Executive Summary:
The document provides a status update on the Namami Gange Programme (NGP) in West Bengal as of July 24, 2025. It details the progress of sewage infrastructure, ghat and crematoria projects, challenges faced during execution, and the total funds allocated and utilized since the program's inception in FY 2014-15 until June 30, 2025. The information was provided in response to questions raised in Lok Sabha.
Key Points / Main Content:
* **Sewage Infrastructure Projects:**
* 31 projects sanctioned at a cost of ₹4,605.72 crore.
* 16 projects completed and operational.
* **Ghat and Crematoria Projects:**
* 10 projects sanctioned, comprising 14 ghats and 9 crematoria, at a cost of ₹49.67 crore.
* 13 ghats and 3 crematoria completed and handed over to Urban Local Bodies (ULBs).
* **Challenges:**
* Identification of suitable land for new Sewage Treatment Plants (STPs).
* Obtaining statutory clearances, including right of way for sewage-related networks.
* **Government Actions:**
* The National Mission for Clean Ganga (NMCG) is actively monitoring project status.
* Regular review meetings are conducted under competent authority and through the Central Monitoring Committee (CMC).
* **Funds Allocated and Utilized:**
* ₹1,906.14 crore disbursed under the Namami Gange Programme in West Bengal from FY 2014-15 to June 30, 2025.
Impact Analysis:
* **State Government (West Bengal):**
* *Impact:* Responsible for the implementation of the Namami Gange Programme within the state, including overseeing the progress of sewage infrastructure and ghat/crematoria projects. Affected by challenges related to land identification and statutory clearances.
* *Action Required:* Facilitate land acquisition for STPs, expedite statutory clearances, and collaborate with NMCG to address project roadblocks.
* **Urban Local Bodies (ULBs):**
* *Impact:* Responsible for the operation and maintenance of completed ghats and crematoria.
* *Action Required:* Effectively manage and maintain the completed infrastructure handed over to them.
* **National Mission for Clean Ganga (NMCG):**
* *Impact:* Responsible for monitoring the progress of projects, identifying roadblocks, and ensuring timely resolutions.
* *Action Required:* Continue monitoring project status, conduct regular review meetings, and provide support to address challenges.
* **State Missions for Clean Ganga (West Bengal):**
* *Impact:* Responsible for implementing projects and interventions under the Namami Gange Programme.
* *Action Required:* Utilize disbursed funds effectively, address challenges in project execution, and coordinate with NMCG for support.
Key Entities Referenced
Namami Gange Programme: Flagship program of the Government of India for the rejuvenation of the River Ganga.
West Bengal: State in eastern India where Namami Gange Programme projects are being implemented.
River Ganga: The major river in India which the Namami Gange Programme aims to rejuvenate.
National Mission for Clean Ganga (NMCG): The implementing agency for the Namami Gange Programme.
Ghat: Embankment or series of steps leading down to a river.
Sewage Treatment Plants (STPs): Facilities designed to treat sewage and wastewater to remove pollutants.
Lok Sabha: The lower house of the Parliament of India, where the question regarding the Namami Gange Programme was raised.
Ministry of Jal Shakti: The Indian government ministry responsible for water resources, river development and Ganga rejuvenation.
GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 810
ANSWERED ON 24.07.2025
CHALLENGES UNDER NAMAMI GANGE PROGRAMME
810. SHRI JAGANNATH SARKAR
Will the Minister of JAL SHAKTI be pleased to state:
(a) the current status of the Namami Gange Programme in West Bengal and the details of all 27 sewage
infrastructure projects including details of completed, ongoing and pending projects along with the funds
sanctioned for each of them;
(b) the number of Ghat and Crematoria projects initiated under this programme in West Bengal along with
the present status thereof;
(c) the specific challenges being faced in the execution of Namami Gange projects in West Bengal and the
steps being taken by the Government to address these challenges; and
(d) the total funds allocated and utilized under the Namami Gange Programme in West Bengal till date?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) Under the Namami Gange Programme (NGP), a total of 31 projects at a cost of ₹4,605.72 crore have
been sanctioned in West Bengal, out of which 16 projects have been completed and made operational. The
detailed list of projects, along with the sanctioned cost, is enclosed at Annexure I.
(b) Under the NGP in West Bengal, a total of 10 projects, comprising 14 ghats and 9 crematoria, have been
sanctioned at a cost of ₹49.67 crore. Out of these, 13 ghats and 3 crematoria have been completed and
handed over to the respective Urban Local Bodies (ULBs).
(c) The identification of suitable land for the establishment of new Sewage Treatment Plants (STPs) and
issue of statutory clearances like right of way for sewage-related networks have emerged as major
challenges. To address and overcome these challenges, the National Mission for Clean Ganga (NMCG) has
been actively involved in closely monitoring the status of the projects. NMCG regularly conducts
comprehensive review meetings under the chairmanship of competent authority and through Central
Monitoring Committee (CMC) to evaluate progress, identify potential roadblocks, and ensure timely
resolutions.
(d) The details of funds disbursed to various agencies, including State Missions for Clean Ganga in the
State of West Bengal, for the implementation of projects/interventions under the Namami Gange
Programme from its inception (FY 2014–15) till 30 June 2025 are enclosed at Annexure II.
***
1ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO. 810 TO BE
ANSWERED IN LOK SABHA ON 24.07.2024 REGARDING “CHALLENGES UNDER NAMAMI
GANGE PROGRAMME”.
Detailed list of NMCG’s of projects, along with the sanctioned cost
SI Towns Name/Nature of works Approve Status
Project cost
(in Cr.)
1 Gayeshpur Sewerage system & STP 168.67 Completed
2 Kalyani Sewerage system & STP 57.87 Completed
3 Bhatpara Sewerage system & STP 228.52 Completed
4 Halisahar Sewerage scheme & STP Halishar 332.56 Completed
5 Budge-Budge Sewerage System and STP at Budge-Budge 225.45 Completed
6 Barrackpore Sewerage system with Sewer network and STP - 341.68 Completed
Kancharapara Interception & Diversion with STP(Upgradation of Completed
7 48.77
(Barrackpore) existing 13 MLD STP to 18 MLD capacity)
Barrackpore Design and Build of I & D structure. including Lock Completed
Municipality Gate and it's all appurtenant structures as well as
8 0.93
allied works at Barrackpore Municipality, North 24
Parganas, West Bengal State
Howrah Pollution Abatement Works for River Ganga at Completed
Howrah(Interception & Diversion with STP) (under
9
Hybrid annuity based PPP mode-Namami Gange
Programme)
Bally Pollution Abatement Works for River Ganga at Bally Completed
under Howrah Municipal Corporation (Interception 595.72
10
& Diversion with STP (under Hybrid annuity based
PPP mode-Namami Gange Programme)
Kamarhati and STP & Sewer network - (under Hybrid annuity based Completed
11 Baranagar PPP mode-Namami Gange Programme)
Municipalities
Nabadwip DPR of Interception & Diversion Network for Completed
12 existing drains falling in river Ganges including STP 61.23
at Nabadwip Muncipality
Jangipur Pollution Abatement Works for River Ganga at Completed
13 68.47
Municipality Jangipur (Interception & Diversion with STP)
Maheshtala Pollution Abatement works for River Ganga at Completed
Town Maheshtala- Municipal Town (Interception &
14 286.97
Diversion with STP)under Hybrid Annuity based PPP
mode
Level 2 Hoogly Rejuvenation of existing STPs alongwith lifting Completed
15 86.61
stations & pumping station
Level 2 North 24 Rejuvenation of existing STPs alongwith lifting Completed
16 65.54
Parganas stations & pumping stations
Burdwan Faecal Sludge Management for abatement of Tendering
17 10.35
pollution in River Ganga (FSTP)
2SI Towns Name/Nature of works Approve Status
Project cost
(in Cr.)
18 keorapukur Rehabilitation of existing STP keorapukur 114.74 Tendering
Murshidabad Pollution Abatement Sewerage Project (Interception Tendering
19 72.63
and Diversion with STP)
Katwa Pollution Abatement Sewerage Project (Interception Tendering
20 and Diversion with STP, 14 MLD STP with co- 133.46
treatment 10.5 KLD)
Uttarpara- Pollution Abatement Integrated Septage Treatment Tendering
21 Kotrung Plant for Uttarpara-Kotrung Municipality, Hooghly 8.04
Dist. Town (FSTP)
Pujali Integrated Septage Treatment Plant for Pujali, South Tendering
22 5.77
24 Parganas District (FSTP)
Tolly's Nullah Pollution Abatement work for Rejuvenation of River Under
23 817.3
(Adi Ganga) Adi Ganga, Kolkata Progress
Berhampore Pollution Abatement works for River Ganga at Under
24 Behrampore- Municipal Town (Interception & 51.21 Progress
Diversion)
Kolkata Pollution Abatement Works for River Ganga at Under
Kolkata municipality (Installation of New Progress
Penstock/construction of I & D structures Gates and
25 7.11
Refurbishment of Existing Gates/I & D structures
along the Bank (Eastern & Western) of Beliaghata
Circular Canal)
Kolkata Pollution Abatement Works for River Ganga at Under
Kolkata (Garden Reach) municipality (Interception & Progress
26 289.02
Diversion with STP) under Hybrid Annuity based
PPP mode
Hooghly- Pollution Abatement works for River Ganga at Under
27 Chinsurah Hooghly Chinsurah- Municipal Town (Interception & 154.73 Progress
Diversion with STP)
North Pollution Abatement Works for River Ganga at North Under
28 Barrackpore Barrackpore municipality(Interception and Diversion 154.27 Progress
with STP)
Chakdah Pollution Abatement Sewerage Project (Interception Under
29 and Diversion with STP) at Chakdah Municipal 121.66 Progress
Town
Krishnanagar Pollution Abatement Sewerage Project (Interception Under
30 and Diversion with STP) at Krishnanagar Municipal 91.88 Progress
Town
Bansberia Pollution Abatement Sewerage Infrastructure Under
31 (Integrated Septage Treatment Plant) at Bansberia 4.56 Progress
Municipal Town (FSTP)
Total 4,605.72
3ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PART (d) OF UNSTARRED QUESTION NO. 810 TO BE
ANSWERED IN LOK SABHA ON 24.07.2024 REGARDING “CHALLENGES UNDER NAMAMI
GANGE PROGRAMME”.
Funds released in the State of West Bengal under Namami Gange Programe
from FY 2014-15 to 30th June 2025.
₹. in Crore
Beneficiary Agency Purpose/Objective Total
State Mission for Clean Ganga Sewerage Infrastructure Projects, Institutional 1,118.97
Development, Communication & Outreach
Activities
State Forest Department Afforestation 20.86
Engineering Projects (India) 20.43
Limited Ghats & Crematoria Projects
Concessionaires of Hybrid Hybrid Annuity Mode (HAM) Projects at 509.88
Annuity Mode (HAM) Projects Howraha-Bally-Baranagar, North Barrackpore
& Garden Reach
Sanitation Mission Rural Sanitation Scheme 236.00
Grand Total 1,906.14
*****