licensee if the distribution system remains stable with a higher rating RE Project gets connected to the grid. 4.2 The Eligible Consumer of all categories may set up the Renewable Energy Generating System under the Net- Billing Arrangement above 500 kW and a maximum up to 1 MW. 4.3 The Eligible Consumer of all categories may set up the Renewable Energy Generating System under the Gross Metering Arrangement maximum up to 1 MW. Provided that the distribution utilities may allow Renewable Energy generating system of rating higher than 1MW under net-billing or gross metering after conducting load flow studies and ascertaining that the installation of such higher capacity of Renewable Energy generating systems do not have any adverse impact on the grid. 4.4 Provided that the eligible consumer can opt for only one arrangement i.e., either net metering or net-billing or gross metering arrangement within the same premises, as specified in these Regulations. 4.5 The minimum size of the Renewable Energy Generating System that can be set up under Net Metering, Net- Billing, or Gross Metering Arrangement would be 1 kW. 4.6 The capacity of the RE generating system to be installed under Group Net Metering or Virtual Net Metering framework shall not be less than 5 kW and more than 500 kW. 4.7 The capacity of the Renewable Energy Generating System to be installed under Net Metering/ Group Net Metering/ Virtual Net Metering or Net-Billing or Gross Metering Arrangement at the Eligible Consumer‟s premises shall not exceed the Sanctioned load (in kW) or the Contract Demand (in kVA) of the Consumer, as applicable. 4.8 Consumers with pending arrears with the Distribution Licensee shall not be eligible for Net Metering or Net Billing or Gross Metering Arrangement under these Regulations. 4.9 Net-Metering including Group Net Metering and Virtual Net Metering or Net-Billing or Gross Metering arrangement, as the case may be, shall be permitted by the Distribution Licensee on a non-discriminatory and Distribution Transformer-wise „first come, first serve‟ basis to the Eligible Consumers who have installed or intend to install a Renewable Energy Generating System connected to the Network of such Distribution Licensee; Provided that the inter-connection of such System with the Network of the Distribution Licensee is undertaken in accordance with the standards and norms specified in the Central Electricity Authority (CEA) (Technical Standard for Connectivity of the Distributed Generation Resources) Regulations, 2013 or as may be specified in future. 5. Third-Party Owned Renewable Energy System 5.1 In the third party owned Renewable Energy system, the following conditions shall apply: a. The Consumer may lease out / rent the Rooftop Space to a Project Developer on a mutual commercial arrangement for setting up a Renewable Energy system under Net Metering including Group Net Metering and Virtual Net Metering or Net Billing or Gross Metering framework. The Consumer will pay the Project Developer for all the energy generated by the Renewable Energy system at a mutually agreed tariff. The commercial arrangement between the Project Developer and the Prosumer will be submitted to the Distribution Licensee for records and the Distribution Licensee will not have any role in a such commercial arrangement. All the provisions of the Net Metering or Net Billing or Gross Metering framework shall be applicable to the Renewable Energy system set up by a Project Developer. b. The Distribution Licensee / Nodal Agency may explore other business models that may facilitate the proliferation of Grid-connected Renewable Energy systems. For any new business model not[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 31 envisaged in these Regulations, the Commission will approve the framework for such a business model based on the specific Petition to be filed in this regard. 6. Capacity limits at the Distribution Transformer level. 6.1 The Distribution Licensee shall allow Gross Metering / Net Billing / Net Metering including Group Net Metering and Virtual Net Metering Arrangement as the case may be, to Eligible Consumers as specified in these Regulations. 6.2 The cumulative capacity of all Renewable Energy Generating Systems under Net Metering, Group Net Metering, Virtual Net Metering Arrangements, and/or Net Billing Arrangements connected to a particular Distribution Transformer/feeder of the Licensee shall be allowed up to 100% of its rated capacity. 6.3 The Distribution Licensee shall update on a yearly basis for each of the Distribution Transformers, the Distribution Transformer capacity available for connecting the Renewable Energy system and shall provide the information on its website, as well as to the Commission. 6.4 A Distribution Licensee must monitor the capacity limit of DT on a regular basis and shall refuse to connect the new RE system connection or arrangement once DT capacity reaches 100% of its rated capacity. 7. Metering Arrangement 7.1 The metering system shall be as per the Central Electricity Authority (Installation & Operation of Meters) Regulations, 2006, as amended from time to time. 7.2 All meters shall have Advanced Metering Infrastructure (AMI) facility with RS 485 (or higher) communication port or any other advanced communication facility. 7.3 Net Meter of the same accuracy class as the Consumer‟s meter existing before the commissioning of the Renewable Energy system, shall be installed in replacement of the existing meter: Provided that, if the prosumer is within the ambit of the Time-of-Day („ToD‟) Tariff, the Net Meter installed shall be capable of recording ToD consumption and generation: Provided further that such Meters may be provided by the Distribution Licensee or the Consumer, subject to the same being from the approved list of the suppliers: Provided also that if the Meter is installed by the Distribution Licensee, its cost shall be recovered from the Consumer before the COD of the Project. 7.4 The Renewable Energy Meter (a unidirectional meter) is to be installed as an integral part of the Net Metering or Net Billing or Gross Metering arrangement as the case may be, at the point at which the electricity is generated by the Renewable Energy system and delivered to the main panel. The Renewable Energy Meter shall have a facility for recording meter readings using Meter Reading Instrument (MRI) or wireless equipment. 7.5 Check Meters shall be mandatory for Renewable Energy systems having a capacity of more than 20 kW. For installations having a capacity less than or equal to 20 kW, the Check Meters would be optional: Provided that the cost of the Check Meter shall be borne by the Consumer, and such meter shall be tested and installed by the Distribution Licensee. 7.6 The Distribution Licensee shall be responsible for the installation, testing, and maintenance of the metering equipment/system and its adherence to the applicable standards and specifications. 7.7 The Meters installed, if arranged by the Consumer, shall be inspected, verified for accuracy, and sealed by the Distribution Licensee in the presence of the Consumer or its representative (if he chooses to be present at the time of testing). 7.8 The meters installed shall be jointly inspected and sealed on behalf of both the parties and shall be tested or checked only in the presence of the consumer and representatives of the Distribution licensee: Provided that the prosumer shall follow the metering specifications, and provisions for placement of the meter as provided by the Distribution licensee from time to time. 7.9 The meter reading taken by the distribution licensee shall form the basis of commercial settlement. 8. Inter-connection with the Distribution Network, Standards, and Safety 8.1 The Distribution Licensee shall ensure that the inter-connection of the Renewable Energy system with its distribution network conforms to the specifications, standards, and other provisions specified in the CEA32 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] (Technical Standard for Connectivity of the Distributed Generation Resources) Regulations, 2013, CEA (Technical Standards for Connectivity to the Grid) Regulations, 2007 including amendments thereto, the CEA (Measures relating to Safety and Electric Supply), Regulations, 2010 including amendments thereto and the Electricity Supply Code Regulations and the state grid code regulations framed by the Commission. 8.2 Renewable Energy generation with Net metering including Group Net Metering and Virtual Net Metering or Net Billing or Gross Metering arrangement will be allowed for all the eligible Consumers of the Distribution Licensee under the jurisdiction of the Commission with/without battery backup support: Provided that, if an Eligible Consumer opts for connectivity with a battery back-up, the inverter shall have a separate backup wiring to prevent the battery/ decentralized generation (DG) power from flowing into the grid in the absence of grid supply, and that an automatic as well as manual isolation switch shall also be provided. Provided further that the Inverter shall comply with the Standards prescribed in Annexure1. 8.3 The prosumer shall be responsible for the safe operation, maintenance, and rectification of any defect in the Renewable Energy system up to the point of Net Meter, beyond which point such responsibility, including in respect of the Net Meter, shall be that of the Distribution Licensee: Provided that the Renewable Energy Meter shall be maintained by the Distribution Licensee. Provided that in case of replacement of defective Net Meter or Renewable Energy Meter, it shall be provided by the prosumer, as mentioned in the proviso to Regulation 7.3 above, and installed as per relevant regulations in force as mentioned in Regulation 7.1 above. 8.4 The prosumer shall provide appropriate protection for islanding of the Renewable Energy system from the network of the Distribution Licensee in the event of grid or supply failure. 8.5 The prosumer shall be solely responsible for any accident to human being/ animals whatsoever (fatal/non- fatal/departmental/non-departmental) that may occur due to back feeding from the Renewable Energy system when the grid supply is off: Provided that the Distribution Licensee shall have the right to disconnect the Renewable Energy system from its distribution network at any time in the event of any threat of accident or damage from such Project to its distribution system, for maintenance of the distribution system so as to avoid any accident or damage to it: Provided further that the prosumer may use his Renewable Energy system in islanding mode for his own consumption. 8.6 The Distribution Licensee and prosumer shall discharge their respective duties and responsibilities as specified in the relevant Regulations of the Central Electricity Authority. 8.7 HT Consumers opting for Net Metering shall not be required to provide separate connectivity for the Renewable Energy system at the HT voltage level for consumption at LT Level. 9. Communication Facilities 9.1 All grid interactive Renewable Energy systems shall have electricity meters with features to record energy for data storage for injection into the grid through Energy Meter as provided under these Regulations: Provided that all projects shall have a communication port for exchanging real-time information with the Distribution Licensee: Provided further that all Meters shall have Advanced Metering Infrastructure (AMI) facility. 10. Billing, Energy Accounting and Settlement 10.1 Net Metering Arrangement a. The accounting of electricity exported from the Renewable Energy system and imported from the Grid by the prosumer shall become effective from the date of connectivity of the Renewable Energy system with the distribution network. b. The Distribution Licensee shall undertake meter readings of both, the Renewable Energy Generation Meter and the Net Meter, for all prosumers, according to the regular billing cycle. c. For each billing period, the Distribution Licensee shall show separately: - i. Quantum of Renewable Energy generation recorded in the Renewable Energy Generation Meter in the billing period, including opening and closing balance[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 33 ii. Quantum of electricity Units exported by the prosumer, including opening and closing balance; iii. Quantum of electricity Units imported by the prosumer, including opening and closing balance; iv. Net quantum of electricity Units billed for payment by the prosumer; and v. Net quantum of electricity Units carried over (if surplus) to the next billing period; vi. Units from Renewable Energy generation used by the Distribution Licensee for RPO compliance. d. The energy generated by the Renewable Energy Generating Station shall be offset against the energy consumption of the consumer from the Distribution Licensee in the following manner: i. If the quantum of electricity exported exceeds the quantum imported during the billing period, the excess quantum shall be carried forward to the next billing period as credited Units of electricity; ii. If the quantum of electricity Units imported by the prosumer during any billing period exceeds the quantum exported, the Distribution Licensee shall raise its bill for the net electricity consumption after adjusting the credited Units as per applicable Tariff Order. iii. In case the prosumer is within the ambit of the Time of Day (ToD) tariff, the electricity consumption in any time block, i.e., peak hours, off-peak hours, etc., shall be first compensated with the quantum of electricity injected in the same time block: Provided that any excess injection over and above the consumption in any other time block in a billing cycle shall be accounted as if the excess injection had occurred during off-peak hours. e. The unadjusted net credited Units of electricity at the end of each financial year shall be considered as units purchased by the Distribution Licensee at the Average Power Purchase cost of the concerned Distribution Licensee or Feed-in-Tariff determined for that Year whichever is lower. Provided that, at the beginning of each Settlement Period, the cumulative quantum of injected electricity carried forward will be re-set to zero. f. The Distribution Licensee shall compute the amount payable to the prosumer, latest by April 30th of the following year for the unadjusted net credited Units purchased by it during the financial year as specified in Regulation 10.1(e), and shall pay the amount to the eligible consumer by May 31st of the following year. g. The Distribution licensee in addition to consumer tariff shall be eligible to raise the bill for any other charges as allowed by the Commission and any tax/duty/cess imposed by the Government. h. The consumer whose entitlement as a consumer of the licensees is ceased or he is not settling his dues to the licensee, shall not be entitled to receive the due amount of the adjustment/credit. i. The prosumer shall have recourse, in case of any dispute with the Distribution Licensee regarding billing, to the mechanism specified by the Commission under Sections 42 (5) to (7) of the Act for the redressal of grievances. 10.2 In the case of Group Net Metering, the billing and energy accounting shall be dealt with as under: a. Where the export of units during any billing period exceeds the import of units at the connection where the renewable energy generating Project is located, such surplus units injected into the grid shall be adjusted against the energy consumed in the monthly bill of service connection(s) in a sequence indicated in the priority list provided by the Consumer. The sequence of priority for adjustment shall be deemed to have begun with the service connection where the renewable energy generating Project is located; b. The priority list for adjustment of the balance surplus energy against other electricity connection(s) may be revised by the Consumer once at the beginning of every financial year with an advance notice of two months; c. The electricity consumption in any time block (e.g., peak hours, off-peak hours, etc.) shall be first compensated with the electricity generation in the similar time blocks in the same billing cycle of the Consumer where the renewable energy generating Project is located, and any surplus units injected shall be adjusted against the energy consumed in the monthly bill of service connection(s) in a sequence indicated in the priority list provided by the Consumer, as if the surplus generation/ Energy34 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Credits occurred during the off-peak time block for Time of Day (ToD) Consumers and normal time block for Non-ToD Consumer; d. Where during any billing period, the export of units either in Non-ToD Tariff or ToD Tariff exceeds the import of units by the electricity service connection(s), such surplus units injected by the Consumer shall be carried forward to the next billing period as energy credit and shown as energy exported by the Consumer for adjustment against the energy consumed in subsequent billing periods within the Settlement Period in the sequence indicated in the priority list; e. For unadjusted net credited Units of electricity at the end of each financial year, the provisions of Clause 10.1 (e) will be applicable for the connection where the renewable energy generating Project is located. 10.3 In case of Virtual Net Metering, the billing and energy accounting shall be dealt with as under: a. The energy generated from the renewable energy generating Project shall be credited in the monthly electricity bill of each participating consumer(s) as per the ratio of procurement from renewable energy generating Project indicated under the agreement/MoU entered on a stamp paper by the Consumer(s) and submitted to the Distribution Licensee; b. The Consumer(s) shall have the option to change the share of credit of electricity from renewable energy generating Project by submitting a fresh Agreement/MoU on a stamp paper subject to the ratio of procurement from renewable energy generating Project indicated under the agreement/MoU entered by the Consumer(s) once at the beginning of the financial year with an advance notice of two months; c. Where the service connection of any participating consumer(s) is disconnected due to any reason under any law for the time being in force, the unadjusted units/remaining credits of that consumer shall be paid by the Distribution Licensee at the end of the financial year; d. The electricity consumption in any time block (e.g., peak hours, off-peak hours, etc.) shall be first compensated with the electricity generation in the similar time blocks in the same billing cycle of the participating consumer(s). Any surplus generation over consumption in any time block in a billing cycle shall be accounted as if the surplus generation/ Energy Credits occurred during the off-peak time block; e. Where the units credited during any billing period of any participating Consumer exceeds the import of units by that consumer, such surplus credited units shall be carried forward in the next billing period as energy credits for adjustment against the energy consumed in subsequent billing periods within the settlement period of each participating Consumer(s); f. For unadjusted net credited Units of electricity at the end of each financial year, the provisions of Clause 10.1 (e) will be applicable for each participating Consumer(s). 10.4 Net Billing Arrangement a. Net billing is the arrangement where the Renewable Energy Generating system is: i. Connected on the consumer side of the net meter, ii. Selling excess power after meeting own requirement (export of power) to a Distribution Licensee at feed–in tariff approved by the Commission: iii. Import of power if any from the distribution licensee shall be charged as per applicable Tariff Order. b. The Distribution Licensee shall undertake meter readings of both, the Renewable Energy Generation Meter and the Net Meter, as applicable, according to the regular billing cycle. c. For each Billing Period, the Distribution Licensee shall make the following information available on its bill to the Eligible Consumer: i. Quantum of Renewable Energy generation recorded in the Renewable Energy Generation Meter, including opening and closing balance; ii. Quantum of electricity units exported to the grid by the prosumer in the billing period, including opening and closing balance; iii. Quantum of electricity units imported from the grid by the prosumer in the billing period, including opening and closing balance;[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 35 iv. Amount of billing credit, if any, in the billing period, including opening and closing balance; v. Units from Renewable Energy generation used by the Distribution Licensee for RPO compliance. d. The Distribution Licensee shall raise the net bill as per the billing cycle after accounting for the units exported by the Renewable Power Developer at feed–in tariff approved by the Commission and after accounting for units imported from grid at applicable Tariff Order. e. The Distribution Licensee shall raise bill on the prosumer in accordance with the following equation: Energy Bill of consumer = Fixed Charges + other applicable charges and levies + ( x ) - ( * ) – Billing Credit (Carried forward from last billing cycle); Where: i. Fixed Charges means the Fixed/Demand Charges as applicable to the consumer category as per the applicable retail supply Tariff Order; ii. Other applicable charges and levies mean any other charges such as duty, cess, etc.; iii. means the imported energy units from the Distribution Licensee as recorded by in the bidirectional meter for the billing period; iv. means the applicable retail supply tariff of the concerned consumer category as per the applicable Tariff Order of the Commission; v. means the export energy units recorded for the billing period by the bidirectional meter; vi. means the feed–in tariff approved by the Commission as per the Agreement entered between the Consumer and Distribution Licensee, in accordance with Regulation 16; vii. Billing Credit is the amount by which the value of exported Renewable Energy generation in a particular month is more than the value of imported units from the distribution licensee including all other components of the consumer bill. f. In case the consumer is subjected to time-of-day tariffs, the energy bill ( x ) shall be computed accordingly. g. In case ( * ) is more than {Fixed charges + other applicable charges and levies + ( x )}, the utility shall give credit of an amount equal to the difference (Billing Credit), which shall be carried forward to the next billing cycle. No interest shall be payable by Distribution Licensee on such credit amount carried forward. h. The net bill amount for a billing period, if payable by the prosumer, then the same shall be paid by the prosumer within the due date of the bill. i. At the end of each Financial Year, any amount payable by Distribution Licensee remaining unadjusted during the financial year shall be paid to the prosumer latest by the end of May of the following Financial Year. j. The consumer whose entitlement as a consumer of the licensees is ceased or he is not settling his dues with the licensee, shall not be entitled to receive the due amount of the adjustment/credit. k. The prosumer shall have recourse, in case of any dispute with the Distribution Licensee regarding billing, to the mechanism specified by the Commission under Sections 42 (5) to (7) of the Act for the redressal of grievances. 10.5 Gross Metering Arrangement a. The Distribution Licensee shall undertake meter readings of both, the Renewable Energy Generation Meter and the Consumer Meter for all prosumers, according to the regular billing cycle. b. For each billing period, the distribution licensee shall make the following information available on its bill to the prosumer:36 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] i. Quantum of Renewable Energy generation recorded in the Renewable Energy Generation Meter, including opening and closing balance; ii. Quantum of electricity units consumed from the grid by the prosumer in the billing period, including opening and closing balance; iii. Units from Renewable Energy generation used by the Distribution Licensee for RPO compliance c. The energy accounting and settlement procedure for consumers installing and operating Renewable Energy systems under gross metering arrangement shall be as per the following procedure: i. For each billing period, the Licensee shall show the quantum of electricity injected by the Renewable Energy System installed at the premises of the prosumer in the billing period. ii. The Distribution Licensee shall reimburse the prosumer for the quantum of injected electricity by the Renewable Energy System during the billing period at the Feed-in-Tariff determined by the Commission for that year. Provided further that, the above Tariff shall be applicable for the entire duration of the Agreement. iii. For each billing period, the Licensee shall show the quantum of electricity consumed from the grid by the prosumer in the billing period. iv. The Distribution Licensee shall prepare the bill for energy consumed from the grid as per the Tariff Order approved by the Commission including fixed Charges /Demand Charges and other applicable charges and levies as applicable to the consumer category as per the applicable Tariff Order; v. The Distribution licensee shall prepare the net bill according to the amount payable by the licensee to the prosumer and amount payable by the prosumer to the licensee for the energy consumed from the grid. vi. The net amount payable by the licensee or the prosumer, as the case may be, shall be paid within the due date mentioned in the bill. d. The consumer whose entitlement as a consumer of the licensees is ceased or he is not settling his dues with the licensee, shall not be entitled to receive the due amount. e. The prosumer shall have recourse, in case of any dispute with the Distribution Licensee regarding billing, to the mechanism specified by the Commission under Sections 42(5) to (7) of the Act for the redressal of grievances. 11. Penalty or Compensation – Failure of the Metering System 11.1 In case of failure of metering system, the provisions of penalty or compensation shall be as per the provisions of the Standards of Performance for Distribution Licensees Regulations regulation framed by the Commission for the Distribution Licensee. 11.2 In case of failure to meet the timelines prescribed under these Regulations, the distribution licensee shall be liable to pay compensation to the consumer as specified under Regulation 15.1 (l) below. 12. Late Payment Surcharge In case the payment by the Distribution Licensee under Regulation 10.1 (e) and Regulation 10.2 (a) above, is delayed beyond 31st of May of that year, a Late Payment Surcharge at the rate of 1.25% per month from the delay beyond 31st May shall be levied on the Distribution Licensee. 13. Charges for Banking of RE Power The Renewable Energy Projects, whether self-owned or third-party owned installed under these Regulations, shall be exempted from charges in respect of banking of electricity. 14. Renewable Purchase Obligation and Eligibility to Participate under REC Mechanism 14.1 The quantum of electricity consumed by the prosumer from the Renewable Energy Project under the Net Metering Arrangement shall qualify towards his compliance of RPO, if such prosumer is an Obligated Entity. 14.2 The quantum of electricity consumed by the prosumer from the Renewable Energy Project owned[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 37 and installed under the Net Metering arrangement shall, if such prosumer is not an Obligated Entity, qualify towards meeting the RPO of the Distribution Licensee. 14.3 The unadjusted net credited Units of Renewable Energy purchased by the Distribution Licensee under the provisions of Regulation 10.1 (e) above, shall also qualify towards meeting its RPO. 14.4 In case of Net Billing or Gross Metering arrangement, the entire quantum of electricity recorded by the Generation Meter shall qualify towards meeting the RPO of the Distribution Licensee. 14.5 The Renewable Energy generated by any prosumer under these Regulations shall not be eligible for REC. 15. Procedure for Application and Registration 15.1. The distribution licensee shall facilitate the process for setting up of Renewable Energy generation system at consumers‟ premises. In this regard, the licensee shall: a. Create an online portal for receiving applications from consumers for installation, interconnection, and metering of distributed Renewable Energy systems or devices, at their premises, and update the same on a regular basis. b. Prominently display on its website and in all its offices, the following namely: - (i) detailed standardized procedure in details for installation and commissioning of Renewable Energy system under gross metering / net billing/ net metering arrangement; (ii) a single point of contact to facilitate the consumers in the installation of such Renewable Energy systems from submission of application form to commissioning; (iii) address and telephone numbers of offices where filled-up application forms can be submitted; (iv) complete list of documents required to be furnished along with such applications; (v) applicable charges to be deposited by the applicant; (vi) empanelled list of service providers for the benefit of consumers who want to install such Renewable Energy systems through service providers; and (vii) financial incentives to the consumers, as applicable under various schemes and programmes of the Central and State Governments. c. The Distribution licensee shall make the form available on its website and through a hard copy at its local offices. d. The consumer of the premises shall submit the application to connect its Renewable Energy system to the distribution system of the licensee in the specified form as Annexure-2 to the Regulation along with a processing fee of Rs. 500 (Rupees Five Hundred Only) at the local office of the concerned Distribution licensee or online through Web portal of Distribution Licensees. e. In case, the application form is submitted in hard copy, it will be received, and acknowledgement with the registration number for that application shall be generated. The same shall be scanned and uploaded on the website as soon as it is received. In case, the application form is received online through web portal of the distribution licensee, the acknowledgement with the registration number shall be generated on submission of application. Application shall be deemed to be received on the date of generation of acknowledgement with registration number; and the application tracking mechanism based on the unique registration number shall be provided by the distribution licensee through a web-based application or any other mode to monitor the status of the processing of the application like receipt of the application, site inspection, meter installation, and commissioning, etc. f. Within 20 days, the licensee shall complete the technical feasibility study and shall communicate to the applicant through email/SMS/post, the sanction /rejection of the application, as the case may be, along with the estimated amount to be deposited and the copy of the agreement to be executed by the consumer. g. On receipt of full payment, the Distribution Licensee shall approve the application and intimate the same to the applicant by providing a Letter of Approval (LoA) via email/SMS/post, within thirty (30) days from the issuance of acknowledgement of the application. h. During the time period from the feasibility study till the completion of installation, in case, there is any requirement of upgradation of distribution infrastructure like augmentation of the service line, distribution transformer capacity, etc., for installation of the required capacity of Renewable Energy system, the same shall be carried out by the distribution licensee or consumer, as the case may be.38 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] i. After installation of the Renewable Energy system, the prosumer shall submit the installation certificate to the distribution licensee. The licensee shall complete the signing of the connection agreement, installation of the meter, and successful commissioning of the Renewable Energy system within thirty days from the date of submission of the installation certificate. Formats of connection agreement and installation certificate shall be placed on the web portal of the distribution licensee within thirty days of notification of these Regulations. j. The Prosumer shall have the option of purchasing the requisite meter himself which shall be tested and installed by the distribution licensee. k. The timelines as specified above in these Regulations shall be adhered to by the distribution licensee. In case of delay, the licensee may take approval from the Commission in specific cases along with justification for the same. l. In case of any delay on the part of the distribution licensee without any just cause, the Licensee shall be liable to pay compensation to the consumer at a rate of Rs.100 (Rupees one hundred only) per day for each day of default. m. The distribution licensee shall pass on the financial incentives to the prosumers, as may be provided under various schemes and programs of the Central and State Governments. n. In case of any billing dispute, the prosumer may approach to the Electricity Consumer Grievance Redressal Forum of the concerned Distribution licensee. Miscellaneous 16. Connection Agreement The Distribution Licensee and Eligible Consumer shall enter into a Net Metering or Net Billing or Gross Metering Connection Agreement, as the case may be, after approval of connectivity of the Renewable Energy Generating System with the distribution Network but before the start of actual generation from the System. The model connection agreements for Net Metering, Net Billing, and Gross Metering Arrangement are provided in Annexure 3, Annexure 4, and Annexure 5 respectively. The distribution licensee in consultation with JAKEDA shall develop a similar connection agreement for the consumers willing to avail of the Group Net metering or Virtual Net Metering facility as allowed under these Regulations and take prior approval of the Commission before entering into the same. The model regulations developed by the Ministry of New and Renewable Energy, GoI ( F No 318/13/2022-GCRT) dated 04.08.2022 may be referred to in this regard. 17. Power to relax The Commission may by general or special order, for reasons to be recorded in writing, and after giving an opportunity of hearing to the Parties likely to be affected, relax any of the provisions of these Regulations on its own motion or on an application made before it by an interested person. 18. Power to amend The Commission may at any time add, vary, alter, suspend, modify, amend or repeal any of the provisions of these Regulations. 19. Repeal and Savings Same as otherwise provided in these Regulations, JERC for the state of Goa and UTs (Solar PV Grid Interactive System based on Net Metering) Regulations, 2019, together with amendments made from time to time, are hereby repealed: Provided that for all purposes, including review matters pertaining to the period till notification of these Regulations, the issues relating to Net Metering shall be governed by the provisions of the JERC for state of Goa and UTs (Solar PV Grid Interactive System based on Net Metering) Regulations, 2019, including amendments thereto, as may be applicable. 20. Power to remove difficulties In case of any difficulty arising while giving effect to the provisions of these Regulations, the Commission may either Suo-Moto or on a Petition, by an order, make such provisions not inconsistent with the provisions of the Act as may appear to be necessary. By Order of the Commission V. K. DHAR, (JKAS), Secy. [ADVT.-III/4/Exty./157/2023-24][भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 39 Annexure 1 Voltage level Harmonics, Standards: Harmonics & Inverter Harmonics shall be as per IEEE 519 Standards. The permissible individual harmonics level shall be less than 3% (for both voltage and current harmonics) and Total Harmonics Distortion (THD) for both voltage and current harmonics of the Grid system shall be less than 5%. Inverter Standards The Inverter should comply with IEC 61683/IS 61683 for efficiency and Measurements and should comply with IEC 60068-2 (1, 2, 14, 30) / Equivalent BIS Standard for environmental testing. Inverter should supervise the grid condition continuously and in the event of grid failure (or) under voltage (or) over voltage, Solar Plant should be disconnected by the circuit Breaker / Auto switch provided in the Inverter. Various Other Standards Parameter Reference Requirements Sl. Overall 1. conditions of State Distribution/Supply Code State Distribution/Supply Code Service Central Electricity Authority Overall Grid Central Electricity Authority (Grid 2. (Grid Standard) Regulations Standards Standard) Regulations 2010 2010 3. Equipment BIS / IEC / IEEE BIS / IEC / IEEE Central Electricity Authority Central Electricity Authority (Installation & operation of (Installation & operation of meters) 4. Meters meters) Regulation 2006 as Regulation 2006 as amended from amended from time to time time to time Central Electricity Authority Central Electricity Authority Safety and (Measures relating to Safety 5. (Measures relating to Safety and supply and Electricity Supply) Electricity Supply) Regulations, 2010 Regulations, 2010 Harmonic IEEE 519 IEEE 519 Requirements CEA (Technical Standards for CEA (Technical Standards for 6. Connectivity of the Distributed Connectivity of the Distributed Harmonic Generation Generation Resources) Regulations Current Resources) Regulations 2013. 2013. IEEE 519 Solar Plant must be equipped with a grid frequency synchronization device. Every CEA (Technical Standards for time the generating station is 7. Synchronization Connectivity of the Distributed synchronized to the electricity system. It Generation Resources) shall not cause voltage fluctuation greater Regulations 2013 than +/- 5% at the point of connection. The voltage-operating window should IEEE 519 minimize nuisance tripping and should CEA (Technical Standards for be under operating range of 80% to 8. Voltage Connectivity of the Distributed 110% of the nominal connected voltage. Generation Resources) Beyond a clearing time of 2 second, the Regulations 2013 Solar Plant must isolate itself from the grid.40 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Various Other Standards Parameter Reference Requirements Sl. IEEE 519 Operation of Solar Plant should not CEA (Technical Standards for cause voltage flicker in excess of the 9. Flicker Connectivity of the Distributed limits stated in IEC 61000 standards or Generation Resources) other equivalent Indian standards, if Regulations 2013 any. When the Distribution system IEEE 519 frequency deviates outside the specified CEA (Technical Standards for conditions (50.5 Hz on the upper side 10. Frequency Connectivity of the Distributed and 47.5 Hz on the lower side), There Generation Resources) should be over and under frequency trip Regulations 2013 functions with a clearing time of 0.2 seconds. Should not inject DC power more than IEEE 519 0.5% of full rated output at the CEA (Technical Standards for interconnection point or 11. DC injection Connectivity of the Distributed 1% of rated inverter output current into Generation Resources) the distribution system under any Regulations 2013 operating condition. IEEE 519 While the output of the inverter is CEA (Technical Standards for greater than 50%, a lagging power 12. Power Factor Connectivity of the Distributed factor of greater than 0.9 should Generation Resources) operate. Regulations 2013 IEEE 519 The Solar Project in the event of a Islanding and CEA (Technical Standards for fault, voltage, or frequency variations 13. Disconnection Connectivity of the Distributed must island/disconnect itself within IEC Generation Resources) standard on astipulated period. Regulations 2013 IEEE 519 The inverter should have the facility to Overload and CEA (Technical Standards for automatically switch off in case of 14. Overheat Connectivity of the Distributed overload or overheating and should Generation Resources) restart when normal conditions are Regulations 2013 restored. IEEE 519 Paralleling device of Solar System shall Paralleling CEA (Technical Standards for be capable of withstanding 220% of the 15. Device Connectivity of the Distributed normal voltage at the interconnection Generation Resources) point. Regulations 2013 16. Note: The standards/specifications shall be subject to amendments/revisions from time to time by the Distribution Licensee and the State Agency on respective websites. ANNEXURE-2 Model Application Form for installation of Renewable Energy System under Net Metering/Net Billing/Gross Metering arrangement Name of Distribution Licensee [ ] Name of Administrative Office [ ] (To be filled by the Applicant in Block Letters)[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 41 1. Applicant‟s Full Name : 2. Address of the premises at which Renewable Energy System / Project is to be installed.: 3. Telephone/Mobile No. : 4. E-mail ID (if available) : 5. Alternate Address for communication (if any) : 6. Category of existing electricity connection : 7. Consumer No. : 8. Sanctioned Load / Contract Demand : (in kW /kVA/ HP). 9. Voltage at which existing supply has been given (in volts). : 10. Proposed AC capacity of Renewable Energy System to be installed (in kW): 11. Voltage at the output of Solar inverter : (in volts), if applicable. 12. Details of Registration Fee paid : (Rs. 500/-). Date: ____________________ Signature of Applicant. Application No. _____________________________________ Date of Receipt: ____________________________________________ List of documents attached with Application Form 1. Copy of the latest paid electricity bill. 2. General Power of Attorney in favor of signatory in case of Partnership Firms; certified true copy of the Resolution, authorizing the signatory to deal with the concerned Distribution Licensee, passed by the Board of Directors in case of Companies (as applicable). 3. Technical details of PV modules, Inverter and other equipment of system proposed to be installed. 4. Proof of payment of Registration Fee. ....…………………………………………………………………………………………………... ACKNOWLEDGEMENT Received an Application from .............................................. for connectivity/installation of Renewable Energy System of capacity of ............................................................ kW as per details below: - Capacity of Existing Consumer Date of Receipt Applicant‟s Name Application Number Renewable Energy No. System (1) (2) (3) (4) (5) Date: (Signature and Designation of Authorized Officer). ANNEXURE – 3 Model Net Metering Connection Agreement This Agreement is made and entered into at (location)_________________on this (date)_______ day of (month)________(year)____________ between the Eligible Consumer (Name)___________________________________having premises at (address)___________________________________________________________and Consumer No. __________________________________as the first Party, AND The Distribution Licensee __________________________________________ (hereinafter referred to as „the Licensee‟) and having its Registered Office at (address)_____________________________as second Party of this Agreement; Whereas, the Eligible Consumer has applied to the Licensee for approval of a Net Metering42 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Arrangement under the provisions of the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and UT of Ladakh (Grid Interactive Renewable Energy system and its related matters) Regulations, 2023 (hereinafter referred to as „the Net Metering Regulations‟) and sought its connectivity to the Licensee‟s Distribution Network; And whereas, the Licensee has agreed to provide Network connectivity to the Eligible Consumer for injection of electricity generated from its Renewable Energy system of _______________ kilowatt; Both Parties hereby agree as follows: - 1. Eligibility The Renewable Energy Project meets the applicable norms for being integrated into the Distribution Network, and the Eligible Consumer shall maintain the Project accordingly for the duration of this Agreement. 2. Technical and Inter-connection Requirements 2.1. The metering arrangement and the inter-connection of the Renewable Energy Project with the network of the Licensee shall be as per the provisions of the Net Metering and the technical standards and norms specified by the Central Electricity Authority for connectivity of distributed generation resources and for the installation and operation of meters. 2.2. The Eligible Consumer agrees, that he shall install, prior to connection of the Renewable Energy Project to the network of the Licensee, an isolation device (both automatic and in built within inverter and external manual relays); and the Licensee shall have access to it if required for the repair and maintenance of the Distribution Network. 2.3. The Licensee shall specify the interface/inter-connection point and metering point. 2.4. The Eligible Consumer shall furnish all relevant data, such as voltage, frequency, circuit breaker, isolator position in his System, as and when required by the Licensee. 3. Safety 3.1. The equipment connected to the Licensee‟s Distribution System shall be compliant with relevant International (IEEE/IEC) or Indian Standards (BIS), as the case may be, and the installation of electrical equipment shall comply with the requirements specified by the Central Electricity Authority regarding safety and electricity supply. 3.2. The design, installation, maintenance, and operation of the Renewable Energy Project shall be undertaken in a manner conducive to the safety of the Renewable Energy Project as well as the Licensee‟s Network. 3.3. If,- at any time, the Licensee determines that the Eligible Consumer‟s Renewable Energy Project is causing or may cause damage to and/or results in the Licensee‟s other Consumers or its assets, the Eligible Consumer shall disconnect the Renewable Energy Project from the distribution network upon direction from the Licensee, and shall undertake corrective measures at his own expense prior to re- connection. 3.4. The Licensee shall not be responsible for any accident resulting in injury to human beings or animals or damage to property that may occur due to back-feeding from the Renewable Energy Project when the grid supply is off. The Licensee may disconnect the installation at any time in the event of such exigencies to prevent such accident. 4. Other Clearances and Approvals The Eligible Consumer shall obtain any statutory approvals and clearances that may be required, such as from the Electrical Inspector or the municipal or other authorities, before connecting the Renewable Energy Project to the distribution Network. 5. Period of Agreement, and Termination This Agreement shall be for a period of 20 years, but may be terminated prematurely, a) By mutual consent; or b) By the Eligible Consumer, by giving 30 days‟ notice to the Licensee; c) By the Licensee, by giving 30 days‟ notice, if the Eligible Consumer breaches any terms of this Agreement or the provisions of the Net Metering Regulations and does not remedy such breach within 30 days, or such other reasonable period as may be provided, of receiving notice of such breach, or for any other valid reason communicated by the Licensee in writing. 6. Access and Disconnection 6.1. The Eligible Consumer shall provide access to the Licensee to the metering equipment and disconnecting devices of Renewable Energy Project, both automatic and manual, by the Eligible[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 43 Consumer. 6.2. If, in an emergent or outage situation, the Licensee cannot access the disconnecting devices of the Renewable Energy Project, both automatic and manual, it may disconnect the power supply to the premises. 6.3. Upon termination of this Agreement under Clause 5, the Eligible Consumer shall disconnect the Renewable Energy Project forthwith from the Network of the Licensee. 7. Liabilities 7.1. The Parties shall indemnify each other for damages or adverse effects of either Party‟s negligence or misconduct during the installation of the Renewable Energy Project, connectivity with the distribution network, and operation of the System. 7.2. The Parties shall not be liable to each other for any loss of profits or revenues, business interruption losses, loss of contract or goodwill, or for indirect, consequential, incidental or special damages including, but not limited to, punitive or exemplary damages, whether any of these liabilities, losses or damages arise in contract, or otherwise. 8. Commercial Settlement 8.1. The commercial settlements under this Agreement shall be in accordance with the Net Metering Regulations. 8.2. The Licensee shall not be liable to compensate the Eligible Consumer if his Renewable Energy Project is unable to inject surplus power generated into the Licensee‟s Network on account of the failure of power supply in the grid/Network. 8.3. The existing metering System, if not in accordance with the Net Metering Regulations, shall be replaced by a bi- directional meter (whole current/CT operated), and a separate generation meter may be provided to measure Renewable Energy generation. The bi-directional meter (whole current/CT operated) shall be installed at the inter-connection point to the Licensee‟s Network for recording the export and import of energy. 8.4. The uni-directional and bi-directional meters shall be fixed in separate meter boxes in the same proximity. 8.5. The Licensee shall issue monthly electricity bill for the net metered energy on the scheduled date of meter reading. If the exported energy exceeds the imported energy, the Licensee shall show the net energy exported as credited Units of electricity as specified in the Net Metering Regulations. If the exported energy is less than the imported energy, the Eligible Consumer shall pay the Distribution Licensee for the net energy imported at the prevailing tariff approved by the Commission for the Consumer category to which he belongs. 9. Connection Costs The Eligible Consumer shall bear all costs related to the setting up of the Renewable Energy Project, excluding the Net Metering Arrangement cost beyond the Net Meter. 10. Dispute Resolution 10.1. Any dispute arising under this Agreement shall be resolved promptly, in good faith and in an equitable manner by both the Parties. 10.2. Disputes pertaining to billing / payments and metering shall be referred to the Consumer Grievances Redressal Forum (CGRF) and then to the Ombudsman appointed under sub-section 6 of Section 42 of the Act for settlement in case the same is not resolved at CGRF. In the witness, where of (Name) _________________________________for and on behalf of Eligible Consumer and (Name) ______________________________ for and on behalf of (Licensee) agree to this agreement. Annexure-4 Model Net Billing Connection Agreement This Agreement is made and entered into at (location)______________ on this (date)___________day of (month)________(year)____________between the Eligible Consumer (Name)_____________________________________________having premises at (address) _________________________________________________and Consumer No. _______________ as the Party, AND44 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] the Distribution Licensee _________________ (hereinafter referred to as „the Licensee‟) and having its Registered Office at (address) _______________________________________________________ as the second Party of this Agreement. Whereas the Eligible Consumer has applied to the Licensee for approval of a Net Billing Arrangement under the provisions of the Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and UT of Ladakh (Grid Interactive Renewable Energy system and its related matters) Regulations, 2023 and sought its connectivity to the Licensee‟s distribution Network; And whereas the Licensee has agreed to provide Network connectivity to the Eligible Consumer for injection of electricity generated from its Renewable Energy Generating System of ________kilowatt; Both Parties hereby agree as follows: 1 Eligibility The Renewable Energy Generating System meets the applicable norms for being integrated into the distribution network, and the Eligible Consumer shall maintain the System accordingly for the duration of this Agreement. 2 Technical and Inter-Connection Requirements 2.1 The metering arrangement and the inter-connection of the Renewable Energy Generating System with the Network of the Licensee shall be as per the provisions of the aforesaid Regulations and the technical standards and norms specified by the Central Electricity Authority for connectivity of distributed generation resources and for the installation and operation of meters, the Eligible Consumer agrees, that he shall install, prior to connection of the Renewable Energy Generating System to the Network of the Licensee, an isolation device (both automatic and in-built within inverter and external manual relays); and the Licensee shall have access to it if required for the repair and maintenance of the distribution Network. 2.2 The Licensee shall specify the interface/inter-connection point and metering point. 2.3 The Eligible Consumer shall furnish all relevant data, such as voltage, frequency, circuit breaker, isolator position in his System, as and when required by the Licensee. 3 Safety 3.1 The equipment connected to the Licensee’s distribution System shall be compliant with relevant International (IEEE/IEC) or Indian standards (BIS), as the case may be, and the installation of electrical equipment shall comply with the requirements specified by the Central Electricity Authority regarding safety and electricity supply. 3.2 The design, installation, maintenance, and operation of the Renewable Energy Generating System shall be undertaken in a manner conducive to the safety of the Renewable Energy Generating System as well as the Licensee’s Network. 3.3 If, at any time, the Licensee determines that the Eligible Consumer’s Renewable Energy Generating System is causing or may cause damage to and/or results in the Licensee’s other consumers or its assets, the Eligible Consumer shall disconnect the Renewable Energy Generating System from the distribution Network upon direction from the Licensee, and shall undertake corrective measures at his own expense prior to re- connection. 3.4 The Licensee shall not be responsible for any accident resulting in injury to human beings or animals or damage to property that may occur due to back-feeding from the Renewable Energy Generating System when the grid supply is off. The Licensee may disconnect the installation at any time in the event of such exigencies to prevent such accident. 4 Other Clearances and Approvals The Eligible Consumer shall obtain any statutory approvals and clearances that may be required, such as from the Electrical Inspector or the municipal or other authorities, before connecting the Renewable Energy Generating System to the distribution Network. 5 Period of Agreement, and Termination 5.1 This Agreement shall be for a period for 20 years, but may be terminated prematurely a) By mutual consent; or b) By the Eligible Consumer, by giving 30 days‟ notice to the Licensee;[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 45 c) By the Licensee, by giving 30 days‟ notice, if the Eligible Consumer breaches any terms of this Agreement or the provisions of the Net Metering Regulations and does not remedy such breach within 30 days, or such other reasonable period as may be provided, of receiving notice of such breach, or for any other valid reason communicated by the Licensee in writing; d) By the Licensee, by giving 30 days‟ notice, if the Eligible Consumer fails to pay his dues in a timely manner or indulges in any malpractices. 6 Access and Disconnection 6.1 The Eligible Consumer shall provide access to the Licensee to the metering equipment and disconnecting devices of Renewable Energy Generating System, both automatic and manual, by the Eligible Consumer. 6.2 If, in an emergent or outage situation, the Licensee cannot access the disconnecting devices of the Renewable Energy Generating System, both automatic and manual, it may disconnect the power supply to the premises. 6.3 Upon termination of this Agreement under Clause 5, the Eligible Consumer shall disconnect the Renewable Energy Generating System forthwith from the Network of the Licensee. 7 Liabilities 7.1 The Parties shall indemnify each other for damages or adverse effects of either Party‟s negligence or misconduct during the installation of the Renewable Energy Generating System, connectivity with the distribution Network and operation of the System. 7.2 The Parties shall not be liable to each other for any loss of profits or revenues, business interruption losses, loss of contract or goodwill, or for indirect, consequential, incidental or special damages including, but not limited to, punitive or exemplary damages, whether any of these liabilities, losses or damages arise in contract, or otherwise. 8 Commercial Settlement 8.1 The commercial settlements under this Agreement shall be in accordance with Net Metering Regulations in force. 8.2 The units exported by the Renewable Energy Generating Station in the billing period shall be purchased by the Distribution Licensee at Rs. _____ per kWh as per the feed-in tariff approved by the consumption, for the entire duration of the Agreement. 8.3 The Licensee shall not be liable to compensate the Eligible Consumer if his Renewable Energy Generating System is unable to inject surplus power generated into the Licensee‟s Network on account of the failure of power supply in the grid/Network. 8.4 The Licensee shall issue a net bill as per the billing cycle after accounting for the units exported by the Renewable Power Developer at feed –in tariff approved by the Commission and after accounting for units imported from the grid at applicable Tariff Order. 9 Connection Costs The Eligible Consumer shall bear all costs related to the setting up of the Renewable Energy Generating System, including the cost of the Renewable Energy Generation Meter. 10 Dispute Resolution 10.1 Any dispute arising under this Agreement shall be resolved promptly, in good faith and in an equitable manner by both the Parties. 10.2 The Eligible Consumer shall have recourse to the concerned Consumer Grievance Redressal Forum constituted under the relevant Regulations in respect of any grievance regarding billing, which has not been redressed by the Licensee. The Eligible Consumer shall have recourse to the concerned Consumer Grievance Redressal Forum constituted under the relevant Regulations in respect of any grievance regarding billing, which has not been redressed by the Licensee.In the witness, where of (Name) __________________________________ for and on behalf of Eligible Consumer) and (Name) _______________________________________ for and on behalf of _____________________________________________________ (Licensee) agree to this agreement.46 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III—SEC.4] Annexure-5 Model Gross Metering Connection Arrangement This Agreement is made and entered into at (location) ……….on this (date) ………..day of (month) ………..year………..between the Eligible Consumer or third party owner, by the name of ……..………..………..………..………..………..…...owning or leasing or having commerce rights to the premises at (address) ………..………..………..………..………..………..as first party AND Distribution Licensee (herein after called as Licensee) and represented by ……….………..………..……….. (Designation of office) and having its registered office at (address) ……….………..………..……….. as the second party of the agreement And whereas, the ……….………..………..……….. (Name of the Licensee) agrees to provide grid connectivity to the eligible consumer for injection of the electricity generated from his Renewable Energy plant of capacity ………. kWs into the power system of the Licensee and as per conditions of this agreement and Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and UT of Ladakh (Grid Interactive Renewable Energy system and its related matters) Regulations, 2023. Both the parties hereby agree to as follows: 1. Eligibility 1.1 The Renewable Energy Generating System meets the applicable norms for being integrated into the distribution network, and that the Eligible Consumer shall maintain the System accordingly for the duration of this Agreement. 2. Technical and Interconnection Requirements 2.1 Renewable Energy generation plant under gross metering system will conform to the standards and requirements specified in Joint Electricity Regulatory Commission for the UT of Jammu & Kashmir and UT of Ladakh (Grid Interactive Renewable Energy Renewable Energy system and its related matters) Regulations, 2023 and in the following Regulations and codes as amended from time to time: i. Central Electricity Authority (Technical Standards for connectivity of the Distributed Generating Resources) Regulations, 2013 and subsequent amendments thereof; ii. Central Electricity Authority (Installation and Operation of Meters) Regulation 2006 and subsequent amendments thereof; iii. Central Electricity Authority (Measures of Safety and Electricity Supply) Regulations, 2010 and subsequent amendments thereof; iv. Grid Code Regulations framed by the Commission; v. Supply Code Regulations framed by the Commission; vi. Any other provisions applicable to the electricity consumer of the Distribution Licensee. 2.2 The Eligible Consumer agrees, that he shall install, prior to connection of the Renewable Energy Generating System to the Network of the Licensee, an isolation device (both automatic and in-built within inverter and external manual relays); and the Licensee shall have access to it if required for the repair and maintenance of the distribution Network. 2.3 The Eligible Consumer agrees that in case of a power outage Licensee‟s system, the photovoltaic system will disconnect/isolate automatically and his plant will not inject power into Licensee‟s distribution system. 2.4 All the equipment connected to the distribution system shall be compliant with relevant International (IEEE/IEC) or Indian standards (BIS) and installations of electrical equipment must comply with Central Electricity Authority (Measures of Safety and Electricity Supply) Regulations, 2010. 2.5 The Eligible Consumer agrees that Licensee will specify the interface/interconnection point and metering point. 2.6 The Eligible Consumer and Distribution Licensee agree to comply with the relevant CEA and JERC UT of Jammu & Kashmir and UT of Ladakh Regulations in respect of operation and maintenance of the plant, drawing and diagrams, site responsibility schedule, harmonics, synchronization, voltage, frequency, flicker etc. 2.7 Due to Licensee‟s obligation to maintain a safe and reliable distribution system, the Eligible Consumer agrees that if it is determined by the Licensee that the respective owner‟s photovoltaic system either causes damage to and/or produces adverse effects affecting other consumers or Licensee‟s assets, the Eligible consumer will have to disconnect photovoltaic system immediately from the distribution system upon direction from the Licensee and correct the problem at his own expense prior to a reconnection.[भाग III—खण् ड 4] भारत का राजपत्र : ऄसाधारण 47 3. Clearances and Approvals 3.1 The Eligible Consumer agrees to obtain all the necessary approvals and clearances (environmental and grid connection related) before connecting the photovoltaic system to the distribution system. 4. Access and Disconnection 4.1 Licensee shall have access to metering equipment and disconnecting means of the Renewable Energy system, both automatic and manual, at all times. 4.2 In emergency or outage situation, where there is no access to the disconnecting means, both automatic and manual, such as a switch or breaker, Licensee may disconnect service to the premises of the eligible consumer. 5. Liabilities 5.1 Eligible consumer and Licensee will indemnify each other for damages or adverse effects from either party‟s negligence or intentional misconduct in the connection and operation of photovoltaic system or Licensee‟s distribution system. 5.2 Licensee and eligible consumer will not be liable to each other for any loss of profits or revenues, business interruption losses, loss of contract or loss of goodwill, or for indirect, consequential, incidental or special damages, including, but not limited to, punitive or exemplary damages, whether any of the said liability, loss or damages arise in contract, or otherwise. 5.3 Licensee shall not be liable for delivery or realization by eligible consumer for any fiscal or other incentive provided by the Central/State Government beyond the scope specified by the Commission in its relevant Order 5.4 The Licensee may consider the quantum of electricity generation from the Renewable Energy system towards meeting its RPO. 6. Commercial Settlement 6.1 All the commercial settlement under this agreement shall follow the aforesaid Regulations issued by the Commission. 7. Connection Costs 7.1 The Eligible Consumer shall bear all costs related to setting up of photovoltaic system including metering and interconnection costs. The First Party agrees to pay the actual cost of modifications and upgrades to the service line required to connect photovoltaic system to the grid in case it is required. 8. Termination 8.1 The Eligible Consumer can terminate agreement at any time by providing Licensee with 30 days‟ prior notice. 8.2 Licensee has the right to terminate Agreement on 30 days‟ prior written notice, if the Eligible consumer commits breach of any of the term of this Agreement and does not remedy the breach within 30 days of receiving written notice from Licensee of the breach. 8.3 The Eligible Consumer shall upon termination of this Agreement, disconnect the Renewable Energy System from License‟s distribution system in a timely manner and to Licensee‟s satisfaction. In witness, whereof, Mr. ……………………………………………… for and on behalf of (Eligible consumer or third-party owner) and Mr. ……………………………………………… for and on behalf of (Licensee) sign this agreement in two originals. Eligible Consumer/ Third Party Name: Address: Service Connection No. Distribution Licensee Name: Designation: Office Address. Uploaded by Dte. of Printing at Government of India Press, Ring Road, Mayapuri, New Delhi-110064 and Published by the Controller of Publications, Delhi-110054.