GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5389
TO BE ANSWERED ON 25.03.2026
DPR FOR THIRD RAILWAY LINE IN KERALA
5389. SHRI M K RAGHAVAN:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has completed the feasibility study and
Detailed Project Report (DPR) for the third line projects in Kerala and if
so, the details thereof;
(b) whether the Government has set timeline for completion of the third
railway line projects in Kerala and if so, the expected date of
completion; and
(c) whether the Government has planned to implement automatic signalling
system in the Shoranur–Mangalore section of Southern Railway and if
so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): To strengthen the railway network in Keralam, the following
surveys have been sanctioned for preparation of Detailed Project Report
(DPR):
S.N Project Status
1 Shoranur - Coimbatore 3rd & 4th Line Survey sanctioned for
(99 Km) preparation of DPR
2 Shoranur - Ernakulam 3rd Line S u r v e y sanctioned for
(107 Km) preparation of DPR
3 Mangaluru - Shoranur 3rd and 4th line Survey sanctioned for
(307 km) preparation of DPR
§ Page 1 of 74 Ernakulam - Kayankulam 3rd line (via Survey sanctioned for
Kottayam) (115 Km) preparation of DPR
5 Thiruvananthapuram - Nagercoil 3rd Survey sanctioned for
Line (71 Km) preparation of DPR
6 Kayankulam - Thiruvananthapuram 3rd Survey sanctioned for
Line (105 Km) preparation of DPR
7 Mararikulam - Alappuzha doubling D P R p r e p ared
(12 Km)
Capacity enhancement works such as Automatic Signalling or
multitracking works are taken up based on several factors such as
topography of the area, operational requirements, anticipated traffic etc.
Therefore to increase capacity of Shoranur–Mangaluru which is already a
double line section, Final Location Survey for 3rd and 4th line (307 km) has
been sanctioned for preparation of Detailed Project Report (DPR) as
detailed above.
After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines cannot be fixed.
Keralam :-
Keralam Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling
fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2025-26 ₹3,042 crore (more than 8 times)
Page 2 of 7Projects sanctioned:-
As on 01.04.2025, 06 projects (02 new line and 04 doubling) of 266 km
length, costing ₹9,415 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Balance to Expenditure
projects Length Commissioned complete upto March
2025
(₹in Crore)
146 309
New line 02 0 km 146 km
km
Doubling 120 2,941
04 26 km 94 km
/multitracking km
266 3,250
Total 06 26 km 240 km
km
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
Keralam are as under :
S. Cost
Project
N (₹ in Crores)
1 Dindigul - Pollachi - Palghat & Pollachi - Coimbatore
1,360
gauge conversion (217 km)
2 Quilon-Tirunelveli-Tiruchendur gauge conversion
1,122
(357 km)
3 Mulanturutti-Kuruppantara doubling (24 km) 303
4 Chenganur-Chingavanam doubling (27 km) 436
5 Ambalapuzha-Haripad doubling (18 km) 346
6 Kurruppanthara-Chingavanam doubling (27 km) 749
Page 3 of 7Ongoing Projects:-
Some of the projects falling fully/partly in Keralam which have been taken
up are as under:
Cost
S No. Project
(₹ in Crores)
1 Tirunnavaya –Guruvayur new line (35 Km) 138
2 Angamali-Sabarimala new line (111 km) 3,801
3 Ernakulam-Kumbalam doubling (8 km) 595
4 Kumbalam - Thuravur Patch doubling 8 0 3
(16 km)
5 Trivandrum- Kanyakumari doubling (87 km) 3,786
6 Shoranur - Vallathol doubling (10 km) 367
7 Palakkad Town to Parli Bypass Line 1 6 4
(2 Km)
8 Alappuzha-Ambalapuzha doubling (13 Km) 324
9 Turavur – Mararikulam doubling (21 Km) 451
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 476 ha
Land Acquired 65 ha (14%)
Balance Land to be acquired 411 ha (86%)
Railway had deposited ₹1,975 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:-
SN Name of the project Total Land Balance
land acquired Land to
required (in Ha) be
(in Ha) acquired
(in Ha)
1. Angamali - Sabarimala new line (111 416 24 392
km)
Page 4 of 72. Ernakulam – Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam – Turavur Patch doubling 10 9 1
(16 km)
4. Shoranur - Vallathol doubling (10 km) 5 0 5
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
Page 5 of 7All these factors affect the completion time and cost of the project/s.
ROBs/ RUBs:-
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
Railway. Such works are prioritised and taken up on the basis of its impact
on safety in train operations, mobility of trains & impact for road users and
feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014 - 25 (Upto 14,024 Nos. (including 121 Nos. in the
Jan’26) State of Keralam)
As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at cost of
₹ 1,14,196 Cr on Indian Railways including 138 Nos. Road Over Bridge
(ROB)/Road Under Bridge (RUB) are sanctioned at cost of ₹ 4,835 Cr in
Keralam which are at various stages of planning and execution.
106 Nos. ROBs/RUBs are delayed on account of the State Govt. The details
are as under:
S.No. Reason ROBs/RUBs (in No.)
1. Delay in Land Acquisition by State Govt. 38
2. Finalization of Alignment by State Govt. 63
3. Law & order/ Public Protest/Court cases etc. 2
4. Agency yet to be fixed 3
Page 6 of 7Completion of any ROB/RUB work depends on various factors like, fixing of
approach alignment, approval of General Arrangement Drawing (GAD), land
acquisition, removal of encroachment, shifting of infringing utilities,
statutory clearances from various authorities, law and order situation in
the area of project / work sites, number of working months in a year for
particular project / work sites due to climatic conditions etc. All these
factors affect the completion time of the projects / works.
Further, Railways have taken following measures to expedite the progress
of work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure drawings for various combinations
of span, skewness and width of road on Railway portion has been
done to avoid delays during the design approval. This has been issued
in the form of compendium, which can be directly adopted for Road
Over Bridge across Railway lines for expeditious planning.
*****
Page 7 of 7