GOVERNMENT OF INDIA
MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE
LOK SABHA
UNSTARRED QUESTION NO. 3841
TO BE ANSWERED ON 16.03.2026
Environmental Clearance to Shree Cement Limited
3841. SHRI VIJAY BAGHEL:
Will the Minister of ENVIRONMENT, FOREST AND CLIMATE CHANGE be pleased to
state:
(a) whether the Government has received any complaint regarding corruption in providing
Environment Clearance to Shree Cement Limited, Khapradih, Tehsil Suhela, district
Balodabazar (Chhattisgarh);
(b) whether any action has been taken by the Government on said complaint and if so, the details
thereof;
(c) whether any action is required to be taken at the State level in Chhattisgarh in this regard, if
so, the details thereof;
(d) whether there is any discrepancy in the presentation of facts relating to the said complaint in
Lok Sabha and the Chhattisgarh Legislative Assembly, if so, the details thereof; and
(e) whether the Government has directed the Integrated Regional Office, Raipur, Chhattisgarh
to conduct an inquiry in this matter and if so, the details thereof
ANSWER
MINISTER OF STATE IN THE MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE
CHANGE
(SHRI KIRTI VARDHAN SINGH)
(a)to(e) The Ministry of Environment, Forest and Climate Change (MoEFCC), including its
Sub-Office Raipur, had received complaints regarding the cement plant of M/s Shree
Raipur Cement Plant (a unit of M/s Shree Cement Limited) located near Village
Khapradih, Tehsil Simga, District Balodabazar – Bhatapara, Chhattisgarh alleging
irregularities in the grant of Environment Clearance (EC) and non-compliance of its
conditions. The complaints were sent to the MoEFCC Sub-Office, Raipur (SO Raipur)
for examination and submission of report. The SO Raipur had examined the
complaints, and submitted a Certified Compliance Report (CCR) and a Factual Status
Report vide letters dated 10-09-2025 and 11-09-2025, respectively. The CCR was
examined in the MoEFCC and steps were taken as per the Standard Operating
Procedure (SoP) issued by the Ministry vide Office Memorandum dated 25-11-2022
for post-environmental clearance monitoring and to ensure compliance with the
stipulated conditions. As per the Compliance Status Report submitted by Project
Proponent and the final Review Report by SO Raipur, no major violation of
Environment (Protection) Act, 1986 has been observed, prima facie for the cementplant operations. Further, the Chhattisgarh Environment Conservation Board (CECB)
has informed that in a leakage incident, an environment compensation of ₹4,00,000/-
vide letter dated 27.02.2025 and ₹10,20,000/- vide letter dated 28-03-2025 was
imposed on the cement plant for violation of the provisions of Hazardous and Other
Wastes (Management and Transboundary Movement) Rules, 2016 and Air
(Prevention and Control of Pollution) Act, 1981.
The MoEFCC had earlier presented the facts related to the cement plant before Lok
Sabha in a reply to Unstarred Question No. 3939 titled ‘Environmental Clearance to
Shree Cement Ltd.’ on 18-08-2025 based on the information available. The CECB has
informed that no question has been received related to the said complaint in
Chhattisgarh Legislative Assembly till 31-01-2026, hence; there is no discrepancy in
presentation of facts.
*****Accordingly, Ministry vide letter dated 10-10-2025 sought an Action Taken Report from the
Project Proponent (PP). Further, vide letter dated 03-12-2025, MoEFCC sought a
Review Report from the SO Raipur. The Review Report was submitted vide letter
dated 05-12-2025 by SO Raipur. The PP submitted an updated compliance Report
vide email dated 09-01-2026 in response to the Review Report submitted by the SO
Raipur. As per the Review Report, no non-compliance has been reported.