See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF TOURISM
RAJYA SABHA
UNSTARRED QUESTION NO.142#
ANSWERED ON 29.01.2026
DEVELOPMENT OF COASTAL CIRCUIT IN RAIGAD
142# SHRI DHAIRYASHIL MOHAN PATIL:
Will the Minister of TOURISM be pleased to state:
(a) whether Government has received any proposal for development of a coastal circuit in the
Raigad Parliamentary Constituency under the Swadesh Darshan scheme;
(b) if so, the details of financial assistance proposed or approved for the said project; and
(c) the funds allocated and released, so far, along with the timeline for completion of the said
project?
ANSWER
THE MINISTER OF TOURISM (SHRI GAJENDRA SINGH SHEKHAWAT)
(a) to (c): Development and promotion of tourism destinations and products is primarily
undertaken by the concerned State Government (SG) / Union Territory Administration (UTA).
However, Ministry of Tourism through its centre sector scheme of ‘Swadesh Darshan (SD), Swadesh
Darshan 2.0 (SD2.0)’, and ‘Challenge Based Destination Development (CBDD), a sub-scheme of
Swadesh Darshan 2.0 scheme complements the efforts of tourism infrastructure development in the
country by extending financial assistance to the SGs/UTAs on receipt of the project proposals from
the concerned State Government/Union Territory Administration in synergy with the scheme
guidelines, Government directions, availability of funds, inter-se priority etc.
While receipt of project proposals under Swadesh Darshan scheme is an ongoing process, the
scheme is presently approved till March, 2026. The details of the projects sanctioned under Swadesh
Darshan, SD2.0 and CBDD in the State of Maharashtra including its coastal region and funds
sanctioned and released / authorized for utilization under these projects is annexed.
*****ANNEXURE
STATEMENT IN REPLY TO PARTS (a) TO (c) OF RAJYA SABHA UNSTARRED QUESTION
NO.142# ANSWERED ON 29.01.2026 REGARDING DEVELOPMENT OF COASTAL CIRCUIT
IN RAIGAD RAISED BY SHRI DHAIRYASHIL MOHAN PATIL
Details of the projects sanctioned under Swadesh Darshan (SD), SD2.0, and CBDD schemes in the
state of Maharashtra:
(Amount in ₹ Crore)
Scheme S. Name of the Circuit/ Year of Amount Amount Status
/ Sub- No. Project/ Destination sanction sanctioned released / (Physically
scheme Experience authorized complete/
for Implementation
utilization Stage)
Swadesh 1 Development Coastal 2015-16 19.06 18.10 Physically
Darshan of Sindhudurg Circuit complete
(SD) Coastal
Circuit -
Sagareshwar,
Tarkarli,
Vijaydurg
(Beach &
Creek),
Mitbhav
2 Development Spiritual 2018-19 45.47 43.19 Physically
of Waki- Circuit complete
Adasa-
Dhapewada-
Paradsingha-
Telankhandi-
Girad
Swadesh 3 Shivshrusthi Pune 2024-25 76.22 7.62 Implementation
Darshan Theme Park Stage
2.0
CBDD 4 Development Ahmednagar 2024-25 25.00 2.50 Implementation
of Stage
Ahmednagar
Fort (under
Culture &
Heritage
Category)
*****