GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6179
TO BE ANSWERED ON 01.04.2026
DATA OF WAGON TURNAROUND TIME
6179. SHRI G KUMAR NAIK:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the data Wagon Turnaround Time (WTR) from 2014-15 to
2024-25 and the percentage of distance travelled empty by wagons
during the said period and the measures taken/being taken to reduce
empty running and improve asset utilisation, year-wise;
(b) the average speed of goods trains during each of the last decade along
with the distribution of trains across different speed ranges;
(c) the details of Capital Output Ratio (COR) from 2014-15 to 2024-25 along
with corresponding capital expenditure and traffic carried, year-wise
(d) the number of railway projects that have experienced cost overrun and
time overruns during the last decade along with the extent of such
overruns and reasons therefor;
(e) the details of the estimated financial impact of empty running and lower
speeds on freight earnings; and
(f) the steps taken/being taken by the Government to optimise route
planning, reduce congestion and enhance operational efficiency?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f) Indian Railway has taken several measures during the last few
years to enhance the freight loading and revenue. Freight loading since 2014
is as below:
Year Freight loading (in Million Tonnes)
2014-15 1,098
2015-16 1,104
Β§ Page 1 of 10Year Freight loading (in Million Tonnes)
2016-17 1,109
2017-18 1,162
2018-19 1,223
2019-20 1,210
2020-21 1,233
2021-22 1,418
2022-23 1,512
2023-24 1,591
2024-25 1,617
1,700
1,617
1,600
1,591
1,500
1,418 1,512
1,400
1,300
1,210
1,162
1,200
1,233
1,104 1,223
1,100
1,098 1,109
1,000
Because of these measures, the freight loading has increased from 1,233
MT in 2020-21 to 1,617 MT in 2024-25. During 2024-25, IR transported 1,617
MT thus becoming second largest freight carrying Railways in the world.
The measures taken include following:
β To increase the network capacity and improve wagon turn round, rail
network expansion has been taken up in a big way by construction of new
lines, multi tracking of existing lines, and gauge conversion of existing
lines. The details of new tracks laid during the 10 years are as under:
Page 2 of 10
51-4102 61-5102 71-6102 81-7102 91-8102 02-9102 12-0202 22-1202 32-2202 42-3202 52-4202
Freight loading (in Million Tonnes)Period New track commissioned
2009-14 7,599 Km
2014-25 34,428 Km
Further as on 01.04.25, there are 431 (154 New Line, 33 Gauge Conversion
and 244 Doubling) projects sanctioned. The summary of which is as under:-
Total Length
No. of Balance
Category Length completed till Cost (Cr.)
Projects length (Km)
(Km) Marβ25 (Km)
New lines 154 16,142 3,036 13,105 3,77,389
Gauge
33 4,180 2,997 1,183 43,820
conversion
Doubling /
Multi 244 15,644 6,736 8,909 2,53,711
tracking
Total 431 35,966 12,769 23,197 6,74,920
Some of the Projects recently completed are as follows:
Length
SN Name of project
(in Kms)
Udhampur- Srinagar- Baramulla new line 272
1
2 Bhairabi - Sairang New Line 51
3 Deoband - Roorkee New Line 27
4 Churu - Ratangarh Doubling 43
5 Tori-Shivpur 3rd Line 44
6 Araria - Galgalia New Line 110
7 Himmatnagar - Khedbrahma Guage Conversion 55
8 Bahraich- Nanpara -Nepalganj Guage Conversion 56
Domingarh- Gorakhpur -Kusumi 3rd Line & Gorakhpur -
9 21
Nakaha Doubling
Page 3 of 10Length
SN Name of project
(in Kms)
10 Vijapur - Ambaliyasan Guage Conversion 43
11 Pune- Miraj -Londa Doubling 467
12 Manmad - Jalgaon 3rd Line 160
13 Phephna βIndara- Mau -Shahganj Doubling 150
14 Adraj -Moti -Vijapur Guage Conversion 40
15 Katni -Bina 3rd Line 279
16 Gandhidham- Adipur Quadrupling 21
17 Khatuwas - Narnaul Doubling 24
18 Penukonda- Dharmavaram Doubling 42
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railwayβs website.
Some of the major projects sanctioned are as follows:
SN Project Name Cost
(βΉ in
Crore)
1 Chopan β Chunar doubling (102 Km) 1,553
2 Guntur β Bibinagar doubling (239 Km) 3,238
3 Mudkhed β Medchal & Mahbubnagar β Dhone doubling 5,655
(418 Km)
4 Samakhiali β Gandhidham Quadrupling (53 Km) 1,571
5 Merta City β Ras & Bypass at Merta Road new line (56 1,038
Km)
6 Lumding β Furkating doubling (140 Km) 2,334
7 Ajmer β Chanderiya doubling (178 Km) 1,813
8 Motumari β Vishnupuram with RoR doubling (100 Km) 1,746
9 Bikramshila β Katareah new line with new bridge on 2,549
river ganga (26 Km)
Page 4 of 10SN Project Name Cost
(βΉ in
Crore)
10 Gunupur β Therubali new line (74 Km) 1,326
11 Malkangiri β Pandurangapuram new line (174 Km) 4,109
12 Badampahar β Kendujhargarh new line (82 Km) 2,106
13 Junagarh β Nabarangpur new line (116 Km) 3,274
14 Buramara β Chakulia new line (60 Km) 1,639
15 Ajanta Caves Rail Connectivity (174 Km) 7,105
16 Bangriposi β Gorumahisani new line (86 Km) 2,549
17 Chandil β Anara β Damodar 3rd line (121 Km) 2,170
18 Bargarh Road β Nawapara Road new line (138 Km) 2,926
19 Sardega β Bhalumuda new double line (37 Km) 1,360
20 Varanasi β Pt. Deen Dayal Upadhyaya Multitracking 2,642
with rail cum road bridge on river ganga (15 Km)
21 Jalgaon β Manmad 4th line (160 Km) 2,773
22 Bhusawal β Khandwa 3rd & 4th line (131 Km) 3,514
23 Sambalpur β Jarapada 3rd & 4th line (127 Km) 3,916
24 Jharsuguda β Sason 3rd & 4th line (35 Km) 1,181
25 Gondia β Ballarshah doubling (240 Km) 4,819
26 Kharsia β Naya Raipur β Parmalkasa 5th & 6th line 8,741
(278 Km)
27 Wardha β Balharshah Quadrupling (135 Km) 2,381
28 Ballari β Chikjajur doubling (185 Km) 3,342
29 Koderma β Barkakana doubling (133 Km) 3,063
30 Itarsi β Nagpur 4th line (297 Km) 5,451
31 Dangoaposi β Jaroli 3rd & 4th line (43 Km) 1,752
32 Secunderabad β Wadi 3rd & 4th line (173 Km) 5,012
33 Furkating β New Tinsukia doubling (194 Km) 3,634
Page 5 of 10SN Project Name Cost
(βΉ in
Crore)
34 Bakhtiyarpur β Rajgir β Tilaiya doubling (104 Km) 2,192
35 Gondia β Dongargarh 4th line (84 Km) 2,223
36 Wardha β Bhusawal 3rd & 4th line (314 Km) 9,197
37 Hosapete β Bellary quadrupling (65 Km) 2,372
38 Kasara β Manmad 3rd & 4th line (131 Km) 10,154
39 Punarakh β Kiul 3rd & 4th line (50 Km) 2,668
40 Gamharia β Chandil 3rd & 4th line (55 Km) 1,168
41 Sainthia- Pakhur 4th Line (81 Km) 1,569
42 Santragachi- Kharagpur 4th line (111 Km) 2,905
43 Nergundi β Barang & Khurda Road β Vizianagaram 3rd 5,618
line (385 Km)
44 Son Nagar β Andal Multi tracking (375 Km) 13,606
45 Gorakhpur Cantt β Valmiki Nagar doubling (96 Km) 1,270
46 Jaipur β Sawai Madhopur doubling (131 Km) 1,269
47 Luni β Samdari β Bhildi doubling (272 Km) 3,531
48 Narkatiaganj β Raxaul β Sitamarhi β Darbhanga & 4,553
Sitamarhi β Muzaffarpur doubling (256 Km)
49 Prayagraj (Iradatganj) β Manikpur 3rd line (84 Km) 1,640
50 Tirupati β Pakala β Katpadi doubling (104 Km) 1,332
51 Ratlam β Nagda 3rd and 4th line (41 Km) 1,018
52 Aluabari Road β New Jalpaiguri 3rd & 4th line (57 Km) 1,786
53 Aurangabad (Chhatrapati Sambhajinagar) β Parbhani 2,179
(177 Km)
54 Bhagalpur β Dumka β Rampurhat doubling (177 Km) 3,169
55 Itarsi β Bina 4th line (237 Km) 4,329
56 Vadodara β Ratlam 3rd & 4th line (259 Km) 8,885
Page 6 of 10SN Project Name Cost
(βΉ in
Crore)
57 Devbhumi Dwarka (Okha) β Kanalus doubling (141 Km) 1,457
58 Badlapur β Karjat 3rd and 4th line (32 Km) 1,324
59 Delhi β Ambala Cantt 3rd & 4th line (194 Km) 5,983
60 Gondia β Jabalpur doubling (231 Km) 5,236
61 Manmad β Indore new line (360 Km) 18,529
62 Errupelam β Amaravati β Nambur new line (57 Km) 2,245
63 Vadhavan Port and New Palghar station new double 1,507
line (22 Km)
64 Deshalpar β Hajipir β Luna and Vayor β Lakhpat new 2,526
line (145 Km)
Completion of Railway project/s depends on various factors which include
the following:
ο Land acquisition
ο Forest clearance
ο Shifting of infringing utilities
ο Statutory clearances from various authorities
ο Geological and topographical conditions of area
ο Law and order situation in the area of project site
ο Number of working months in a year for particular project site etc.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
ο Substantial increase in allocation of funds.
ο Delegation of powers at field level.
ο Close monitoring of progress of project at various levels.
ο Regular follow up with State Governments and concerned authorities
for expeditious land acquisition, forestry and Wildlife clearances and
for resolving other issues pertaining to projects.
Page 7 of 10β Procurement of Wagons and Locomotives: To increase freight carrying
capacity, large numbers of IR wagons have been procured and
locomotives have been manufactured. During 2014 to 2025, about 2 lakh
wagons have been procured and more than 10,000 locomotives have
been added for increasing freight loading and mobility.
β Removing bottlenecks in operations by yard remodeling, construction of
bypass/chord lines, rail flyovers etc.
β The construction of Eastern Dedicated Freight Corridor (EDFC) from
Ludhiana to Sonnagar (1337 Km) and Western Dedicated Freight Corridor
(WDFC) from Jawaharlal Nehru Port Terminal (JNPT) to Dadri (1506 Km)
has been taken up. Out of total 2843 kms, 2741 route kms (96.4%) has
been commissioned and operational.
β Indian Railways has taken up electrification of Railway lines in a mission
mode. So far, about 99.4% of Broad Gauge (BG) network has been
electrified. A comparison of electrification before and after 2014 is as
follows:
Period Route Kilometre
Before 2014 21,801
2014-26 (upto Feb 26) 47,966
β Industry participation in investment in General Purpose Wagons, Special
Purpose/High- Capacity wagons and Automobile carrier wagons for
cement, oil, steel, fly-ash, automobile etc. By the FY 2024-25, around 240
rakes of special purpose wagons, 374 rakes of general-purpose wagons
and 48 rakes of automobile wagons have been inducted.
β Under the 'Gati Shakti Multi-Modal Cargo Terminal (GCT)' policy so far,
128 new GCTs have been commissioned, with an estimated traffic
capacity of 198 million tonnes per annum (MTPA). In addition, for
improvement of freight and parcel terminals from the financial year
2023-24 onwards, an amount of βΉ14,500 crore has been allocated.
Page 8 of 10β A βBulk Cement Terminal Policyβ for setting up terminals on Railway land
has been launched recently as part of Railway reforms for facilitating
Bulk Cement transportation.
β Ensuring increased availability of rakes/wagons against demand.
β Increasing the loadability for carrying additional traffic per wagon.
Length of freight trains has also been increased to increase throughput
per train.
β Use of Information Technology in freight operations to improve
monitoring and utilization of assets.
β Induction of higher horsepower locomotives.
β Improvement in maintenance practices of wagons and locomotives
resulting in increased availability of loco and rolling stock for traffic use.
β Improvement in track and signaling standards to carry higher volume of
traffic.
β Training of staff and officers to adopt the new technology and
management practices.
Further, Indian Railway has taken various steps to promote the
improvement of freight segment through freight rationalization, adoption of
various freight incentive schemes for transportation of bulk and small cargo
& various concession and services. Some of them are as under:
β Introduction of Gross Tonne Kilometer based haulage rate for Bulk
Cement in Tank Containers,
β Cargo Aggregator Transportation Product to promote Fast- Moving
Consumer Goods (FMCG), White Goods, Electronics, Automotive
Components, etc.,
β Liberalised Automatic Freight Rebate Scheme in Traditional Empty Flow
Directions,
β Concession on Short lead traffic,
β Discount in freight to Fly Ash /Bed Ash traffic booked in Open/flat Stock
& covered wagons,
Page 9 of 10β Rationalisation of Haulage rate of Automobile traffic,
β Promotion of Bamboo Traffic in North Eastern Region by granting
exemption from levy of Busy Season Charge (BSC).
β To enhance the capacity of the automobile stock, various new wagons
have been introduced such as ACT 1, ACT 2, ACT 3, NMGHS, etc.
β Discount on empty haulage of containers transporting Chemical Gypsum
and Tiles traffic,
β Classification of new commodities such as Potassium Sulphate,
Ammonium Bicarbonate Food Grade, RUF Pitch, Liquefied Isobutylene,
Liquefied Ethane, etc.
The freight train movement is continuously monitored through the Freight
Operations Information System (FOIS). To reduce empty runs and enhance
wagon productivity, following measures have been taken:
β Traditional Empty Flow Direction (TEFD) Policy: Providing freight
discounts (up to 15β20%) to customers for loading traffic in the empty
flow direction.
β Gati Shakti Cargo Terminals (GCT): Fast-tracking the development of
terminals to reduce detention times at loading/unloading points.
β Stationary Asset Optimization: Deployment of high-speed freight
locomotives and the commissioning of Dedicated Freight Corridors
(DFCs) to segregate freight and passenger traffic.
β Dynamic Pricing: Implementation of various incentive schemes for
"Round Trip" loading to encourage back-haul traffic.
*****