This report summarizes water quality monitoring efforts and sanitation measures undertaken for the Ganga River, particularly during and after the Maha Kumbh 2025, as well as progress under the Namami Gange Programme (NGM).
During the Maha Kumbh 2025, the Central Pollution Control Board (CPCB) monitored water quality at initially 5, then expanded to 8 locations, analyzing pH, Dissolved Oxygen (DO), Biochemical Oxygen Demand (BOD), and Fecal Coliform (FC) levels. Results indicated that median values were within permissible limits for primary bathing water quality criteria. The Prayagraj Mela Authority implemented a comprehensive Sanitation Plan which included: Service Level Benchmarks (SLBs) in contracts with toilet vendors, systematic dismantling and disinfection of temporary toilets post-mela, approximately 250 km of temporary drainage lines with bioremediation treatment ponds, and temporary Sewage Treatment Plants (STPs) and Faecal Sludge Treatment Plants (FSTPs). Post-event reviews confirmed the effectiveness of these systems, informing improvements for future events.
The Namami Gange Programme, with 502 sanctioned projects (323 completed, 150 under implementation, and 29 at the tendering stage), has significantly contributed to wastewater treatment infrastructure, riverfront development, river surface cleaning, afforestation, biodiversity conservation, and organic agriculture. The Administrative Staff College of India (ASCI), as a Third-Party Agency (TPA), observed that the NGM has led to Aviral Dhara (continuous flow) and Nirmal Dhara (unpolluted flow) and has been decentralized and mainstreamed within basin states and local bodies. Key challenges remain in securing land for STPs and obtaining statutory clearances. The National Mission for Clean Ganga (NMCG) actively monitors project status through review meetings and the Central Monitoring Committee (CMC).
CPCB reports indicate varying levels of pollution across different stretches of the Ganga. Uttarakhand and Jharkhand do not fall under polluted stretches (BOD ≤ 3 mg/l). Priority Class V stretches (BOD 3-6 mg/l) exist in Uttar Pradesh (Farrukhabad to Allahabad, and Mirzapur to Ghazipur). Bihar has Priority Class IV stretches (BOD 6-10 mg/l) along Buxar, Patna, Fatwah, and Bhagalpur. West Bengal also has Priority Class IV stretches (BOD 6-10 mg/l) from Behrampur to Haldia. DO levels are generally within acceptable limits. Biomonitoring from 2024-25 at 50 locations along the Ganga and its tributaries, and 26 locations along the Yamuna and its tributaries, showed Biological Water Quality (BWQ) predominantly ranging from Good to Moderate.
The dolphin population in the Ganga has increased from an estimated 2,500-3,000 in 2009 to approximately 6,327 in 2021-2023. Dolphins have been confirmed in 17 tributaries where they were previously unrecorded.
This information was provided by THE MINISTER OF STATE FOR JAL SHAKTI SHRI RAJ BHUSHAN CHOUDHARY in a written reply to a question in Lok Sabha.
Key Entities Referenced
Ganga River: The main river being monitored for water quality.
Central Pollution Control Board: Organization (CPCB) that carried out water quality monitoring of Ganga River.
Prayagraj Mela Authority: Authority responsible for sanitation planning during Maha Kumbh 2025.
Namami Gange Programme: A program for the rejuvenation of the River Ganga and its tributaries.
Administrative Staff College of India: A Third-Party Agency (ASCI) engaged for the appraisal of the Namami Gange Mission.
National Mission for Clean Ganga: An organisation (NMCG) actively involved in monitoring the status of the projects under Namami Gange Programme.
Uttarakhand: A state in India where stretches of Ganga River are not under polluted stretches.
Uttar Pradesh: A state in India where stretches of Ganga River from Farrukhabad to Allahabad and Mirzapur to Ghazipur fall under Priority Class V.
Ministry of Jal Shakti
MONITORING OF WATER QUALITY OF GANGA
RIVER
Posted On: 24 JUL 2025 5:15PM by PIB Delhi
Central Pollution Control Board (CPCB) has informed that it carried out water quality monitoring at 5
stations (twice a week) from 12th January 2025 to 20th February 2025 during Maha Kumbh 2025 at
Shringverpur Ghat, Lord Kurzon Bridge, Nagvasuki Mandir, Sangam and Deeha Ghat, covering auspicious
bathing (Amrit Snan) days including pre- and post- days of such auspicious bathing days. Further, three
more water quality monitoring locations at Shastri Bridge, Someshwar Ghat and downstream of Delhi
Public School with effect from 21.02.2025, thus taking the monitoring locations for river Ganga water
quality from 5 to 8.
As per the comprehensive report prepared based on the above monitoring, the median value of pH,
Dissolved Oxygen (DO), Biochemical Oxygen Demand (BOD) and Feacal Coliform (FC) for all the
monitored locations was found within the respective criteria/permissible limits for Primary Bathing Water
Quality Criteria.
The Prayagraj Mela Authority had prepared a comprehensive Sanitation Plan for Maha Kumbh 2025 after
conducting industry consultations to explore and adopt the latest technologies with following main
features:
i. To ensure accountability and performance, Service Level Benchmarks (SLBs) were included in the
contracts with toilet vendors, covering manpower deployment, cesspool operations, and jet spray
cleaning.
ii. Post-Mela Sanitation Measures included the systematic dismantling and removal of all toilets.
Hygienic uninstallation was ensured by the sanitation team, using Malathion (5%) and Slaked
Lime for effective disinfection and neutralisation of waste.
iii. Approximately 250 km of temporary drainage lines for collecting wastewater (excluding septage)
within the Mela area. The collected water was treated through bioremediation techniques in
dedicated ponds. These temporary lines were dismantled post-event and stored for reuse in future
events such as the upcoming Magh Mela, and the ponds were subsequently backfilled.
iv. For septage treatment, three temporary Sewage Treatment Plants (STPs) of 500 KLD capacity
each were installed at various locations within the Mela premises. Additionally, two Faecal
Sludge Treatment Plants (FSTPs) of 50 KLD capacity each and one FSTP of 100 KLD were also
utilised. These facilities were uninstalled after the event concluded.
v. The post-event reviews confirmed that sanitation and wastewater management systems functioned
effectively. Based on these learnings, corrective actions and planning improvements are being
implemented for Maha Kumbh 2025, including enhanced reuse strategies, improved disinfection
protocols, and structured redeployment of sanitation infrastructure.
A total of 502 projects has been sanctioned under the Namami Gange Programme for the rejuvenation of
the River Ganga and its tributaries. Out of these, 323 projects have been completed, 150 are currently
under implementation, and 29 are at the tendering stage.
The Administrative Staff College of India (ASCI) was engaged as a Third-Party Agency (TPA) for the
appraisal of the Namami Gange Mission (NGM). ASCI has observed the following in its report:
i. NGM has led to considerable additions to wastewater treatment infrastructure in the Ganga River
basin, balanced with investments in riverfront and ghat development, river surface cleaningprocesses, afforestation, biodiversity conservation, organic agriculture, etc.
ii. Capacity building of implementing agencies and other stakeholders, along with community
engagement to support the initiatives, are among the other key contributions of the projects.
iii. The decentralization and mainstreaming of program tasks within the basin states and local body
establishments have been the hallmark of the programme.
iv. ASCI, in its appraisal, stated that NGM has shown good progress in achieving its mandate of
continuous flow (Aviral Dhara) and unpolluted flow (Nirmal Dhara).
v. It has demonstrated successful and replicable models for implementing a large-scale river
rejuvenation programme in a mission mode and has gained global recognition.
The main challenges in implementation of Namami Gange Mission are following:
i. Identification of suitable land for the establishment of new Sewage Treatment Plants (STPs)
ii. The issuance of statutory clearances such as right of way for sewage-related networks, obtaining
permissions for road cutting, No Objection Certificates (NoCs) from competent authorities like
forest and revenue departments;
In order to address and overcome these challenges, the National Mission for Clean Ganga (NMCG) has
been actively involved in closely monitoring the status of the projects. NMCG regularly conducts
comprehensive review meetings under the chairmanship of the competent authority and through the
Central Monitoring Committee (CMC) to evaluate progress, identify potential roadblocks, and ensure
timely resolutions.
Measurable outcomes of the implementation of the NGM is provided through the reports of the Central
Pollution Control Board (CPCB) on pollution assessment of rivers of India. As per the report, the Priority
River Stretches (PRSs) on the river Ganga, based on the assessment carried out in 2022 (using 2019 and
2021 data), are as under:
a. Uttarakhand does not fall under polluted stretches (BOD < 3 mg/l);
b. In Uttar Pradesh, stretches from Farrukhabad to Allahabad and Mirzapur to Ghazipur fall under
Priority Class V (BOD 3–6 mg/l);
c. In Bihar, stretches along Buxar, Patna, Fatwah, and Bhagalpur fall under Priority Class IV (BOD
6–10 mg/l);
d. Jharkhand does not fall under polluted stretches (BOD < 3 mg/l);
e. In West Bengal, the stretch from Behrampur to Haldia falls under Priority Class IV (BOD 6–10
mg/l).
Further, the value of Dissolved Oxygen (DO), which is an indicator of river health, has been found to be
within the acceptable limits of the notified primary bathing water quality criteria and is satisfactory to
support the ecosystem of the river along almost the entire stretch of the river Ganga.
As per the biomonitoring conducted during 2024–25 at 50 locations along River Ganga and its tributaries,
and 26 locations along River Yamuna and its tributaries, the Biological Water Quality (BWQ)
predominantly ranged from ‘Good’ to ‘Moderate’. The presence of diverse benthic macro-invertebrate
species indicates the ecological potential of the rivers to sustain aquatic life.
Further, the population of Dolphins in the river Ganga has shown a marked increase over the past decade.
From an estimated baseline of 2,500–3,000 individuals in 2009, the population rose to approximately 3,500
in 2015 and further to around 6,327 individuals as per the nationwide survey conducted during 2021–2023.
This represents more than a twofold increase since 2009. In the Ganga basin, the 2021–2023 assessment
across 17 tributaries confirmed dolphin presence in multiple rivers where they were previously unrecorded,
such as the Rupnarayan, Girwa, Kauriyala, Babai, Rapti, Bagmati, Mahananda, Ken, Betwa, and Sind.
This information was provided by THE MINISTER OF STATE FOR JAL SHAKTI SHRI RAJ
BHUSHAN CHOUDHARY in a written reply to a question in Lok Sabha today.
*****
MAM/SMP(Lok Sabha US Q832)