**Executive Summary**
This report highlights the operationalisation of five sewerage infrastructure projects under the Namami Gange Mission Phase II during the third quarter of FY 2025-26. These projects aim to strengthen pollution abatement and river rejuvenation efforts across multiple states. The commissioning of these projects has increased the total STP capacity under the Namami Gange Programme to 3,976 MLD, with 173 STPs now commissioned.
**Key Points / Main Content**
* **Overall Progress:**
* 9 projects have been made operational in FY 2025-26 so far.
* Total STP capacity commissioned under the Namami Gange Programme reaches 3,976 MLD.
* Total number of Sewage Treatment Plants (STPs) commissioned now stands at 173.
* **Shuklagunj, Uttar Pradesh:**
* A 5 MLD Sewage Treatment Plant (STP) has been commissioned.
* The project cost ₹65 crore.
* The project is implemented under the Hybrid Annuity Model and uses Sequential Batch Reactor (SBR) technology.
* **Agra, Uttar Pradesh:**
* Two STPs with capacities of 31 MLD and 35 MLD have been commissioned.
* The project sanctioned at a cost of ₹842 crore, envisages a cumulative capacity of 177.6 MLD across 13 STPs.
* Implemented under the HAM Model using SBR technology.
* **Varanasi:**
* A 55 MLD STP at Assi-BHU has been made operational.
* Project sanctioned at ₹308 crore, based on SBR technology and implemented under the DBOT model.
* **North Barrackpore, West Bengal:**
* One 30 MLD STP has been commissioned.
* Project sanctioned at ₹154 crore, out of a planned total capacity of 38 MLD across two STPs.
* Implemented under the HAM Model.
* **Patna Kankarbagh STP, Bihar:**
* The capacity is increased from 15 MLD to 30 MLD during Q3 of FY 2025-26.
**Impact Analysis**
**Residents of Shuklagunj (Uttar Pradesh)**
* **Impact:** Benefit from improved sanitation and prevention of sewage discharge into the River Ganga. Specifically, approximately three lakh people will benefit.
* **Action Required:** No action listed.
**Residents of Agra (Uttar Pradesh)**
* **Impact:** Benefit from reduced untreated sewage flow into the River Yamuna and improved city sanitation. Specifically, nearly 25 lakh residents will benefit.
* **Action Required:** No action listed.
**Residents of Varanasi**
* **Impact:** Benefit from protection of the River Ganga from sewage pollution and strengthened long-term wastewater management. Specifically, approximately 18 lakh people will be served.
* **Action Required:** No action listed.
**Residents of North Barrackpore (West Bengal)**
* **Impact:** Benefit from improved sanitation and prevention of untreated sewage discharge into the River Ganga. Specifically, approximately 2.2 lakh people will benefit.
* **Action Required:** No action listed.
**Residents of Patna (Bihar)**
* **Impact:** Benefit from enhanced sewage treatment infrastructure.
* **Action Required:** No action listed.
Key Entities Referenced
Namami Gange Mission Phase II: A mission focused on strengthening pollution abatement and river rejuvenation efforts for the Ganga and Yamuna rivers.
Ganga: A major river in India, targeted for pollution reduction.
Yamuna: A major river in India, targeted for pollution reduction.
Uttar Pradesh: A state in India where key infrastructure projects are being implemented to reduce pollution in the Ganga and Yamuna rivers.
Ministry of Jal Shakti: The Indian government ministry responsible for water resources, including the Namami Gange Mission.
Ministry of Jal Shakti
Five key sewerage infrastructure projects made
operational for Ganga and Yamuna in Namami
Gange Mission Phase II
प्रव तथ: 09 JAN 2026 1:03PM by PIB Delhi
Under Namami Gange Mission Phase II, the operationalisation of 5 sewerage infrastructure projects
during the 3rd quarter of FY 2025–26 marks another significant step towards strengthening pollution
abatement and river rejuvenation efforts across multiple States. During the FY 25-26, so far 9 projects
have been made operational, enhancing sewage treatment capacity in key urban centres. Till Q2 Udham
Singh Nagar (Uttrakhand), Moradabad (UP), Maheshtala (WB) and Jangipur (WB) have been
operationalised.
With the commissioning of these 5 projects, the total STP capacity commissioned under the Namami
Gange Programme has reached 3,976 MLD, while the total number of Sewage Treatment Plants
(STPs) commissioned now stands at 173. These achievements reinforce the Mission’s core objective of
preventing untreated sewage from entering rivers and improving urban sanitation infrastructure.
In Shuklagunj, Uttar Pradesh, pollution abatement efforts have received a major boost with the
commissioning of a 5 MLD Sewage Treatment Plant, developed at a cost of ₹65 crore. The project,
implemented under the Hybrid Annuity Model, is based on Sequential Batch Reactor (SBR)
technology. The project will benefit a population of approximately three lakh people, ensure effective
interception and diversion of sewage and prevent its discharge into the River Ganga.
5 MLD STP at Shuklagunj
5 MLD STP at Shuklagunj
In Agra, Uttar Pradesh, a key city along the Yamuna basin, two STPs with capacities of 31 MLD and 35
MLD have been commissioned during Q3 under the Pollution Abatement Works, Agra project.
Sanctioned at a total cost of ₹842 crore, the project envisages a cumulative capacity of 177.6 MLDacross 13 STPs. Implemented under the HAM Model using SBR technology, the project will benefit
nearly 25 lakh residents, significantly reducing the flow of untreated sewage into the River Yamuna and
improving the city’s sanitation profile.
35 MLD STP at Agra
31 MLD STP at Agra
In the holy city of Varanasi, a 55 MLD STP at Assi–BHU has been made operational under a project
sanctioned at ₹308 crore. Based on SBR technology and implemented under the DBOT model, the
project will serve a population of around 18 lakh people. The commissioning of this facility is expected to
play a crucial role in protecting the River Ganga from sewage pollution while strengthening long-term
wastewater management in the city.
55 MLD STP at Assi BHU, Varanasi 55 MLD STP at Assi BHU, Varanasi
In North Barrackpore, West Bengal, one 30 MLD STP has been commissioned during Q3 under a
project sanctioned at ₹154 crore, out of a planned total capacity of 38 MLD across two STPs.
Implemented under the HAM Model and designed to meet NGT norms, the project will benefit
approximately 2.2 lakh people, contributing to improved sanitation and preventing untreated sewage
discharge into the River Ganga.30 MLD STP at North Barrackpore
30 MLD STP at North Barrackpore
In addition, the Patna Kankarbagh STP in Bihar, which was earlier partially commissioned with a
capacity of 15 MLD, is increased to 30 MLD during Q3 of FY 2025–26, further strengthening sewage
treatment infrastructure in the city and supporting pollution abatement efforts along the Ganga.
Kankharbag STP
These accomplishments represent significant progress in achieving cleaner rivers and improved urban
sanitation, while also reinforcing the mission's core objective of sustainable and holistic river
rejuvenation.
***