See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4290
TO BE ANSWERED ON 18.03.2026
ADDITIONAL PLATFORM AT AMBIKAPUR RAILWAY STATION
†4290. SHRI CHINTAMANI MAHARAJ:
Will the Minister of RAILWAYS be pleased to state:
(a) whether construction of the sanctioned additional platform at
Ambikapur railway station has not yet commenced despite completion
of the tender process and award of the work under the jurisdiction of
South East Central Railway and if so, the details thereof;
(b) whether the work could not begin due to non-availability of the site to
the construction department in time by the commercial and operating
departments and if so, the details thereof;
(c) whether the inconvenience is being faced by passengers due to this
delay and if so, the action taken against the officials responsible for the
same; and
(d) the concrete steps taken/being taken by the Government to commence
and complete the construction of the said additional platform within a
stipulated timeframe?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Ambikapur Railway Station presently handles 06 pair of coaching
trains per day. Average Daily passenger footfall at Ambikapur Railway
Station is 4495 persons. To cater these passengers, Facilities like a high
level platform, platform shelter, waiting hall, drinking water arrangement,
urinal, lavatory, seating arrangement etc. are available at Ambikapur
Railway Station.
Further, Ambikapur Railway station has been identified for development
under Amrit Bharat Station Scheme.
§The works taken up for redevelopment of Ambikapur station are as under:
Improvement of station building
Entrance porch
New platform shelter
Improvement of platform surface
Improvement of waiting hall and toilet
New booking counter
Circulating area and parking
Signage
Construction of a passenger platform
Construction of a loop line
Construction of 6m wide Foot Over Bridge
Provision of Coaching Maintenance/Terminal facility having provisions
of 1 Pit Line, 1 Stabling line and 1 Shunting neck
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
Further, Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check for
quality of works and audits. Works are carried out adhering to the
standards and specifications laid down in various codes and manuals.
Progress review/Inspections etc are carried out from time to time at
various levels including DRMs, CAO/Cs, GMs, Railway Board Officers etc.
and necessary action is taken accordingly.
*****