GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA
REJUVENATION
LOK SABHA
UNSTARRED QUESTION NO. 1948
ANSWERED ON 30.07.2026
DISTRIBUTION OF YAMUNA WATER BETWEEN RAJASTHAN AND HARYANA
†1948. Dr. MANNA LAL RAWAT:
Will the Minister of JAL SHAKTI be pleased to state:
(a) whether any new agreement or Memorandum of Understanding (MoU) has
recently been entered into between Rajasthan and Haryana regarding the
supply/distribution of Yamuna water and if so, the details thereof;
(b) the number of years for which the said water-sharing remained pending;
(c) the quantity of Yamuna water likely to be provided to Rajasthan under the
said agreement and the details of the cost of the project, financial
participation, implementing agency and the time by which the said agreement
is likely to be implemented;
(d) the name of districts of Rajasthan likely to be benefitted from the said
agreement and the details of drinking water supply, irrigation coverage,
beneficiary population and water allocation, district-wise;
(e) whether drinking water supply, irrigation, agriculture, industry and
employment in the water-stressed areas of Rajasthan is likely to be promoted
under the said agreement and if so, the details thereof; and
(f) the action taken by the Government so far for effective and time-bound
implementation of the said agreement?
1ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) & (b) The Memorandum of Understanding (MoU) for allocation of the
utilisable surface flow of the Yamuna River was signed among the co-basin
States in May, 1994. The Upper Yamuna River Board (UYRB) was constituted
by the Government of India on 11.03.1995 for implementation of the
provisions of the said MoU. The UYRB, in its 22nd meeting held on
21.12.2001, allocated 1917 cusecs (577 MCM) of Yamuna water at
Hathnikund Barrage to the State of Rajasthan during July–October.
An agreement has been signed between the Governments of Haryana and
Rajasthan on 29.06.2026 for the construction and implementation of the
Yamuna Water Project to facilitate transfer of Yamuna water to
Rajasthan through an underground pipeline system.
(c) to (f) As per information provided by the State Government of Rajasthan,
a Detailed Project Report (DPR) of the project has been prepared for transfer
of water through underground pipelines during July to October upto 577 MCM
for drinking water supply and other requirements for Churu, Sikar, Jhunjhunu
and other Districts of Rajasthan after utilization of full capacity (24,000
cusec) of Western Yamuna Canal by Haryana including Delhi share at
Hathnikund. The estimated cost of the project is Rs. 34102.24 Cr. As per the
agreement, the State of Rajasthan, as the primary beneficiary State, shall
bear the capital cost of the Project (including rehabilitation and
compensation costs). As per the DPR, a raw water reservoir at Hasiyawas in
Rajasthan with total storage capacity of about 386 MCM is earmarked
exclusively for drinking water supply. The DPR envisages time required for
construction of project as 72 months from the date of award.
*****
2