Executive Summary & Key Takeaways

**Executive Summary** This document is an answer to an unstarred question raised in the Lok Sabha regarding railway development in the Dausa Lok Sabha Constituency. The question was answered on December 17, 2025. It addresses the establishment of electric loco sheds and washing pit lines, development of Bandikui Junction, and extension of the railway line to Mehandipur Balaji. **Key Points / Main Content** * **Electric Loco Sheds and Washing Pit Lines:** * Electric Loco Sheds are planned based on existing and anticipated future traffic requirements. * Washing Pit Line facilities are planned and executed as per operational and maintenance requirements. * Currently, pit line facilities are available at Jaipur, and works related to pit line facilities at Khatipura have been sanctioned. * **Amrit Bharat Station Scheme:** * Ministry of Railways has launched the Amrit Bharat Station Scheme for station redevelopment, involving master plans implemented in phases. * The scheme includes improvements to station access, integration with the city, station buildings, waiting halls, foot over bridges, lifts, platforms, kiosks for local products ('One Station One Product'), parking, amenities for Divyangjans, and passenger information systems. * Sustainable and environment-friendly solutions, ballastless tracks, and city center creation are also envisaged. * 1337 stations have been identified for development, including Bandikui, Dausa, Rajgarh, and Mandawar Mahwa Road stations in Rajasthan. * **Station Development Works in Rajasthan:** * Development works under the Amrit Bharat Station Scheme are underway at various stations. * Works have been completed at 11 stations: Barmer, Bundi, Deshnoke, Fatehpur Shekhawati, Gogameri, Govind Garh, Jaisalmer, Khairthal, Mandal Garh, Mandawar Mahwa Road, Rajgarh. * Specific works at Bandikui, Dausa, Bikaner, Gandhinagar Jaipur, and Jaipur Junction stations are in progress. * **General Development/Upgradation:** * Development/Upgradation of stations is a continuous process, prioritized based on category and fund availability. * Funding is generally under Plan Head-53 'Customer Amenities', managed zonally. * For the railway zones covering Rajasthan, ₹5,257 crore has been allocated for FY 2025-26, with expenditure of ₹2,829 crore incurred up to October 2025. * Development is complex, requiring statutory clearances and is affected by brownfield challenges. * **Connectivity to Mehandipur Balaji:** * Mehandipur Balaji is currently served by Bandikui Junction (10 km away). * The Dausa-Gangapur City New Line (93 km) has been commissioned at ₹950 crore in 2023-24. * Agra Fort – Bandikui Doubling (150 km) has been sanctioned at ₹988 crore, with land acquisition underway. **Impact Analysis** **Stakeholder:** Railway Passengers and the Public **Impact:** Improved railway infrastructure, enhanced station amenities, and better connectivity in the region, including access to Mehandipur Balaji. **Action Required:** No direct action required; benefit from the infrastructure improvements. **Stakeholder:** Indian Railways **Impact:** Increased operational capacity, improved maintenance facilities, enhanced passenger services, and station modernization. **Action Required:** Continue planning, funding, and executing development works under the Amrit Bharat Station Scheme and other relevant plans. **Stakeholder:** Dausa Lok Sabha Constituency **Impact:** Development of railway infrastructure, increased employment opportunities (implied), and improved connectivity. **Action Required:** N/A

Key Entities Referenced

Amrit Bharat Station Scheme: A scheme launched by the Ministry of Railways for the redevelopment of railway stations with a long-term approach. Ministry of Railways: The primary ministry responsible for establishing railway infrastructure and initiatives discussed in the document. Bandikui Junction: A railway station in Rajasthan, India, the development of which is the focus of the initial question in the document. Rajasthan: The state in India where the mentioned railway station development projects are located. Dausa Lok Sabha Constituency: The parliamentary constituency encompassing Bandikui where improvements and development projects are being considered.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION No. 2836 TO BE ANSWERED ON 17.12.2025 ELECTRIC LOCO SHED AND WASHING PIT LINE FOR BANDIKUI RAILWAY JUNCTION † 2836. SHRI MURARI LAL MEENA: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government proposes to establish an electric loco shed and Washing Pit Line at Bandikui Junction Railway Station in Dausa Lok Sabha Constituency which will not only increase the operational capacity of the Railways but also significantly increase employment opportunities at the local level and if so, the details thereof; (b) whether the Government is working on a Detailed Project Report (DPR), budget allocation, phased development plan to develop Bandikui Junction as developed station and if so, the present status thereof; and (c) whether any survey, pre-feasibility study/approval/ proposal are under consideration for extension of railway line up to Mehandipur Balaji in view of the increasing passenger load in the Bandikui-Dausa-Mehandipur Balaji sector and if so, the details thereof and the probable timeline? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (c) Electric Loco Sheds are planned based on existing and anticipated future traffic requirements of Indian Railways. Washing Pit Line facilities are planned and executed as per operational and maintenance requirement. Atpresent, Pit line facilities are available at Jaipur. Further, works related to Pit line facilities at Khatipura have been sanctioned and work has been taken up. These facilities are sufficient to fulfil the present and future requirements of the region. Ministry of Railways has launched Amrit Bharat Station Scheme for redevelopment of stations with a long-term approach. The scheme involves preparation of master plans and their implementation in phases to improve the stations. The master planning includes:  Improvement of access to station and circulating areas  Integration of station with both sides of city  Improvement of station building  Improvement of waiting halls, toilets, sitting arrangement, water booths  Provision of wider foot over bridge/air concourse commensurate with passenger traffic  Provision of lift/escalators/ramp  Improvement /Provision of platform surface and cover over platforms  Provision of kiosks for local products through schemes like 'One Station One Product'  Parking areas, Multimodal integration  Amenities for Divyangjans  Better passenger information systems  Provision of executive lounges, nominated spaces for business meetings, landscaping, etc. keeping in view the necessity at each station. The scheme also envisages sustainable and environment friendly solutions, provision of ballastless tracks etc. as per necessity, phasing and feasibility and creation of city centre at the station in the long term.So far, 1337 stations have been identified for development under Amrit Bharat Station Scheme, out of which 85 stations including Bandikui, Dausa, Rajgarh, Mandawar Mahwa Road stations of Dausa Lok Sabha Constituency, are located in Rajasthan. The names of stations identified for development under Amrit Bharat Station Scheme in Rajasthan are as following: State No. of Names of Amrit Stations Amrit Stations Rajasthan 85 Abu Road, Ajmer, Alwar, Anupgarh, Asalpur Jobner, Balotra, Bandikui, Baran, Barmer, Bayana, Beawar, Bharatpur, Bhawani Mandi, Bhilwara, Bijainagar, Bikaner, Bundi, Chanderiya, Chhabra Gugor, Chittorgarh Jn , Churu, Dakaniya Talav, Dausa, Deeg, Degana, Deshnoke, Dholpur, Didwana, Dungarpur, Falna, Fatehnagar, Fatehpur Shekhawati, Gandhinagar, Jaipur, Gangapur City, Gogameri, Gotan, Govind Garh, Hanumangarh, Hindaun City, Jaipur Jn, Jaisalmer, Jalor, Jawai Bandh, Jhalawar City, Jhunjhunu, Jodhpur, Kapasan, Khairthal, Kherli, Kota Jn, Lalgarh Jn, Mandal Garh, Mandawar Mahwa Road, Matwar, Bhinmal, Marwar Jn, Mavli Jn, Merta Road Jn, Nagaur, Naraina, Nim ka Thana, Nokha, Pali Marwar, Phalodi Jn, Phulera Jn, Pindwara, Rai Singh nagar, Rajgarh, Ramdevra, Ramganj Mandi Jn, Ranapratapnagar, Rani, Ratangarh Jn, Ren, Ringas, Sadulpur, Sanganer, Sawai Madhopur, Shri Mahaveerji, Sikar, Sojat Road, Somesar, Sri ganganagar, Sujangarh, Suratgarh, Udaipur CityDevelopment works at railway stations under Amrit Bharat Station Scheme in Rajasthan have been taken up at a good pace. Till now, works of 11 stations (Barmer, Bundi, Deshnoke, Fatehpur Shekhawati, Gogameri, Govind Garh, Jaisalmer, Khairthal, Mandal Garh, Mandawar Mahwa Road, Rajgarh) in Rajasthan have been completed. The works at other stations have also been taken up at good pace and progress of some of the above stations is as given below:  Bandikui station: The works of station building, platform shelter, improvement of platform surface, circulating area, waiting hall, toilet and 12 m Foot Over Bridge have been taken up.  Dausa station: The works of improvement of station building, waiting hall, toilet, platform shelter, circulating area, Divyangjan facilities and 12 m Foot Over Bridge have been completed. The work of lift has been taken up.  Bikaner station: The work of refurbishment of MFC building except telecom side has been completed. The foundation work of North side station building have been taken up.  Gandhinagar Jaipur station: The structural works of main and second entry station building, works of launching of air concourse and casting of deck slab have been completed. The finishing works of main and second entry station building, works of platform shelter and platform resurfacing have been taken up.  Jaipur Junction station: The structural works of second entry station building and basement, foundation work of air concourse and launching of Foot Over Bridge at Dausa end from platform 1 to platform 4&5 have been completed. The works of front station building and basement, finishing works of second entry station building and basement, fabrication, launching of air concourse and Foot Over Bridge at Sikar end have been taken up. Udaipur City station: The structural work of East and West side station building including basement has been completed. The finishing works of East and West side station building including basement have been taken up. Further, development / redevelopment / upgradation / modernisation of stations on Indian Railways is a continuous and ongoing process and works in this regard are undertaken as per requirement, subject to inter-se priority and availability of funds. The priority for development / redevelopment / upgradation / modernisation of stations is accorded to higher category of station over lower category of station while sanctioning and executing the works. Development / upgradation / modernisation of stations including under Amrit Bharat Station Scheme is generally funded under Plan Head-53 'Customer Amenities'. The details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway-wise and not work-wise, or station-wise or state- wise. Rajasthan is covered under the jurisdiction of five railway zones, namely, Northern Railway, North Central Railway, North Western Railway, Western Railway and West Central Railway. For these zones, allocation of ₹ 5,257 crore has been made for the financial year 2025-26 under Plan Head- 53 and expenditure of ₹ 2,829 crore (up to October, 2025) has been incurred so far. Development / Upgradation of railway stations is complex in nature involving safety of passengers & trains and requires various statutory clearances such as fire clearance, heritage, tree cutting, airport clearance etc. The progress also gets affected due to brownfield related challenges such as shifting of utilities (involving water/sewage lines, optical fibre cables, gas pipe lines, power/signal cables, etc.), infringements, operation of trains without hindering passenger movement, speed restrictions due to works carried outin close proximity of tracks and high voltage power lines, etc. and these factors affect the completion time. Mehandipur Balaji is presently served by Bandikui Junction, which is located at 10 Km distance from Mehandipur Balaji. Dausa-Gangapur City New Line (93 Km) at a cost of ₹ 950 crore has been commissioned in 2023-24. To further improve connectivity in the region, Agra Fort – Bandikui Doubling (150 Km) at a cost of ₹ 988 crore has been sanctioned. Land acquisition has been taken up. *****