**Executive Summary**
The Union Cabinet has approved the ‘Small Hydro Power (SHP) Development Scheme’ for FY 2026-27 to FY 2030-31 with a total outlay of Rs. 2584.60 crore. The scheme aims to install approximately 1500 MW of capacity through projects ranging from 1–25 MW, primarily targeting hilly, North Eastern, and international border areas. This initiative seeks to leverage Rs. 15,000 crore in investment while promoting indigenous machinery and creating significant rural employment.
**Key Points / Main Content**
**Financial Provisions and Targets**
* **Total Budget:** An outlay of Rs. 2584.60 crore is designated for the scheme’s duration.
* **Capacity Goal:** The scheme targets the installation of approximately 1500 MW of Small Hydro Power.
* **Investment Leverage:** The government outlay is expected to bring in a total investment of Rs. 15,000 crore to the sector.
* **Detailed Project Reports (DPR):** Rs. 30 crore is allocated to support state and central agencies in preparing DPRs for approximately 200 future projects.
**Central Financial Assistance (CFA) Structure**
* **North Eastern and Border Districts:** Support is provided at Rs. 3.6 crore per MW or 30% of the project cost (whichever is lower), capped at Rs. 30 crore per project.
* **Other States:** Support is provided at Rs. 2.4 crore per MW or 20% of the project cost (whichever is lower), capped at Rs. 20 crore per project.
**Operational and Technical Requirements**
* **Project Scope:** The scheme covers small hydro projects with a capacity between 1 MW and 25 MW.
* **Indigenous Sourcing:** 100% of plant and machinery must be sourced from indigenous providers to fulfill 'Atmanirbhar Bharat' objectives.
* **Infrastructure Efficiency:** Projects are decentralized, minimizing the need for long transmission lines and reducing transmission losses.
**Socio-Economic and Environmental Benefits**
* **Employment Generation:** The scheme is projected to create 51 lakh person days of employment during construction, alongside long-term operation and maintenance roles.
* **Sustainability:** Projects are designed to avoid large-scale land acquisition, deforestation, and community displacement.
* **Longevity:** SHP projects offer a long lifespan, typically ranging from 40 to over 60 years.
**Impact Analysis**
**State and Central Government Agencies**
**Impact**
Agencies will receive financial incentives to build a pipeline of small hydro projects through subsidized reporting and project preparation.
**Action Required**
Prepare Detailed Project Reports (DPRs) for the identified 200 projects to utilize the Rs. 30 crore incentive fund.
**Hilly and North Eastern States (including Border Districts)**
**Impact**
These regions will receive higher tiers of financial assistance to exploit their high hydro potential in remote and difficult-to-reach locations.
**Action Required**
Identify and facilitate the development of project sites to tap into the specific CFA provisions for border and NE regions.
**Indigenous Equipment Manufacturers**
**Impact**
The sector will see increased demand as the scheme mandates 100% indigenous sourcing for all plant and machinery.
**Action Required**
Scale up production and supply chains to meet the requirements for the targeted 1500 MW capacity.
**Rural and Remote Communities**
**Impact**
Communities will benefit from socio-economic development, local investment, and significant employment opportunities (51 lakh person days).
**Action Required**
Provide the necessary local labor force for construction, maintenance, and operation of decentralized power units.
Key Entities Referenced
Small Hydro Power (SHP) Development Scheme: A scheme approved for the period FY 2026-27 to FY 2030-31 with an outlay of Rs. 2584.60 crore to install 1500 MW of capacity via projects between 1-25 MW.
North Eastern States and border districts: Priority geographical areas eligible for higher central financial assistance of up to Rs. 3.6 crore per MW or 30% of the project cost.
Atmanirbhar Bharat: A national initiative whose objectives are met by the scheme's requirement to leverage 100% of plant and machinery from indigenous sources.
Cabinet
Cabinet approves scheme on ‘Small Hydro
Power (SHP) Development Scheme for the period
FY 2026-27 to FY 2030-31’
Posted On: 18 MAR 2026 4:12PM by PIB Delhi
The Union Cabinet chaired by the Prime Minister Shri Narendra Modi has approved the ‘Small Hydro
Power (SHP) Development Scheme for the period FY 2026-27 to FY 2030-31’ with an outlay of
Rs.2584.60 crore for installation of Small Hydro Power (SHP) Projects of an approximate capacity of
1500 MW.
The scheme will support small hydro projects (between 1-25 MW capacity) to come up in different states
and will especially benefit hilly and North Eastern states with high potential for such projects. In North
Eastern States and in districts with international border, central financial assistance to the tune of Rs.3.6
crore per MW or 30%of the project cost, whichever is lower with an upper limit of Rs.30 crore per project
will be available. In other states Rs.2.4 crore per MW or 20% of project cost, whichever is lower with a
cap of Rs.20 crore per project would be available. This will help in tapping the small hydro potential in
remote and difficult to reach locations. An amount of Rs. 2,532 crore has been earmarked for such
projects. This is likely to bring in Rs. 15,000 crore of investment in the small hydro sector giving a boost
to the clean energy initiative, investment in remote and rural areas and creating significant employment
opportunities. The investment will also leverage 100% of the plant and machinery from indigenous
sources fulfilling the objective of Atmanirbhar Bharat.
The scheme will also incentivise the states to prepare the detailed project report for about 200 projects to
create a pipeline of small hydro projects in future. An amount of Rs.30 crore has been kept to support
state and central government agencies to prepare such DPR.
The scheme will support 51 lakh person days of employment during the project construction and will also
enable employment in maintenance and operation of these SHPs which will come up in largely rural and
remote locations. SHP projects being decentralized in nature, the requirement of long transmission line is
minimal, which also reduces the transmission losses.
Launching of this Scheme will rejuvenate the Small Hydro Power sector and will help in exploiting the
available potential at a much faster pace. SHP projects are environmentally sustainable, as they avoid
large-scale land acquisition, deforestation, and displacement of communities. It will also promote socio-
economic development of remote areas by boosting local investment, apart from creating long-term
employment with project lifespans typically ranging from 40 to over 60 years.
****