GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6162
TO BE ANSWERED ON 01.04.2026
BENGALURU SUBURBAN RAIL PROJECT
6162. DR. K SUDHAKAR:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the current status of the four corridors under the
Bengaluru Suburban Rail Project;
(b) the details of the specific reasons for the delays in the execution of the
project despite repeated citizen demands;
(c) the details of the total funds sanctioned and the actual expenditure
incurred on the project till date;
(d) whether any revised deadline has been set for the completion of the
Mallige and Kanaka corridors and if so, the details thereof;
(e) the details of the steps being taken to resolve land acquisition and
coordination issues between K-RIDE and South Western Railway; and
(f) the details of the steps taken to resolve the concerns of passenger
forums and citizens regarding the delay in the project?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Rail Infrastructure Development Company (Karnataka) Limited (K-
RIDE), a Company controlled by State Government of Karnataka (51%
equity) is executing the Bengaluru Suburban Rail Project (BSRP). BSRP
(148.17 Km) has been sanctioned at a cost of ₹ 15,767 Cr. with 20% funding
each by Government of India and Government of Karnataka and 60%
through debt.
§ Page 1 of 6There are four Corridors in BSRP. The status of these corridors is as under:
Corridor-1 (Sampige): KSR Bengaluru City – Devanahalli (41.4 Km)
Alignment plans have been approved. Land acquisition has been taken up
by State Government. Shifting of S&T and electrical utilities have also
been taken up.
Corridor-2 (Mallige): Baiyyapanahalli – Chikkabanawara (25.01 Km)
The entire land acquisition has been completed. For station buildings,
separate contracts have been awarded and work is in progress. For other
works, tender has been invited.
Corridor-3 (Parijaata): Kengeri – Whitefield (35.52 Km)
Alignment plans have been approved. Land acquisition has been taken up
by State Government. Shifting of S&T and electrical utilities have also
been taken up.
Corridor-4 (Kanaka): Heelalige – Rajankunte (46.25 Km)
The land acquisition has been taken up. So far, 7.8 acre land out of 57 acre
land has been acquired. For station buildings, separate contracts have
been awarded and work is in progress in the available land.
The project has been delayed due to non-acquisition of private land and
transfer of State Government’s land by the Government of Karnataka.
An expenditure of Rs. 2659 Cr. has been incurred on the BSRP project.
Regular coordination meetings of K-RIDE and Railway are being held
regularly to resolve issues.
Page 2 of 6Karnataka:
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Karnataka is as under:
Period Outlay
2009-14 ₹835 crore/year
2025-26 ₹7,564 crore (more than 9 times)
Projects sanctioned:-
As on 01.04.2025, 25 projects (15 new lines, 10 doubling) of 3,264 km
length, costing ₹ 42,517 crore falling fully/partly in Karnataka are
sanctioned. The summary is as under:-
Category No of Total Length Exp
sanctioned Length Commissioned upto Mar'25
Projects (in km) Upto Mar'25 (km) (₹ in cr.)
New Line 15 2,034 421 8,794
Doubling/ 1,230 973 12,516
10
Multitracking
Total 25 3,264 1,394 21,310
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
Karnataka are as under :
S. No Project Cost (₹in Crores)
1 Kottur-Harihar new line (65 km) 468
2 Hassan-Bangalore new line (167 km) 1,290
3 Bidar-Gulbarga new line (110 km) 1,543
4 Shivani - Hosadurga Road doubling (10
50
km)
5 Shivani-Birur Doubling (29 km) 143
6 Hosadurga-Chikjajur doubling (29 km) 260
Page 3 of 67 Ramanagram - Mysore patch doubling
998
(94 km)
8 Yelahanka – Chennasadra doubling (13
108
km)
9 Yeshwantpur - Yelahanka doubling(12
95
km)
10 Netrawati - Mangalore Central doubling
28
(2 km)
11 Kankanadi - Panambur doubling (19 km) 350
12 Arsikere-Tumkur doubling (96 km) 758
13 Yelahanka - Penukonda doubling (123 1,104
km)
14 Daund-Gulbarga doubling (225 km) 3,182
15 Hubli-Chikjajur doubling (190 km) 1,850
Ongoing Projects:-
Some of the projects falling fully/partly in Karnataka which have been taken
up are as under:
S Cost
Project
No. (₹ in Crores)
1 Hospet - Hubli - Londa - Vasco - de - Gama 4,153
doubling (312 km)
2 Hotgi-Gadag doubling (284 km) 2,459
3 Ginigera - Raichur new line (165 km) 3,401
4 Gadag - Wadi new line (257 km) 2,842
5 Bagalkot – Kudachi new line (142 km) 1,649
6 Tumkur – Rayadurga new line (207 km) 2,496
7 Tumkur – Davangere new line (182 km) 2,142
8 Kadur – Chikmagalur – Belur new line (68 km) 825
9 Baiyyapanahalli – Hosur doubling (48 km) 336
10 Yeshwanthpur – Channasandra doubling (22 314
km)
11 Hosapete – Ballari 3rd & 4th line (65 Km) 2,372
12 Ballari-Chikjajur doubling(185 KM) 3,342
13 Bypass line between Bettahalsoor- 248
Rajanakunte (6 Km)
Page 4 of 6Details of some major projects which are delayed due to land acquisition
are as under:-
Total Land Balance
Land acquire Land to
S
Project require d be
No.
d (in ha) acquired
(in ha) (in ha)
1 Shimoga – Rannebennur new
559 226 333
line (96 km)
2 Belgaum–Dharwad new line (73
581 0 581
km)
3 Shimoga–Harihar new line (79
488 0 488
km)
4 Whitefield - Kolar new line (53
337 0 337
km)
5 Hassan-Belur new line (32 km) 206 0 206
Summary of the status of land acquisition in Karnataka is as under:-
Total Land required for Projects in 9,064 ha
Karnataka
Land Acuired 5,707 ha (63%)
Balance Land to be acquired 3,357 ha (37%)
Government of India is geared up to execute projects, however success
depends upon the support of Government of Karnataka.
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Page 5 of 6 Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****
Page 6 of 6