GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
RAJYA SABHA
UNSTARRED QUESTION NO. 4077
ANSWERED ON 30.03.2026
DAM REHABILITATION AND IMPROVEMENT PROJECT PHASE-II
4077 SHRI IRANNA KADADI:
Will the Minister of Jal Shakti be pleased to state:
(a) the nationwide progress achieved in conducting rigorous, technologically advanced structural
inspections under the landmark Dam Safety Act;
(b) whether the rapid deployment of the Dam Rehabilitation and Improvement Project (DRIP) Phase-II
has successfully fortified critical aging dam infrastructure;
(c) the details of the substantial funds specifically allocated and efficiently utilized for integrating
sophisticated early warning systems;
(d) the successful establishment of the National Dam Safety Authority ensuring uniform, stringent
safety protocols across all States; and
(e) the proactive steps taken to conduct nationwide mega mock-drills to ensure absolute preparedness
for extreme weather and flood events?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) The Union Government enacted the Dam Safety Act, 2021, which came into effect on 30th
December 2021. The Act provides a comprehensive framework for surveillance, inspection, operation,
and maintenance of specified dams across the country, ensuring their safe functioning and minimizing
the risk of dam-related disasters. Since its enactment, dam inspections have been institutionalized in all
States/UTs, with mandatory pre-monsoon and post-monsoon safety audits. Furthermore, several
States/UTs have constituted Independent Panels of Experts to undertake comprehensive safety
evaluations, thereby strengthening surveillance, maintenance, and overall resilience of specified dams.
The year-wise details of pre-monsoon and post-monsoon inspections of specified dams, as reported
by the respective dam owners, are presented in the table below:
Year Pre-Monsson Inspection of Dams (Nos.) Post-Monsson Inspection of Dams (Nos.)
2023 6414 5881
2024 6366 6456
2025 6524 6555
(b) To improve the safety and operational performance of selected existing dams across the country,
Govt. of India is implementing the Dam Rehabilitation and Improvement Project (DRIP), Phase-II & III
1with external funding. The project emphasizes rehabilitation works, safety improvement, and capacity
building, ensuring that vulnerable dams are strengthened against structural and hydrological risks.
Further, the digital tools developed under DRIP-II are enabling dam owners, State Dam Safety
Organizations, and the National Dam Safety Authority to effectively fulfill their obligations under the
Dam Safety Act, 2021 within the prescribed timelines. In parallel, the capacity-building programmes
conducted under the project have been effective in strengthening institutional frameworks across States.
Moreover, under DRIP-II, the technology demonstration both related to use of diagnostic tools,
studies and rehabilitation techniques is helping the States to adopt cost effective solutions. Apart from
this, major rehabilitation works on 40 distressed dams have been completed under the scheme.
(c) Project allocations under DRIP Phase-II are made to implementing agencies on the basis of
comprehensive proposals that encompass both structural and non-structural measures for selected dams,
including provision of early warning systems. In line with the Dam Safety Act, 2021, these agencies
have made proposal for installation of instrumentation for health monitoring of dams. To facilitate this,
the Central Water Commission has prepared and circulated standard bidding documents for
instrumentation works at dams and barrages, while also extending technical support to States in
formulating their instrumentation plans. Simultaneously, DRIP implementing agencies are developing
Emergency Action Plans for their designated dams and establishing early warning to ensure timely alerts
to downstream communities.
(d) The National Dam Safety Authority (NDSA) has been established under the Dam Safety Act, 2021.
The Authority oversees dam safety standards, regulates inspections, and implements policies framed by
the National Committee on Dam Safety (NCDS).
As mandated under the provisions of the Dam Safety Act, 2021, NDSA on the recommendations of
the NCDS has prepared and published 20 dam safety regulations through official Gazette notifications.
In addition, NDSA has played a pivotal role in standardizing guidelines, monitoring compliance with the
Act, and providing technical oversight and support to States. These efforts have significantly
strengthened the safety, surveillance, and maintenance of specified dams across the country.
(e) As part of the implementation of the Dam Safety Act, 2021, dam owners are preparing Emergency
Action Plans (EAPs) for their respective dams. Mock drills, conducted in coordination with State
Governments, District Authorities, and Disaster Management Agencies, are enhancing preparedness for
floods and extreme weather events. These exercises strengthen stakeholder coordination and improve
response mechanisms.
In addition to these efforts, NDSA has organized Community Awareness Programs at various dam
sites, involving State authorities, other stakeholders, and downstream communities. These programmes
aim to build awareness on dam safety, promote proactive risk mitigation, and strengthen resilience and
emergency preparedness.
*****