GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3197
TO BE ANSWERED ON 11.03.2026
ALLOCATION OF FUNDS UNDER ABSS FOR MAHARASHTRA
†3197. DR. SHIVAJI BANDAPPA KALGE:
SHRI NILESH DNYANDEV LANKE:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of Railway Stations in the country particularly in
Maharashtra wherein the redevelopment work has been completed
under the Amrit Bharat Station Scheme (ABSS) along with the list of
those where the said work is under progress at present, Station-wise;
(b) the details of stations where tenders have been officially issued but
work has not yet commenced including the date of award of each
tender;
(c) the details of various means of funding are being used for
implementation of the said scheme along with the number of stations
being funded under each of the said means;
(d) the details of total amount of Central Funds allocated, released and
utilised under the said scheme in Maharashtra since its inception; and
(e) the list of Railway Stations under the said scheme for which the original
date of completion has already elapsed along with the reasons for the
delay and the respective revised timelines for completion thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach.
§The scheme involves preparation of master plans and their implementation
in phases to improve the stations. The master planning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1337 stations have been identified for development under this
scheme, out of which 132 stationsare located in Maharashtra. The names
of stations identified for development under Amrit Bharat Station Scheme
in Maharashtra are as following:State No. of Name of Stations
Stations
Maharashtra 132 Ahmednagar, Ajni (Nagpur), Akalkot Road,
Akola, Akurdi, Amalner, Amgaon,
Amravati, Andheri, Badnera, Balharshah,
Bandra Terminus, Baramati, Belapur,
Bhandara Road, Bhokar, Bhusawal,
Borivali, Byculla, Chalisgaon, Chanda
Fort, Chandrapur, Charni Road,
Chhatrapati Sambhajinagar, Chhatrapati
Shivaji Maharaj Terminus, Chinchpokli,
Chinchwad, Dadar (CR), Dadar (WR),
Dahisar, Daund, Dehu Road, Devlali,
Dhamangaon, Dharangaon, Dharashiv,
Dharmabad, Dhule, Diva, Dudhani,
Gangakher , Godhani, Gondia, Grant Road,
Hadapsar, Hatkanangale, Hazur Sahib
Nanded, Himayatnagar, Hinganghat,
Hingoli Deccan, Igatpuri, Jalgaon, Jalna,
Jeur, Jogeshwari, Kalyan Jn, Kamptee,
Kandivali, Kanjur Marg, Karad, Katol,
Kedgaon, Kinwat , Kopargaon, Kurduwadi
Jn, Kurla Jn, Lasalgaon, Latur, Lokmanya
Tilak Terminus, Lonand Jn, Lonavla,
Lower Parel, Malad, Malkapur, Manmad
Jn, Manwath Road, Marine Lines,
Matunga, Miraj Jn, Mudkhed Jn, Mumbai
Central, Mumbra, Murtizapur Jn,
Nagarsol, Nagpur Jn, Nandgaon, Nandura,State No. of Name of Stations
Stations
Nandurbar, Narkher Jn, Nashik Road,
Netaji Subhash Chandra Bose Itwari
Junction, Pachora Jn, Palghar,
Pandharpur, Panvel Jn, Parbhani Jn, Parel,
Parli Vaijnath, Partur, Phaltan,
Prabhadevi, Pulgaon Jn, Pune Jn, Purna
Jn, Raver, Rotegaon, Sainagar Shirdi,
Sandhurst Road, Sangli, Satara, Savda,
Selu, Sewagram, Shahad, Shegaon,
Shivaji Nagar Pune, Shri Chhatrapati
Shahu Maharaj Terminus Kolhapur,
Solapur, Talegaon, Thakurli, Thane,
Titvala, Tumsar Road, Umri, Uruli, Vadala
Road, Vidyavihar, Vikhroli, Wadsa,
Wardha, Washim, Wathar
Development works at railway stations under Amrit Bharat Station Scheme
in Maharashtra have been taken up at a good pace. Till now, works of 17
stations (Amgaon, Baramati, Chanda Fort, Chinchpokli, Devlali, Dhule,
Kedgaon, Lasalgaon, Lonand Jn, Matunga, Murtizapur Jn, Nandura, Netaji
Subhash Chandra Bose Itwari Junction, Parel, Savda, Shahad, Vadala Road)
in Maharashtra have been completed under this scheme. The activities for
development at other stations have also been taken up at good pace and
progress of some of the stations is as given below:
Diva station: The works of improvement of station building, circulating
area and parking on East side, new entry gate, platform raising and
flooring of platform no. 5/6 and 7/8, platform shelter at platform no. 7/8,new toilet block, sewage treatment plant on West side, improvement of
Foot Over Bridge at Kalyan end and Mumbai end and new staircase for
Foot Over Bridge have been completed. The works of new 6 m Foot Over
Bridge have been taken up.
Mumbra station: The works for improvement of platform surface,
seating arrangement, new toilet block, improvement of booking office,
circulating area, sewage treatment plant and flooring of Foot Over
Bridge have been completed. The work of escalator has been taken up.
Titwala station: The works for station building, entrance gate, platform
surfacing, improvement of ticket booking office, toilet block, sewage
treatment plant and improvement of two wheeler parking and approach
road on East and West side have been completed. The work of new 6 m
Foot Over Bridge have been taken up.
Vikhroli station: The works for improvement of station building on West
side, platform surfacing, platform shelter, new toilet block at Mumbai
end, improvement of toilet block at Kalyan end and Foot Over Bridge
have been completed. The works of new booking office, circulating area
on East and West side and parking of East side have been taken up.
Igatpuri station: The structural work new station building, improvement
of existing station building, entrance gate, booking office, toilet block,
platform surfacing, platform shelter over stairs of Foot Over Bridge and
escalator, circulating area shelter and sewage treatment plant have
been completed. The finishing work of new station building has been
taken up.Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Award of tenders is followed by planning of works for site mobilisation,
preparatory works like relocation of structures, utilities etc. and their
associated clearances. Indian Railways has a well established mechanism
to monitor implementation of projects including their reviews, inspection,
check for quality of works and audits. Works are carried out adhering to
the standards and specifications laid down in various codes and manuals.
Inspections/audits/checks are carried out from time to time by various
agencies/officials/multi-disciplinary teams as per laid down instructions
and actions for correction are taken immediately. This is a continuous and
ongoing process.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport clearance
etc. The progress also gets affected due to brownfield related challenges
such as shifting of utilities (involving water/sewage lines, optical fibre
cables, gas pipe lines, power/signal cables, etc.), infringements, operation
of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines,
etc. and these factors affect the completion time.
Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme is generally funded under Plan Head-53 ‘CustomerAmenities’. The details of allocation and expenditure under Plan Head-53
are maintained Zonal Railway-wise and not work-wise or station-wise or
state-wise. Maharashtra is covered under the jurisdiction of four railway
zones, namely, Central Railway, South Central Railway, South East Central
Railway and Western Railway. For these zones, an allocation of ₹ 3,834
crore has been made for the financial year 2025-26, out of which an
expenditure (up to January, 2026) of ₹ 3,461 crore has been incurred so far.
*****