GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5430
TO BE ANSWERED ON 25.03.2026
ABSS FOR MARODA RAILWAY STATION
†5430. SHRI VIJAY BAGHEL:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of progress of construction works under the Amrit Bharat
Station Scheme particularly the slow pace at Maroda Railway Station
and the status of operationalisation of street lights from the station to
the railway gate;
(b) the status of approval for much-needed construction of an Road Over
Bridge (ROB) near Risama Railway DD-19 in Durg, which connects the
capital to other major cities;
(c) the status of approval for the construction of a double railway line from
Durg to Rowghat to reduce pressure on passenger and goods trains on
this route; and
(d) the status of approval for the daily operation of passenger train number
78826 (Dallirajhara–Durg) and 78827 (Durg–Dallirajhara) with 12
coaches, keeping in view the increasing daily rush of passengers?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) At Marauda station, located in Chhattisgarh, facilities like high
level platform, platform shelter, waiting hall, drinking water
arrangement, urinal lavatory, seating arrangement etc. are available.
Marauda station has been identified for development under Amrit Bharat
Station Scheme. Development works at Marauda station have been taken
up at good pace. The structural work of concourse and waiting hall,
§ Page 1 of 10platform shelter, platform surfacing, parking and approach road have been
completed. The finishing works of concourse and waiting hall, toilet,
circulating area, entry/exit gate, lighting, Public Address System and
booking counter have been taken up.
Further, the work of providing street lights from Marauda railway station to
railway gate has been taken up.
Development / redevelopment / upgradation / modernisation of stations on
Indian Railways is a continuous and ongoing process and works in this
regard are undertaken as per requirement, subject to inter-se priority and
availability of funds. Development / redevelopment / upgradation /
modernisation of a station is carried out based on category of
station/condition/traffic handled etc.
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/air concourse commensurate
with passenger traffic
Provision of lift/escalators/ramp
Page 2 of 10 Improvement /Provision of platform surface and cover over
platforms
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity, phasing
and feasibility and creation of city centre at the station in the long
term.
So far, 1,338 stations have been identified for development under the
Amrit Bharat Station Scheme. Out of these, 32 stations are located in
Chhattisgarh. The name of stations identified under Amrit Bharat
Station Scheme in Chhattisgarh are as following:
No. of
State Name of Stations
Stations
Chhattisgarh 32 Akaltara, Ambikapur, Baikunthpur Road,
Balod, Baradwar, Belha, Bhanupratappur,
Bhatapara, Bhilai, Bhilai Nagar, Bhilai
Power House, Bilaspur, Champa,
Dallirajhara, Dongargarh, Durg, Hathbandh,
Jagdalpur, Janjgir Naila, Korba,
Page 3 of 10No. of
State Name of Stations
Stations
Mahasamund, Mandir Hasaud, Marauda,
Nipania, Pendra Road, Raigarh, Raipur Jn,
Raj Nandgaon, Sarona, Tilda-Neora, Urkura,
Uslapur
Completed stations:
Development works at railway stations under Amrit Bharat Station
Scheme in Chhattisgarh have been taken up at a good pace. Till now,
works of 05 stations have been completed. The name of stations
completed in Chhattisgarh are as following:
No. of
State Name of stations
stations
Chhattisgarh 05 Ambikapur, Bhanupratappur, Bhilai,
Dongargarh, Urkura
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Bhilai Power House station: The works of new second entry station
building, improvement of main entry station building, platform
upgradation, improvement of waiting areas, development of
circulating area, parking, lifts, escalators and 12 m Foot Over Bridge
have been completed. The finishing works of station building and
improvement of illumination on platforms have been taken up.
Page 4 of 10 Dallirajhara station: The works of improvement of station building,
waiting areas, toilet, platform upgradation and Public Address System
have been completed. The works of improvement of circulating area,
landscaping, art & culture works, signage and improvement of
illumination on platforms have been taken up.
Raipur Junction station: The works of utility shifting and relocation at
second entry side have been completed. The structural works of
second entry station building, multi level parking facility on both main
and second entry side, service buildings and development of
circulating area at second entry side have been taken up.
Sarona station: The works of new second entry station building,
improvement of main entry station building, platform upgradation,
improvement of waiting areas, development of circulating area,
parking, Public Address System, lifts, escalators and 12 m Foot Over
Bridge have been completed. The finishing works of station building,
landscaping, art & culture and improvement of illumination on
platforms have been taken up.
Development / Upgradation of stations is complex in nature involving safety
of passengers & trains and requires various statutory clearances such as
fire clearance, heritage, tree cutting, airport clearance etc. The progress
also gets affected due to brownfield related challenges such as shifting of
utilities (involving water/sewage lines, optical fibre cables, gas pipe lines,
power/signal cables, etc.), infringements, operation of trains without
hindering passenger movement, speed restrictions due to works carried out
in close proximity of tracks and high voltage power lines, etc. and these
factors affect the completion time.
Page 5 of 10Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation and expenditure under Plan Head-53
are maintained Zonal Railway-wise and not work-wise or station-wise or
state-wise. Chhattisgarh is covered under the jurisdiction of two railway
zones, namely, South East Central Railway and East Coast Railway. For
these zones, an allocation (revised estimate) of ₹ 1,163 crore has been
made for the financial year 2025-26, out of which an expenditure (up to
February, 2026) of ₹ 974 crore has been incurred so far.
ROB/RUB
The work for construction of Road Under Bridge (RUB) in lieu of Level
Crossing (LC) Nos. DD-19 (Risama Level Crossing) at Km 889/7-8 has been
sanctioned. The work of launching of segment boxes has been taken up.
Further, the work of preparation of Technical Feasibility Report / Detailed
Project Report (TFR / DPR) for the construction of ROB at the demanded
location has been taken up.
Further, Railways have also taken several remedial measures to mitigate
the problem of water logging, as under:
Adequate drainage arrangement has been made as integral part of
planning of new RUB/underpasses.
In existing RUBs/underpasses remedial measures like water flow
diversion to nearby bridge and nallahs/drains, provision of cover shed
on approach roads, provision of hump at entry to RUB, provision of
cross drains, sealing of joints etc. have been made as per feasibility,
suitability and site requirements.
Page 6 of 10 In addition, pumping arrangement has also been made for identified
RUBs, to drain out water expeditiously in case of emergency and
provision to stop road traffic in exceptional/unusual rainfall situation
for safety of road users.
Completion & commissioning of ROB/RUB works depends on various
factors like cooperation of State Governments in giving consent for
closure of LC, fixing of approach alignment, approval of General
Arrangement Drawing (GAD), land acquisition, removal of encroachment,
shifting of infringing utilities, statutory clearances from various authorities,
law and order situation in the area of project / work sites, duration of
working season in a year for the particular project / area due to climatic
conditions etc. All these factors affect the completion time of the projects
/ works.
Railways have taken following measures to expedite the progress of
ROB/RUB works:
(i) Joint survey with concerned State Govt./Road Owning Authority is done
before finalizing the General Arrangement Drawing (GAD) to ensure
smooth execution.
(ii) Periodic meetings of Railway & State Government officials are done to
resolve various issues related to ROB/RUB works.
(iii) Standardization of superstructure drawings for various combinations
of span, skewness and width of road on Railway portion has been done
to avoid delays during the design approval. This has been issued in the
form of compendium, which can be directly adopted for Road Over
Bridge across Railway lines for expeditious planning.
Page 7 of 10Train Services
Dallirajhara-Durg sector is being served by 10 train services listed below:-
SN Train No. & Name
1 78824 Durg - Dallirajhara DEMU
2 78825 Dallirajhara-Durg DEMU
3 68764 Raipur - Taroki MEMU
4 68765 Taroki-Raipur MEMU
5 78817 Durg - Dallirajhara DEMU
6 78818 Antagarh-Durg DEMU
7 78826 Durg-Dallirajhara DEMU
8 78827 Dallirajhara-Durg DEMU
9 78815 Raipur-Antagarh DEMU
10 78816 Antagarh-RaipurDEMU
Besides, increase in frequency of train services is an on-going process,
which depends on various factors including:
● Capacity of that section
● Availability of path
● Availability of required rolling stock
● Availability of matching infrastructure for rolling stock
● Maintenance requirement of railway tracks and other assets.
● Occupancy and the traffic requirement of the section.
Railway Projects
Durg is an existing railway station and already connected to Dallirajhara.
Presently, Durg- Dallirajhara is being served by 05 pairs of trains. At
present, the section has adequate line capacity to meet the current traffic.
Page 8 of 10For further providing connectivity to Rowghat and improving the
connectivity in the region, Railway has taken up the work of Dallirajhara-
Rowghat-Jagdalpur new line project (235 Km). An expenditure of ₹ 1,028
Cr. has been incurred upto March 2025 and an outlay of ₹ 85 Cr. has been
provided for this project for the financial year 2025-26. Status of the project
is as under:
Section Status
Dallirajhara-Taroki (77 Km) Commissioned.
Taroki-Rowghat (18 Km) Work has been completed.
Rowghat-Jagdalpur (140 Km) Land acquisition has been taken up.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Page 9 of 10 Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
Page 10 of 10