GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4331
TO BE ANSWERED ON 18.03.2026
BG LINE BETWEEN SWAMIHALLI TO RAYADURGA (ANDHRA PRADESH)
4331. SHRI E TUKARAM:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the current status of the Final Location Survey (FLS)
report of the Broad Gauge (BG) Line between Swamihalli (Ballari
District, Sandur Taluk, Karnataka) and Rayadurga (Andhra Pradesh) via
junction and Obalapuram Railway Station (Andhra Pradesh);
(b) the details of the timeline for the completion of the Final Location
Survey report/DPR of said line including commencement of effective and
meaningful work on the project; and
(c) the details of the estimated cost of the project including the allocation
of funds during the current financial year?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Swamihalli is already connected to Rayadurga with existing
railway network via Hosapete and Obalapuram. However, to provide direct
connectivity, Final Location Survey (FLS) of Swamihalli – Rayadurga New
Line (52 Km) has been completed and Detailed Project Report (DPR) has
been prepared.
After preparation of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
...2/-
§-2-
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines cannot be fixed.
Karnataka:
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Karnataka is as under:
Period Outlay
2009-14 ₹835 crore/year
2025-26 ₹7,564 crore (more than 9 times)
Project sanctioned:-
As on 01.04.2025, 25 projects (15 new lines, 10 doubling) of 3,264 km
length, costing ₹ 42,517 crore falling fully/partly in Karnataka are
sanctioned. The summary is as under:-
Category No of Total Length Exp
sanctioned Length Commissioned upto Mar'25
Projects (in km) Upto Mar'25 (km) (₹ in cr.)
New Line 15 2,034 421 8,794
Doubling/ 1,230 973 12,516
10
Multitracking
Total 25 3,264 1,394 21,310
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
...3/--3-
Karnataka are as under :
S. Project Cost
No (₹in Crores)
1 Kottur-Harihar new line (65 km) 468
2 Hassan-Bangalore new line (167 km) 1,290
3 Bidar-Gulbarga new line (110 km) 1,543
4 Shivani - Hosadurga Road doubling
50
(10 km)
5 Shivani-Birur Doubling (29 km) 143
6 Hosadurga-Chikjajur doubling (29 km) 260
7 Ramanagram - Mysore patch doubling
998
(94 km)
8 Yelahanka – Chennasadra doubling
108
(13 km)
9 Yeshwantpur - Yelahanka doubling
95
(12 km)
10 Netrawati - Mangalore Central doubling
28
(2 km)
11 Kankanadi - Panambur doubling (19 km) 350
12 Arsikere-Tumkur doubling (96 km) 758
13 Yelahanka - Penukonda doubling 1,104
(123 km)
14 Daund-Gulbarga doubling (225 km) 3,182
15 Hubli-Chikjajur doubling (190 km) 1,850
Ongoing Projects:-
Some of the projects falling fully/partly in Karnataka which have been taken
up are as under:
S Cost
Project
No. (₹ in Crores)
1 Hospet - Hubli - Londa - Vasco - de - Gama 4,153
doubling (312 km)
...4/--4-
2 Hotgi-Gadag doubling (284 km) 2,459
3 Ginigera - Raichur new line (165 km) 3,401
4 Gadag - Wadi new line (257 km) 2,842
5 Bagalkot – Kudachi new line (142 km) 1,649
6 Tumkur – Rayadurga new line (207 km) 2,496
7 Tumkur – Davangere new line (182 km) 2,142
8 Kadur – Chikmagalur – Belur new line 8 2 5
(68 km)
9 Baiyyapanahalli – Hosur doubling (48 km) 336
10 Yeshwanthpur – Channasandra doubling 3 1 4
(22 km)
11 Hosapete – Ballari 3rd & 4th line (65 Km) 2,372
12 Ballari-Chikjajur doubling (185 KM) 3,342
13 Bypass line between Bettahalsoor- 248
Rajanakunte (6 Km)
in last three years 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 65 surveys (25 new line and 40 doubling) covering a total length of
7,240 km has been sanctioned falling fully/partly in the State of Karnataka.
Details of some major projects which are delayed due to land acquisition
are as under:-
Total Land Balance
Land acquired Land to
S
Project required (in ha) be
No.
(in ha) acquired
(in ha)
1 Shimoga – Rannebennur new line
559 226 333
(96 km)
2 Belgaum–Dharwad new line (73 km) 581 0 581
3 Shimoga–Harihar new line (79 km) 488 0 488
4 Whitefield - Kolar new line (53 km) 337 0 337
5 Hassan-Belur new line (32 km) 206 0 206
...5/--5-
Summary of the status of land acquisition in Karnataka is as under:-
Total Land required for Projects in Karnataka 9,064 ha
Land Acquired 5,707 ha (63%)
Balance Land to be acquired 3,357 ha (37%)
Government of India is geared up to execute projects, however success
depends upon the support of Government of Karnataka.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
...6/--6-
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****