**Executive Summary**
This document answers questions posed by Shri Tejasvi Surya regarding the redevelopment of railway stations in the Bengaluru Circle under the Amrit Bharat Station Scheme. The Ministry of Railways outlines the progress of the scheme in Karnataka, where 61 stations have been identified for development, including several in the Bengaluru area. While significant progress has been made, the document indicates that no specific time frames can be provided for the projects. The unstarred questions were due to be answered on 11.02.2026.
**Key Points / Main Content**
* **Amrit Bharat Station Scheme:**
* Launched by the Ministry of Railways for the long-term redevelopment of stations.
* 1337 stations identified nationwide, with 61 in Karnataka.
* **Karnataka Stations:**
* Stations in Karnataka selected for redevelopment include: Bangalore Cantt., Krantivira Sangolli Rayanna (Bengaluru Station), Yesvantpur, Malleswaram, Whitefield, Krishnarajapuram, Kengeri, Channasandra, Dodballapur, and many others.
* Development works are underway and progressing well.
* Nine stations (Alnavar, Badami, Bagalkot, Bantawala, Dharwad, Gadag, Gokak Road, Koppal, Munirabad) have been completed.
* **Station Redevelopment Progress (Examples):**
* **Yesvantpur:** Civil works on the east side arrival plaza, sub-station, elevated road, and multi-level car parking are completed.
* **Bangalore Cantt.:** Diversion road, training center, hostel, and structural work of the south side station building have been completed.
* **Whitefield:** Construction of boundary wall, improvement of parking, provision of platform shelter on PF 1 & 2, and ladies waiting hall have been completed.
* **Amrit Bharat Station Scheme – Scope:**
* Includes preparation of master plans and phased implementation.
* Encompasses improvements to station access, circulating areas, station building, waiting halls, toilets, foot over bridges, platforms, lifts, parking, amenities for disabled persons, and information systems.
* **Project Funding and Monitoring:**
* Funded under Plan Head-53 "Customer Amenities."
* Allocation for South Western Railway: ₹ 572 crore (Revised Estimate) for FY 2025-26.
* Expenditure incurred up to Dec. 2025: ₹ 468 Crore.
* Projects monitored through IRPSM (Indian Railway Project Sanction and Management).
* **Challenges and Timelines:**
* Development requires various statutory clearances and faces challenges like utility shifting, operational constraints, and safety concerns.
* No specific time frame can be indicated for project completion due to the complexity and variable factors involved.
**Impact Analysis**
**Stakeholder: Passengers**
* **Impact:** Improved station facilities, including better access, waiting areas, amenities, and overall passenger experience.
* **Action Required:** None, the passengers just need to avail the facilities provided
**Stakeholder: Ministry of Railways**
* **Impact:** Responsible for implementing the Amrit Bharat Station Scheme and monitoring project progress.
* **Action Required:** Continue project implementation, monitoring, and addressing challenges to ensure timely and effective redevelopment of stations.
**Stakeholder: South Western Railway**
* **Impact:** Responsible for execution of the projects within their jurisdiction.
* **Action Required:** Execute project, adhere to the guidelines, monitor the progress and flag the issues faced during execution so that the Ministry of Railways is aware of the progress.
**Stakeholder: Local Businesses**
* **Impact:** Potential opportunities for setting up kiosks and participating in the 'One Station One Product' scheme, potentially leading to increased revenue and visibility.
* **Action Required:** Explore the option to set up the shop at the railway station, participate in the 'One Station One Product' scheme.
Key Entities Referenced
Amrit Bharat Station Scheme: A scheme by the Ministry of Railways for the redevelopment and modernization of railway stations across India.
Ministry of Railways: The Indian government ministry responsible for the country's rail transport.
Karnataka: The state in India where 61 railway stations are being redeveloped under the Amrit Bharat Station Scheme, including stations within the Bengaluru Circle.
Bengaluru Circle: A geographical region containing a number of railway stations that are being redeveloped under the Amrit Bharat Station Scheme.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 1898
TO BE ANSWERED ON 11.02.2026
BENGALURU CIRCLE UNDER AMRIT BHARAT STATION SCHEME
1898. SHRI TEJASVI SURYA:
Will the Minister of RAILWAYS be pleased to state:
(a) the list of the railway stations in the Bengaluru Circle being redeveloped
under the Amrit Bharat Station Scheme, along with the date of
commencement of works at each station;
(b) the details of the sanctioned cost, revised cost, if any, expenditure
incurred so far, and the reasons for cost overruns, wherever reported,
station wise;
(c) the timelines fixed for completion of works at each of these stations
and the current physical and financial progress, station wise; and
(d) the measures taken/being taken by the Government to ensure timely
completion of redevelopment works and to prevent further cost
escalation along with revised completion schedules?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Ministry of Railways has launched Amrit Bharat Station Scheme
for redevelopment of stations with a long-term approach. So far, 1337
stations have been identified for development under Amrit Bharat Station
Scheme, out of which 61 stations are located in Karnataka. This includes
stations of Bangalore Cantt., Krantivira Sangolli Rayanna (Bengaluru
Station), Yesvantpur, Malleswaram, Whitefield, Krishnarajapuram, Kengeri,
…2/-
§-2-
Channasandra and Dodballapur, which are located in Bengaluru City area.
The names of stations identified for development under Amrit Bharat
Station Scheme in Karnataka are as following:
State No. of Names of Amrit Stations
Amrit
Stations
Karnataka 61 Almatti, Alnavar, Arsikere Junction, Badami,
Bagalkot, Ballary, Bangalore Cantt., Bangarpet,
Bantawala, Belagavi, Bidar, Bijapur, Chamaraja
Nagar, Channapatna, Channasandra,
Chikkamagaluru, Chitradurga, Davangere,
Dharwad, Dodballapur, Gadag, Gangapur Road,
Gangavathi, Ghataprabha, Gokak Road, Gubbi,
Harihar, Hassan, Hosapete, Kalaburagi, Kengeri,
Kopal, Krantivira Sangolli Rayanna (Bengaluru
Station), Krishnarajapuram, Malleswaram, Malur,
Mandya, Mangalore Central, Mangalore Jn.,
Munirabad, Mysore, Raybag, Raichur,
Ramanagaram, Ranibennur, Sagar Jambagaru,
Sakleshpur, Shahabad, Shivamogga Town,
Shravanabelagola, Shree Siddharoodha Swamiji
Hubballi Jn, Subramanya Road, Talguppa, Tiptur,
Tumakuru, Udupi, Wadi, Whitefield, Yadgir,
Yesvantpur, Chikkodi Road Station
…3/--3-
Development works at railway stations under Amrit Bharat Station Scheme
in Karnataka have been taken up at a good pace. Till now, works of 09
stations (Alnavar, Badami, Bagalkot, Bantawala, Dharwad, Gadag, Gokak
Road, Koppal, Munirabad) in Karnataka have been completed. The works at
other stations have also been taken up at good pace and progress of some
of the above stations is as given below:
Yesvantpur station: The civil works of east side arrival plaza, civil
works of east side sub-station, east side elevated road and multi level
car parking have been completed. The finishing works of east side
arrival plaza, east side elevated road and multi level car parking,
sewage treatment plant, structural work of west side station building,
platform shelters and air concourse have been taken up.
Bangalore Cantt. station: The works of 24 m wide diversion road on the
south side, training centre, hostel on North side and structural work of
south side station building have been completed. The finishing work of
south side station building, structural work of north side station
building, foot over bridge, south basement and circulating area have
been taken up.
Whitefield: The works for construction of boundary wall, improvement
of 2 & 4 wheeler parking, provision of platform (PF) shelter on PF 1 & 2
and ladies waiting hall have been completed. The works for provision
of platform shelter on PF 3 & 4, construction of food plaza,
improvement of station with new canopy and construction of 12 m
wide foot over bridge have been taken up.
…4/--4-
Krishnarajapuram: The works for pay & use toilet and improvement of
2 & 4 wheeler parking at back of platform 4 have been completed. The
works for provision of 3rd entry booking office, construction of waiting
hall, provision of platform shelters and improvement of parking at 3rd
entry have been taken up.
Kengeri: The works for improvement of 4 wheeler parking at main
entry side, structural works of 2nd entry station building, 2nd entry
approach road, 2 wheeler parking at 2nd entry and pay & use toilet at
PF 4 have been taken up. The works for 2nd entry station building
finishes, provision of platform shelters, extension of main entry station
building (waiting hall), construction of 12 m wide foot over bridge and
improvement of circulating area at main entry side have also been
taken up.
Dodballapur: The works for improvement of 2 & 4 wheeler parking at
main entry has been completed. The works for provision of platform
shelters, pay & use toilet, provision of 2nd entry station building,
improvement of 2nd entry parking area and provision of 12 m wide
foot over bridge have been taken up.
The Amrit Bharat Station scheme involves preparation of master plans and
their implementation in phases to improve the stations. The master
planning, keeping in view the necessity at each station includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
…5/--5-
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
• Amenities for Divyangjans
• Better passenger information systems
• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
Further, development / redevelopment of station on Indian Railways is a
continuous and ongoing process and works in this regard are undertaken
as per requirement, subject to inter-se priority and availability of funds. The
priority for development / redevelopment / upgradation / modernisation of
stations is accorded to higher category of station over lower category of
station while sanctioning and executing the works.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
..6/--6-
Head-53 are maintained Zonal Railway-wise and not station-wise or state-
wise. Stations of Bengaluru City area are covered under the jurisdiction of
South Western Railway. For South Western Railway, allocation of ₹ 572
crore (Revised Estimate) has been made for the financial year 2025-26
under Plan Head-53 and expenditure of ₹ 468 Crore (up to Dec. 2025) has
been incurred so far.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport clearance
etc. The progress also gets affected due to brownfield related challenges
such as shifting of utilities (involving water/sewage lines, optical fibre
cables, gas pipe lines, power/signal cables, etc.), infringements, operation
of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines,
etc. and these factors affect the completion time. Therefore, no time frame
can be indicated at this stage.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check for
time and cost overruns, quality of works and audits. Monitoring of projects
is done at various levels including through dedicated portal of Indian
Railways named Indian Railway Project Sanction and Management (IRPSM).
Works are carried out adhering to the standards and specifications laid
down in various codes and manuals. Inspections/audits/checks are carried
out from time to time by various agencies/officials/multi-disciplinary teams
as per laid down instructions and actions for correction are taken
immediately. The issues faced by the executing units are accordingly
addressed. This is a continuous and ongoing process.
*****