See Full Document Text
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
STATUTORY INSTRUMENTS
2026 No. 533
INFRASTRUCTURE PLANNING
The North Lincolnshire Green
Energy Park (Correction) Order 2026
Made - - - - 14th May 2026
Coming into force - - 15th May 2026
The North Lincolnshire Green Energy Park Order 2025 (“the Order”)(1), which granted development
consent within the meaning of the Planning Act 2008 (“the Act”)(2), contains correctable errors
within the meaning of paragraph 1 of Schedule 4 to the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant
period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a
written request from the applicant(3) for the correction of errors in the Order.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has
informed Bassetlaw District Council, East Riding of Yorkshire Council, City of Doncaster Council,
North Lincolnshire Council, Lincolnshire County Council, North East Lincolnshire Council,
Nottinghamshire County Council and West Lindsey District Council as the relevant local planning
authorities(4), that the request has been received.
The Secretary of State, in exercise of powers conferred by section 119, and paragraphs 1(4) and
1(8) of Schedule 4 to the Act, makes the following Order.
Citation and commencement
1. This Order may be cited as the North Lincolnshire Green Energy Park (Correction) Order 2026
and comes into force on 15th May 2026.
Corrections
2. The North Lincolnshire Green Energy Park Order 2025 is corrected as set out in the table in
the Schedule (corrections) to this Order, in which—
(a) column 1 sets out where the correction is to be made;
(1) S.I. 2025/362.
(2) 2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the
Localism Act 2011 (c. 20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23). There are
other amendments to the Act which are not relevant to this Order.
(3) As defined in paragraph 4 of Schedule 4 to the Act.
(4) As defined in paragraph 4 of Schedule 4 to the Act.Document Generated: 2026-05-20
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text which is to be substituted, inserted or omitted.
Signed by authority of the Secretary of State for Energy Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning &
Innovation
14th May 2026 Department for Energy Security and Net Zero
2Document Generated: 2026-05-20
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
Schedule Article 2
CORRECTIONS
(1) Where the correction is to How the Correction is to be (3) Text to be substituted,
be made made inserted or omitted
Contents, Schedules, After “SCHEDULE 6” insert “ – PRIVATE MEANS OF
Schedule 6 ACCESS"
Article 2(2) (“Interpretation”) After “article 5” insert “ (limits of deviation)”
For “Schedule 1, Part 3” “Schedule 1, Part 2”
substitute
Article 5(1)(a) (“Limits of For “show” substitute “shown”
deviation”)
Article 5(1)(d) (“Limits of Before "2 of Schedule 1;" insert “Part ”
deviation”)
Article 11(2) (“Application For “authorised project” “authorised development”
and modification of legislative substitute
provisions”)
Article 13(1)(b) (“Power to After “kerb, ” insert “footpath, ”
alter layout, etc., of streets”)
Article 16(3) (“Public rights of For "intention so to do the “intention to do so to the
way – creation and temporary relevant highway authority." relevant highway authority.”
stopping up”) substitute
Article 18(3) (“Clearways, After “Schedule 7” insert “(clearways)”
prohibitions and restrictions”)
Article 20(3) (“Speed limits”) For “paragraph (20)” substitute “paragraph (2)”
Article 21(2) (“Traffic For “paragraph (3)” substitute “paragraph (1)”
regulation”)
Article 21(3) (“Traffic For “paragraph (3)” substitute “paragraph (1)”
regulation”)
Article 21(4) (“Traffic For “paragraph (3)” substitute “paragraph (1)”
regulation”)
Article 21(6) (“Traffic For “paragraph (3)” substitute “paragraph (1)”
regulation”)
Article 30(1) (“Acquisition of For “paragraph 21(1)” “paragraph (1)”
subsoil or airspace only”) substitute
Article 35(4) (“Apparatus and For “paragraph (4)” substitute “paragraph (3)”
rights of statutory undertakers
in stopped up streets”)
Article 35(5) (“Apparatus and For “paragraph (5)” substitute “paragraph (4)”
rights of statutory undertakers
in stopped up streets”)
Article 39(5) (“Felling or For “paragraph (5)” substitute “paragraph (4)”
lopping of trees”)
3Document Generated: 2026-05-20
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) Where the correction is to How the Correction is to be (3) Text to be substituted,
be made made inserted or omitted
Article 40(4) (“Removal of For “paragraph, (1)” substitute “paragraph (1),”
hedgerows”)
Article 40(5) (“Removal of For “paragraph 39(2)” “paragraph (4)”
hedgerows”) substitute
Article 41(8) (“Removal of For “remains from individual “remains from individual
human remains”) graves must be reinterred in graves must be reinterred in
individual containers which individual containers which
must identifiable” substitute must be identifiable”
Article 41 (“Removal of human Insert new paragraphs (13) and “(13) Section 25 (offence
remains”), after paragraph (12) (14) of removal of body from
burial ground) of the Burial
Act 1857(a) does not apply
to a removal carried out in
accordance with this article.”
“(14) Section 3 (burial not
to take place after Order in
Council for discontinuance) of
the Burial Act 1853(b) does
not apply to a removal carried
out in accordance with this
article.”
Article 41 (“Removal of human Insert footnote (a) “(a) 1857 c. 81. Section
remains”), new paragraph (13), 25 was substituted by
at footnote “(a)” of “Burial Act section 2 of the Church
1857(a)” of England (Miscellaneous
Provisions) Measure 2014
(No. 1) and amended by
section 96(1) of, and paragraph
1 of Schedule 3 to, the
Ecclesiastical Jurisdiction and
Care of Churches Measure 2018
(No. 3).”
Article 41 (“Removal of human Insert footnote (b) “(b) 1853 c. 134.”
remains”), new paragraph (14),
at footnote “(b)” of “Burial Act
1853(b)”
Article 41 (“Removal of human For paragraph number “(13)” “(15)”
remains”), paragraph (13) substitute
Requirement 1 (defined After “article 46” insert “(certification of plans, etc.)”
term “combined heat and
power assessment”), Part 1,
Schedule 2
Requirement 1 (defined term After “article 46” insert “(certification of plans, etc.)”
“waste area plan”), Part 1,
Schedule 2
4Document Generated: 2026-05-20
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) Where the correction is to How the Correction is to be (3) Text to be substituted,
be made made inserted or omitted
Requirement 16(3), Part 1, For “requirement 16” substitute “requirement 17”
Schedule 2
Requirement 16(4), Part 1, For “requirement 16” substitute “requirement 17”
Schedule 2
Requirement 24(1), Part 1, After "completion." omit “ Approved details and
Schedule 2 amendments to them.”
Requirement 25, Part 1, Before requirement 25 insert “Approved details and
Schedule 2 bold heading amendments to them”
Paragraph 32(1)(b), Part 2, After “paragraph 29” insert “(applications made under
Schedule 2 requirements)”
Schedule 3, in the first row For "Installation of the “Installation of the DHPWN
after the sub-heading entitled DHPWN (Work Nos. 11 and (Work Nos. 10 and 11).”
‘The rights of way and access 12)." substitute
plans - Sheet 9’ , in column 3
(“Description of street works”)
“”
Part 1, Schedule 6 On the row underneath “PRIVATE MEANS OF
“SCHEDULE 6” insert ACCESS”
Paragraph (4)(b) (“Full cable For “portakabins” substitute “portacabins”
rights”), Part 1, Schedule 10
Paragraph 10 (“Utility works”), For “paragraph 1” substitute “paragraph 10”
Part 1, Schedule 10
Paragraph 13 (“Drainage For “paragraph 2” substitute “paragraph 13”
rights”), Part 1, Schedule 10
Paragraph 18 (“Access tracks”), For “paragraph 1” substitute “paragraph 18”
Part 2, Schedule 10
Paragraph 19 (“Access tracks For “paragraph 1” substitute “paragraph 19”
(public rights of way)”), Part 2,
Schedule 10
Paragraph (21)(b) (“Full cable For “portakabins” substitute “portacabins”
rights”), Part 2, Schedule 10
Paragraph 22 (“Full cable For “paragraph 3” substitute “paragraph 22”
rights”), Part 2, Schedule 10
Paragraph 27 (“Utility works”), For “paragraph 1” substitute “paragraph 27”
Part 2, Schedule
Paragraph 30 (“Drainage For “paragraph 2” substitute “paragraph 30”
rights”), Part 2, Schedule 10
Paragraph 24(3), Part 3, For “article 48” substitute “article 49”
Schedule 14
Paragraph 25(3), Part 3, For "replacement services." “replacement services).”
Schedule 14 substitute
5Document Generated: 2026-05-20
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) Where the correction is to How the Correction is to be (3) Text to be substituted,
be made made inserted or omitted
Paragraph 36(1), Part 4, For “NPG” substitute “Northern Powergrid”
Schedule 14
Paragraph 36(4), Part 4, After “article 49” insert “(arbitration)”
Schedule 14
Paragraph 36(5), Part 4, After “article 49” insert “(arbitration)”
Schedule 14
Paragraph 37(2), Part 4, For “paragraph (1)” substitute “sub-paragraph (1)”
Schedule 14
Paragraph 37(2), Part 4, For “If” substitute “if”
Schedule 14
Paragraph 39(1)(a)(vi), Part 4, For “Schedule)” substitute “Schedule”
Schedule 14
Paragraph 45, Part 4, For “Undertaker” substitute “undertaker”
Schedule 14
Paragraph 69, Part 6, After “article 2(1)” insert “(interpretation)”
Schedule 14 (definition of
“authorised works”)
Schedule 15, row 17 For “May 2023” substitute “October 2023”
(“environmental statement”),
column 4 (“date”)
Schedule 15, row 20 For “Rev. 6” substitute “Rev. 8”
(“CoCP (code of construction
practice)”), in column 3
(“Revision number”)
Schedule 15, row 20 For “May 2023” substitute “October 2023”
(“CoCP (code of construction
practice)”), in column 4
(“Date”)
Schedule 15, row 21 (“OEMP For “Rev. 2” substitute “Rev. 3”
(operational environmental
management plan)”), in column
3 (“Revision number”)
Schedule 15, row 21 (“OEMP For “April 2023” substitute “October 2023”
(operational environmental
management plan)”), in column
4 (“Date”)
Schedule 15, row 23 For “Rev. 0” substitute “Rev. 1”
(“framework travel plan”), in
column 3 (“Revision number”)
Schedule 15, row 23 For “May 2022” substitute “December 2022”
(“framework travel plan”), in
column 4 (“Date”)
6Document Generated: 2026-05-20
Status: This is the original version (as it was originally made). This
item of legislation is currently only available in its original format.
(1) Where the correction is to How the Correction is to be (3) Text to be substituted,
be made made inserted or omitted
Schedule 15, row 27 (“land For “Rev. 2” substitute “Rev. 3”
plans”), in column 3 (“Revision
number”)
EXPLANATORY NOTE
(This note is not part of the Order)
This Order corrects errors identified in the North Lincolnshire Green Energy Park Order 2025 (S.I.
2025/362), which granted development consent under the Planning Act 2008, following a request
under paragraph 1(5)(a) of Schedule 4 to that Act.
7