Official TranscriptGOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS RAJYA SABHA UNSTARRED QUESTION NO - 4257 ANSWERED ON - 01/04/2026 AGREEMENTS ON MAINTENANCE AND DEFECT LIABILITY 4257. SHRI SANT BALBIR SINGH: Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state: (a) whether Government, through its implementing agency NHAI, requires contractors to sign written agreements specifying the...
GOVERNMENT OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS RAJYA SABHA UNSTARRED QUESTION NO - 4257 ANSWERED ON - 01/04/2026 AGREEMENTS ON MAINTENANCE AND DEFECT LIABILITY
4257. SHRI SANT BALBIR SINGH:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) whether Government, through its implementing agency NHAI, requires contractors to sign written agreements specifying the maintenance responsibility and defect liability period after the construction of National Highways;
(b) if so, the details of the standard duration of maintenance or defect liability period provided in such contracts for newly constructed highways;
(c) whether contractors are legally bound to repair any damage or deterioration occurring within this stipulated period and the penalties imposed for failure to do so; and
(d) whether any contractor has been penalized, blacklisted or issued notices for failing to maintain highways during the specified maintenance period? ANSWER THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS (SHRI NITIN JAIRAM GADKARI)
(a) & (b) There is provision of Defect Liability Period (DLP) in the Contract / Concession Agreement (CA) of the respective Contractors / Concessionaires to maintain the National Highways (NH) post construction / concession Period.
The Concession period of projects including maintenance in Build-Operate-Transfer (BOT) mode is 15 to 30 years and generally 15 years in case of Hybrid Annuity Model (HAM) projects.
Further, in case of Engineering Procurement & Construction (EPC) Projects, the provision of DLP is for 05 Years for bituminous pavement and 10 Years for concrete pavement.
For Toll-Operate-Transfer (TOT) and InvIT projects, concession period including maintenance is for 20 to 30 years. Concession period for projects on Operate, Maintain and Transfer (OMT) projects is generally 9 years.
For the remaining NHs stretches where DLP period had ended or is not under any concession period of BOT / HAM / TOT / Infrastructure Investment Trust (InvIT) project, maintenance works are being undertaken through Performance Based Maintenance Contract
(PBMC) mode for a period of 5 or 7 Years or Short-Term Maintenance Contract (STMC) mode for a period of 1-2 years.(c) & (d) Remedial work to repair or reconstruct damages during construction or in the DLP is the responsibility of the Contractor / Concessionaire at their own cost as per provisions of contract agreement except in those cases where the Contract Agreement has been terminated, in which case the securities provided are forfeited. Actions against defaulting agencies have been taken as per the provisions of the Contract / Concession Agreement in cases of deficiencies / damages, such as termination of contract agreement, levying of penalties / liquidated damages, debarment / blacklisting, declaring as non-performers, etc. The list of cases where the Contractors/Concessionaires, etc. against whom the actions are initiated in last 3 years is annexed.ANNEXURE ANNEXURE REFERED TO IN REPLY TO PART (c) and (d) OF RAJYA SABHA UNSTARRED QUESTION NO. 4257 TO BE ANSWERED ON 01ST APRIL, 2026 ASKED BY SHRI SANT BALBIR SINGH REGARDING AGREEMENTS ON MAINTENANCE AND DEFECT LIABILITY.
State S. Name of the Project Year of Details of Major Action Taken No. incident damages / defects Arunachal 1 Permanent solution to 2024 RE wall Collapsed Rectification of Pradesh Slip Zones on Papu – defective work initiated Yupia – Hoj – Potin by the Contractor.
section of NH-713A & Penalty of 5% of NH-13 at Km 31.000 contract value imposed (Hoj Market), Km on Contractor.
38.300 (Yabi Village), Km 39.000 (Waterfall), Km 39.700 (Appa Crusher) and Km
40.300 (Crusher Point) in the state of Arunachal Pradesh Andhra 2 Six-laning of 2024 Defects in the Concessionaire Pradesh Vijayawada bypass construction of RE commenced the from Chinna Autupalli wall. rectification work based (Design Ch.0+000) to on recommendation Gollapudi (Design Ch. /suggestion of RE wall 30+000) in Vijayawada Expert.
– Gundugolanu Section Rs.10,99,235/- was of NH-16 in the State recovered as damages of Andhra Pradesh from Concessionaire. under Bharatmala Pariyojana on Hybrid Annuity Mode 3 6 laning of existing 4-2025 Defects in the Contractor rectified lane road from construction of RE defects at his own cost.
Kalaparru (Design Km wall.
Show-cause notices
1050.680) to Chinna issued to Contractor as Avutupalli (Design Km per Contractual
1076.480) of NH-5 provisions. including 6-laneHanuman Junction Bypass from (Existing Km 1055.680 to Km
1060.800) (Design Ch.0.000 to Ch.6.720) (Total Design Length:
27.40 Km) in the State of Andhra Pradesh under NHDP Phase-V under Bharatmala Pariyojana on EPC Mode (Package-2) Bihar 4 Four Laning of 2023 Issues reported by Repair works taken up Simaria-Khagaria CRRI in quality of by Contractor as
Section of NH-31 from Concrete of recommended in CRRI Km. 206.050 to Km. superstructure in report
266.282 (Design bridge at Km 264.946 Chainage) and (Existing Chainage Km. 209.945 to Km.
270.000 of NH-31) in the State of Bihar on EPC Mode 5 Varanasi - Mohania 2023 Major deficiencies in Damages of INR 25 Cr (GTRIP/5; Package - structural elements imposed on Contractor IV A): 4L of existing 2L section from km. 65 to km. 317 of NH-2 in UP and Bihar on NH-2 6 Chhapra-Hajipur 2023 Falling of concrete Project Manager &
Section of NH-19 from the deck slab of Bridge Engineer of the Major Bridge at km (New NH-31) Concessionaire were 145+280 and Falling suspended. of Concrete from the Reconstruction Deck Slab of ROB at completed by Ch 157+860.
concessionaire at their own cost.
7 Umagaon-Saharsa 2024 A girder collapsed Chief Project Manager during construction. & Engineer (Launching)PKG-IV of Contractor suspended. (Kosi Bridge & approach Road) Chhattisgarh 8 4-Laning of Simga-2024 Cracks in Cement Rectifications initiated at Sargaon Section of Concrete Panels cost of EPC Contractor.
NH-200 (New NH-
130) from Km 48+580 to Km 91+026 9 Rehabilitation & 2025 Damage in slab of The work is in Defect Upgradation 2-lane Minor bridge Liability Period and with paved shoulders taken up by Contractor configuration of at his own cost.
Bilaspur Urdawal
section in km 241.553 to 312.60 = 71.0476 km (Masanialala to Rengapali) on NH 200 (New NH 49) (Package-III)(Borai river MNB at km
217.358) Haryana 10 Flyover and underpass 2024 Some portion of deck Arbitration notice issued at Hero Honda Chowk slab fallen down with to Contractor for NH 48 settlement of the recovery of damages. bituminous surface Process of Rectification (MCW-01) on RHS and repair works at Ch. 36+350 initiated.
11 Delhi-Vadodara 2024 Rutting Authority has imposed Expressway Pkg. 2 damages amounting to Rs.48,61,243/- on the contractor for delayed maintenance.
Rectification of rutting has been taken up by Contractor and majority of the rutted portion has been rectified.12 Delhi-Vadodara 2024 Rutting Authority has imposed Expressway Pkg. 3 damages amounting to Rs. 42,95,049/- on the contractor for delayed maintenance.
Rectification of rutting has been taken up by Contractor and majority of the rutted portion has been rectified.
Gujarat 13 Sanchore-Santalpur 2025 Ruts, cracks and Penalty of ₹2.8 crore Package-4 surface deformation/ has been imposed on the Distress was Contractor along with a observed recently recommendation for after rains in June debarment up to one month 2025, severe year or until successful rutting at some rectification, whichever locations. is later. Contractor has taken up repair/ restoration works. The Project Director of NHAI was suspended.
Jharkhand 14 Four Laning of 2024 Cracked PQC panels, Rs. 1.55 Cr penalty Mahulia-Baharagora- Potholes imposed on Contractor.
JH/WB Border Section of NH- 33 (from Km.277+ 500 to Km.333+500) & NH- 06 (from Km.199+200 to Km.183+587) (Length of 71.61Km)in the State of Jharkhand on EPC Pattern under NHDP Phase –III.
Karnataka 15 Two/Four Laning of 2025 Km 337+670 to Concessionaire has BRT Tiger Reserve Km337+680 RE taken up repair/ Boundary to Bengalore Block of length 10 restoration works as per
Section of NH-948 mts collapsed recommendation of report submitted by IISC Bangalore.
16 Four laning of Goa-2024 Incident of collapse Contractor debarred for Karnataka Border to of three spans of 1 month on Aug 2024.
Kundapur section of Kaali Bridge.
NH-66 (formerly NH- Inadequate slope
17) from Km. 93.700 stability works. to Km. 283.300 in the State of Karnataka Kerala 17 NH Connectivity to 2025 Distress in pile Penalty of Rs. 30.74 Cr ICTT at Vallarpdam foundation was was imposed on from Kalamassery to observed at Bridge Contractor Vallarpadam NH 966A no. 07 & 08 Ch.
7+960 and Ch. 9+067
(BHS) 18 Kodugallur to 2025 Damages in the pile Concessionaire debarred Edappally NH 66 foundation Ch. for 1 year. Rectification 398+400 and works taken up at cost of 398+989 (RHS) contractor.
Sub-standard work (Minor Bridge works, backfill material for RS Wall, Poor safety precautions, delayed grouting of girders, bulging of bearing) or poor quality (Defective RE Panels) 19 Chengala- 2025 Authority has suspended Neeleshwaram Section the Concessionaire andof NH-66 Soil nailing collapsed its promoter from future incident occurred at bidding for 01-month Ch. 58+035 to Ch. period. Debarment also 58+100 (RHS) on issued to
16.06.2025 with no Concessionaire. Senior casualties. Bridge Engineer of AE removed from site.
20 Neeleshwaram- 2025 Unprotected soil slip Rectification work Thaliparambha Section in the cut section carried out and traffic of NH-66 with debris restored with deposition on precautionary carriageways. barricading in median portion.
21 NHAI - Six laning RE wall collapsed Debarment of Contractor from start of and Independent 2025 Valanchery bypass to Engineering firm from Kappirikkad section of participating in NH – 66 (old NH-17) ongoing/future bidding from Design Ch. for 01 month period or 298+500 (Ex. km completion of
304.250) to Design investigation by the Chainage 335+850 expert Committee (Ex. km 349.260) in whichever is later. the state of Kerala on Hybrid Annuity Mode under Bharatmala Pariyojana 22 Thuravoor-paravoor 2025 Collapse of 4 PSC Penalty of Rs. 15.35 Girders during Lakhs imposed. Bridge constructions Engineer & Team Leader of AE were Terminated.
23 Six Laning of Start of 2025 Failure/Collapse of Penalty of Rs. 9.55 lakhs Kollam Bypass to scaffolding of Minor imposed on Kadambattukonam Bridge (under Concessionaire from Km.486+000 to construction) at Km.517+800 of NH-47 Km.Ch.
(New NH-66) in the 497+370(RHS) State of Kerala on 24 2025 Failure of RE Wall Rectification initiated by Hybrid Annuity Mode Ch. 504+400 to underBharatmalaPariyojna 504+500(LHS) Concessionaire.
25 6L Elevated Corridor 2025 Toppling of two PSC Contractor and AE along with girders at span P-debarred from future development of 202-P-203 bidding for 1 month. existing 4 lane road at ground level from Aroor to Thuravoor Failure on part of AE Thekku section of NH to review efficacy of 66 material being used in launching and not ensuring application of approved launching scheme.
26 Azhiyur-Vengalam 2024 Soil nailing collapse Rectification initiated by
At Km:191(LHS) and Concessionaire.
Km:193(RHS 27 Ramanattukara- 2025 Defects in RE wall Rectification works Valanchery initiated by Contractor at his own cost.
28 Thaliparamba- 2026 Retaining wall Damaged portion Muzhapilangadu sliding and defects in dismantled and ground improvement rectification works works. initiated by Concessionaire.
Madhya 29 4-laning of Bhopal-2025 Premature failure of Penalty of Rs. 119 Cr Pradesh Bioara section of NH- pavement. imposed on Contractor.
46 Rectification work initiated at the cost of Contractor.
Maharashtra 30 Balance work for 4-2024 Panel cracking, poor Contractor has taken up laning of Panvel to riding quality, rectification works.
Indapur section from bumps, poor km.0.0 to km.42.3 of diversions etc.
NH-66 - EPC 31 Mehkar-Ajispur Road 2024 Cracked panels The Performance BG of Contractor is forfeited.
Process initiated for rectification of damages.32 Bhokar-Sarsam 2024 Cracked panels Contractor has initiated actions for rectification of damages.
33 Sillod-Fardapur 2024 Cracked panels Contractor has initiated actions for rectification of damages.
34 Rehabilitation and Depression & cracks Contractor has initiated upgradation & NH-66 in PQC actions for rectification 2025 (Erstwhile NH-17) of damages. form km 241+300 to 281+300 (Arawali to Kante Section) to four lane with paved shoulder in the state of Maharashtra under NHDP-IV on Hybrid Annuity Mode.
35 Rehabilitation & 2024 PQC cracks and Contractor has replaced Upgradation of NH-66 settlement. cracked panels. (Old NH17) from Km 281+300 to Km 332+200 (Kante to Waked section) to four lanes in the state of Maharashtra under NHDP-IV on Hybrid Annuity Mode.
36 Rehabilitation and up-2024 Full depth Cracks in Contractor has initiated gradation of NH-66 PQC actions for rectification (Old NH-17) form km of damages.
332/200 to km 367/200 (Watul to Talgaon
Section) to four lanes in the State of Maharashtra under NHDP-IV on EPC Mode.37 Rehabilitatyion & up 2025 Cracks in PQC Contractor has initiated gradation for Talere actions for rectification Gaganbawada of damages.
Kolhapur Road (NH- 166G) stretches start from Ch. 6/00 Km. to Ch. 11/00 Km. and Ch.
19/300 Km. (Start of Karul Ghat) to 35/300 Km. (End of Gaganbawada) of NH- 166G to 2 lane paved shoulder/2 lane configuration lane, length 21.00 Km. in the state of Mahrashtra on EPC Mode.
38 Rehabilitation and Up-2024 Cracked panels Rectification of damages gradation to Two lanes taken up at risk and cost with paved shoulder of Contractor. from Karad to Tasgaon NH 266 from Km. 0/00 to 58/830 in the State of Maharashtra on EPC mode 39 Upgradation to two 2024 Post IIT Bombay has been lane with paved construction defects appointed for Technical shoulder are observed in the Investigation of defects from Salaikhurd Rigid Pavement i.e. and suggestion of to Tiroda Km 120/100 formation of remedial measures.
to 163/200 (Design Longitudinal & Km 44/00 to Lateral cracks, 87/00) of NH 753 on Opening of Central EPC Mode in the state Joints, Settlement of of Maharashtra Panels etc.
Rajasthan 40 Delhi Vadodara 2024 Rutting, Raincuts, Penalty imposed on each Expressway NE-4 potholes & settlement contractor amounting to Pkg.06 Rs. 50 Lakhs for non- rectification of defects in the stipulated time frame as per provision ofcontract agreement.
41 Delhi Vadodara 2024 Expressway NE-4 Pkg.07 42 Delhi Vadodara 2024 Expressway NE-4 Pkg.08 43 Delhi Vadodara 2024 Expressway NE-4 Pkg.09 44 Construction of 6-lane 2024 Deficiencies in riding (i) Damage of Rs. 50.00 access-controlled quality and Lakhs imposed upon the Greenfield highway settlement at some Contractor.
from km 28+70 to Km. locations observed (ii) Two key personnel 53+0 of Sangariya of Authority Engineer (near Chautala)-Rasisar team were terminated (near Bikaner) section due to poor supervision. of NH-754K as a part of Amritsar-Jamnagar Economic Corridor in the State of Rajasthan under Bharatmala Pariyojana -Phase-I (AJ/SR-Package-2) 45 Construction of 6-lane 2024 Failure of the nose Penalty of Rs. 1.00 Cr.
access controlled structure while imposed and warning for Greenfield highway launching of 83 mtr debarment action for any from km 53+000 to single span truss future instances upon the Km. bridge Contractor was issued.
88+000 of Sangariya Debarment of (near Chautala)-Rasisar fabrication team and (near Bikaner) section Designer team issued for of NH-754K as a part the period of 02 years in of Amritsar-Jamnagar NHAI works.
Economic Corridor in the State of Rajasthan Penalty of Rs. 20 Lakhs under Bharatmala and warning for Pariyojana-Phase-I debarment action for any (AJ/SR-Package-3) future instances upon theAuthority Engineer.
Debarment of Senior bridge Engineer deployed by the Authority Engineer issued for a period of 2 years in NHAI works.
46 Delhi-Vadodara 2024 Rutting & settlement Damages amounting to Expressway Pkg. 4 of approach Rs. 1.06 Cr. imposed for delayed maintenance.
Also, IIT Kharagpur has been engaged for detailed study for permanent rectification of defects.
47 Delhi-Vadodara 2024 Rutting, settlement of Damages amounting to Expressway Pkg. 5 approach & bulging Rs. 88.32 lakhs imposed of RE wall for delayed maintenance. Bulging of RE wall has been rectified as per suggestions of CRRI.
Majority of the rutting has been rectified.
Further, in addition to above, IIT Kharagpur has been engaged for detailed study for permanent rectification of defects.
48 Delhi-Vadodara 2024 Stretch is operational EPC Contractor has Greenfield Alignment w.e.f. 30.11.2023 and rectified damages. R (NH-148N) (Pkg-16) at some locations the (Ch. 427.300 to settlements observed Ch.452.420) [Major in approaches of bridge over Takli river structure near Nayagaon Jageer village to Rajasthan/MP Border]49 Construction of 2024 Post-completion, Contract has been proposed 2-lane ROB structural defects terminated. Debarment and its approaches in have been observed of contractor taken up.
lieu of existing level in the deck slab of Bid for rectification crossing no. C-64 at the ROB due to works invited. km. 172.990 on honeycombing Jodhpur–Ajmer Road caused by poor on NH-65 in District workmanship.
Nagaur Rajasthan 50 4-laning of 2025 Sethiyathope - The RE wall blocks Cholpauram section portion of the A2 from Km 65.960 to Km The rectification work
(Thanjavur) side
116.440 completed by the approach (LHS side) Concessionaire at their have been own cost. disconnected from the geo grid and fallen down.
51 4-laning of Thanjavur - 2023 The RE wall panel Trichy section from portion of the A1 Based on report of Km 80.000 to Km (Thanjavur) side Expert Committee,
136.490 approach (LHS side) restoration work using have been soil nailing completed disconnected from by Contractor. the geo grid and fallen down.
Uttar 52 Construction of 4 lane 2025 Cracks observed over The project is under Pradesh green field highway DBM due to construction, the repair from km 35.00 to percolation of rain and rectification work
49.155 of NH-731A water in some taken up by the with paved shoulder on stretches. concessionaire at its own Hybrid Annuity Mode cost. in the State of Uttar Pradesh.
53 Lucknow Ring Road 2024 Cracks in PQC Panel Contractor has initiated Pkg-3A in length of 2.886 process for rectification Km. of damages.Uttar 54 4L of Haridwar-Nagina 2023 PQC panel cracks Contractor has initiated Pradesh & section of NH-74 process for rectification Uttarakhand of damages.
Uttarakhand 55 Construction, 2023 Collapse at cavity in Rectification measures Operation and under construction taken up by the EPC Maintenance of 2-Lane Silkyara Tunnel. contractors at its own Bi- Directional cost.
Silkyara Bend Barkot Tunnel with escape passage including Actions as per the approaches on Investigation Committee Dharasu–Yamunotri Report initiated.
section between Ch.
25.400 Km and Ch.
51.000 Km falling along NH-134 (OLD NH-94) in the state of Uttarakhand West Bengal 56 Construction of 4-2025 Cracks have i) Rectification works Laning of Puruliya developed in the initiated by Contractor.
Bypass Section from newly constructed Amount of Rs. 20.00 Km. 84.030 to Km. PQC. Lakh withheld from
94.345 of NH-32 Contractor's bill. (length 10.315 Km) in the State of West ii) Key personal of AE Bengal on EPC Mode has been debarred for a period of one year.
57 Four laning with paved 2023 Cracks in PQC Rectification works shoulders of NH-6 panels completed at cost of from Chichra to EPC Contractor.
Kharagpur Km
185.150 to Km
134.400 including rehabilitation of existing four lane from Km 134.400 to Km
129.600 in the state of West Bengal58 Four laning of 2024 Failure of membrane Rs. 26.19 lacs penalty Berhampore – Farakka pad of Pot – PTFE imposed on
Section of NH-12 (old bearing on P2 of Concessionaire.
NH-34) Ahiron Bridge (Ch. Rectification work 257+440 LHS MJB-completed. truss). Also, a level difference up to 90mm had been observed between expansion joint of deck-I and deck-II along with missing of some anchoring bolts of connecting gusset plates.
59 Four laning of Farakka 2024 Crack at the bottom Rectification work – Raiganj Section of of the deck slab at initiated by NH-12 (old NH-34) km 325+060 of the Concessionaire.
Mahananda Bridge
(LHS). The crack was located under the fast lane between span P1 & P2 (PSC Girder).
At RHS Pier 4 of MJB at 325+223, piles are exposed and heavy reinforcement were exposed.
Exposed reinforcement were corroded.
60 Four laning of 2025 Rutting, Potholes, Rectification initiated by Berhampore – Farakka Cracks Concessionaire at his
Section of NH-12 (old own cost.
NH-34)61 Six Laning of National 2026 Collapse of RE Wall Toll has been suspended.
Corridor NH-19 from 2 key personnel of IE Palsit to Dankuni (up and Concessionaire to NH-6 Connector) suspended. from km 588.870 to km 652.700 in the state of West Bengal under Bharatmala Pariyojana to be executed on BOT
(Toll) basis.
Odisha 62 Chandikhole-Bhadrak 2023 1. Faulty Design in 1. For Faulty Design at
Section of NH-16 Bridge at km. Km 96+326, penalty 96+326: imposed of Rs.30 Lakhs on the Concessionaire and Rs.5 Lakhs on the Independent Engineer.
2. Bridge at km.
Team Leader of IE and 79+614:
Key Personnel of The span A1-P1 had Concessionaire dislodged from the suspended. pier P2 due to breaking of the cantilever
2. For Bridge at km.
79+614:
Portion of the pier cap and had fallen on Penalty of Rs.5 crore the ground. imposed on the Contractor and Penalty of Rs.20 lakh imposed Appearance of wide on the Supervision cracks (up to 3-4mm) Consultant.
in the pier cap on grid “P2”.
Debarment of DPR Consultant for 1 year.
Damages of deck slab and girders of the dislodged span.
The cost of entire remedial measures / reconstruction recovered from the Concessionaire.Assam 63 Construction of 6-lane 2024 Falling of one PSC Penalty imposed on Standalone Flyovers at Girder at Baihata Contractor. Contractor Bongaigaon, Flyover (Span P1-debarred for 4 months.
Chapaguri, Pathsala, P2), resulting in the Simlaguri Chowk and death of one person.
Baihata Junctions on stretches of NH-31 & NH-31C [new NH-27
(EW)] in the State of Assam under Bharatmala Pariyojana on EPC basis Meghalaya 64 Two Lane with paved 2025 Slippage of Penalty of Rs. shoulders configuration Bituminous concrete 20,00,000/- imposed on in Jowai-Meghalaya for a length of Contractor and Assam Border Section approximate 10-15 rectification work of NH - 44 from Km mtrs carried out by
69.200 to Km 173.200 Contractor at his own (design Ch 171.455 ) in cost. the state of Meghalaya Delhi 65 Construction of 2023 P8-P9 of flyover part Remedial measures Dwarka Expressway of Shiv Murti completed by Package-1, from Shiv interchange on Contractor.
Murti Intersection at Dwarka Expressway Km 20 of NH-8 till toppled. road under Bridge
(RUB) near Dwarka Sector-21(From Km -
0.600 to 5.300) in the state of Delhi on EPC mode Andaman & 66 Rehabilitation of km 2024 Distress, sinking of Rectification works Nicobar 181.00 to Km 206.00 pavement at various completed.
Islands section in Andaman locations.
Trunk Road of NH-4 to Intermediate Lane with hard shoulder in the union Territory of Andaman & Nicobar islands (Total length25.00 km) on EPC Mode” (Package-VII) 67 Construction of 4 Nos. 2024 Punching in Deck The EPC contractor has of Minor Bridges at Slab (LHS) of the carried out the necessary Km 21.717, Km minor bridge across rectifications at their
23.150, Km 88.300, BD Nallah at Km own expense including Km 92.100 of NH- 223 88+300 and other replacement of slab as (New NH-4) quality issues recommended by CRRI- connecting South including bad CSIR report.
Andaman and Baratang workmanship.
Island in the Union Territory of Andaman & Nicobar Islands on EPC mode. *****