GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 1378
ANSWERED ON –11/02/2026
GANGA EXPRESSWAY AND ACCESS-CONTROLLED CORRIDORS
1378 SMT. KIRAN CHOUDHRY:
SMT. SANGEETA YADAV:
SHRI SHAMBHU SHARAN PATEL:
SHRI KESRIDEVSINH JHALA:
SMT. REKHA SHARMA:
SHRI MITHLESH KUMAR:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) the current construction and commissioning status of the Ganga Expressway and other
access-controlled expressways;
(b) what safety audits and crash barrier standards have been enforced before opening these
corridors;
(c) how maintenance responsibilities are being monitored during the defect-liability period;
and
(d) whether any penalties have been imposed on concessionaires for delays or quality
deviations and if so, the details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (d) The Government in Ministry of Road Transport & Highways is primarily
responsible for development and maintenance of National Highways (NHs) in the
country. As far as Ganga expressway is concerned, the project has been undertaken by the
State Government of Uttar Pradesh.
Project-wise details of completed and commissioned expressway on NHs is at
Annexure-I and commissioning status of ongoing access-controlled expressway projects on
NHs is at Annexure-II. Delay in construction of these expressway has been mostly caused
due to utility shifting, land acquisition delay, Change of Scope (COS) works due to Force
Majeure conditions, General arrangement Drawings (GAD) clearance for Road Over Bridge
(ROB), issue of non-reimbursement of transportation cost of pond ash by Thermal Power
Plants in some States in accordance with the notification dated 25.01.2016 of the
Government in Ministry of Environment, Forest and Climate change, non availability of
earth for highway construction in some States due to onerous conditions, etc.Works on NHs are carried out as per standards, guidelines, manual, code of practice
of Indian Roads Congress as well as specifications for Road and Bridge Works. Necessary
road safety measures inter-alia include provision of service roads, median openings, merging
and diverging facilities, crash barriers, signage boards, foot over bridges, etc. are part of the
works. Further, Road Safety Audit is carried out for the independent assessment of newly
constructed Expressway before opening them to commercial traffic. All identified road safety
issues, including those related to crash barriers, road signage and markings, are addressed
before the road is opened to the public.
Compliance to the maintenance requirements is ensured through regular field visits and
inspections by the Authority Engineer (AE) / Independent Engineer (IE) and Authority
officers. Repair of identified defects / issues in the road condition during defect liability
period are rectified by the Contractor / Concessionaire within the stipulated timelines as per
provisions of the Contract Agreement and its Schedules.
Actions against defaulting agencies are taken as per the provisions of the Contract/
Concession agreement in case of any defaults. In addition to termination/debarment/
blacklisting of defaulting agencies, penalties/ liquidated damages are also levied on
Contractor for damages/ sub-standard work.
Penalty amounting to Rs 42.76 crore have been imposed on Contractors/
Concessionaires for delay/ deviation from stipulated quality control standards for access
controlled Expressway projects taken up by the Government.ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (d) OF RAJYA SABHA
UNSTARRED QUESTION NO. 1378 FOR ANSWER ON 11.02.2026 ASKED BY SMT.
KIRAN CHOUDHRY, SMT. SANGEETA YADAV, SHRI SHAMBHU SHARAN PATEL,
SHRI KESRIDEVSINH JHALA, SMT. REKHA SHARMA, SHRI MITHLESH KUMAR
REGARDING " GANGA EXPRESSWAY AND ACCESS-CONTROLLED CORRIDORS "
Details of completed and commissioned National Expressway works
Sl Name of Expressway Length Actual date of
No in Km commissioning
1 DME, Pkg.-I: Delhi-Meerut Expressway from Km. 0.00 to 8.716 28.06.2018
Km. 8.716 (Nizamuddin to U.P. Gate) in Delhi on Hybrid
Annuity Mode
2 DME, Pkg.-II: Delhi-Meerut Expressway from Km. 8.716 19.284 31.03.2021
to Km. 28.000 (U.P. Border to Dasna) in UP on Hybrid
Annuity Mode
3 DME, Pkg.-IV: Greenfield Delhi-Meerut Expressway from 31.777 31.03.2021
Dasna to Meerut (Km. 27.740 to Km 59.777) in UP on EPC
Mode
4 EPE, Pkg.-I: 6-lane of Eastern Peripheral Expressway from 21 26.05.2018
km 1.000 to km 22.00 in the States of Haryana and Uttar
Pradesh
5 EPE, Pkg.-II: 6-lane of Eastern Peripheral Expressway 24.5 26.05.2018
from km 22.000 to km 46.500 in the States of Haryana and
Uttar Pradesh
6 EPE, Pkg.-III: 6-lane of Eastern Peripheral Expressway 24.5 26.05.2018
from km 46.500 to km 71.00 in the State of Uttar Pradesh
7 EPE, Pkg.-IV: 6-lane of Eastern Peripheral Expressway 22 26.05.2018
from Km 71.000 to Km 93.000 in the state of Uttar Pradesh
8 EPE, Pkg.-V: 6-lane of Eastern Peripheral Expressway 21 26.05.2018
from Km 93.000 to Km 114.000 in the States of Haryana
and UP.
9 EPE, Pkg.-VI: 6-lane of Eastern Peripheral Expressway 22 26.05.2018
from Km 114.000 to Km 136.000 in the State of Haryana.10 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-18+461 10-02-2023
01) (Ch. 0+000 to Ch. 18+461) [Sohna-Gurugram Road
(NH-248A) near Alipur Village and ending before KMP
Expressway]
11 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-28+500 10-02-2023
02) (Ch. 18+500 to Ch. 47+000)[Expressway starting
before KMP Expressway and ending at Ch. 47+000 near
Khanpur Ghati]
12 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-31+800 10-02-2023
03) (Ch. 47+000 to Ch. 78+800) [starting near Khanpur
Ghati and ending at HR/RJ Border]
13 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-36+900 26-06-2022
04) (Ch. 78+800 to Ch. 115+700) [HR/Rajasthan Border to
Junction with SH-44]
14 Delhi-Vadodara Greenfield Alignment (NH-148N) (Pkg-36+140 28-06-2022
05) (Ch.115+700 to Ch. 151+840) [Junction atSH-44 to
Junction Keshopura road]
15 Delhi Vadodara Expressway Section of NE-4 Package-29 22.50 16.05.2023
16 Delhi Vadodara Expressway Section of NE-4 Package-30 21.50 09.01.2026
17 Vadodara Mumbai Expressway Section of NE-4 Package I 23.74 03.08.2022
18 Vadodara Mumbai Expressway Section of NE-4 Package II 32.00 09.01.2024
19 Vadodara Mumbai Expressway Section of NE-4 Package 31.00 10.01.2024
III
20 Vadodara Mumbai Expressway Section of NE-4 Package 13.00 02-04-2024
IV
21 Ahmedabad - Dholera (Pkg III) from km. 48.52 to km. 22.54 28.10.2025
71.06) [Vejallka Village - Start of DSIR zone]
22 Ahmedabad - Dholera (Pkg IV) from km. 71.06 to km. 37.96 10.06.2025
109.019) [Start of DSIR zone - Adhelai Village]
23 Four Laning of Ahmedabad-Vadodara Expressway from 93.30 01.10.2004
km.0.000 to km 93.302
24 Delhi-Mumbai Expressway-MP Portion (NE-4) 244.5 20.09.202325 Delhi Amritsar Katra Package-3 30.6 21-05-2024
26 Delhi Amritsar Katra Package-4 28.85 25-09-2024
27 Delhi-Vadodara 8-lane carriageway starting at Junction 31.16 10.03.2022
with Keshopura Road to Junction with NH-11 (km 151+84
to 183+0) Green Filed Alignment under BM, NE-4
(Package-6)
28 Delhi-Vadodara 8-lane carriageway starting near Junction 31.26 30.06.2022
with NH-11 to start of ROB near junction with NH-11A
(km 183 to 214.26) NE-4 (Package-7)
29 Delhi-Vadodara 8-lane carriageway (km 214.26 to 247.31) 33.05 06.02.2023
Green Filed Alignment under BM, NE-4 (Package-8)
30 Delhi-Vadodara 8-lane carriageway (km 247.31 to 292.95) 45.64 31.12.2023
Green Filed Alignment under BM, NE-4 (Package-9)
31 Delhi - Vadodara [starting from Hardeoganj Village near 11.63 30.11.2023
Indergarh to Major Bridge on Maj River (Ch. 319.40 to
331.030), NE-4 (Package-11]
32 Delhi - Vadodara [starting near Major Bridge on Mej 28.14 21.05.2024
River - Junction on SH-37A (Ch. 331.030 to 359.170), NE-
4 (Package-12]
33 Delhi - Vadodara [Junction with SH-37A to Junction with 29.25 28.07.2024
NH- 76 (km. 359.170 to 388.42), NE-4 (Package-13]
34 Delhi - Vadodara [Junction with NH- 76 to Junction with 30.58 31.12.2024
NH-12 near village Ummedpura] (Ch 388.42 to Ch. 419),
NE-4 (Package-14]
35 Delhi-Vadodara [Start of Bridge near Manoharpur to 25.125 30.12.2023
Rajasthan/MP Border (km. 427.3 to 452.425), NE-4
(Package-16]
36 4-lane Green Field Expressway Spur from Delhi-66.916 01.06.2025
Vadodara Greenfield expressway near Bandikui to
Jaipur in Bharatmala Pariyojana Ph-I in Rajasthan (HAM)
NE-4CANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (d) OF RAJYA SABHA
UNSTARRED QUESTION NO. 1378 FOR ANSWER ON 11.02.2026 ASKED BY SMT.
KIRAN CHOUDHRY, SMT. SANGEETA YADAV, SHRI SHAMBHU SHARAN PATEL,
SHRI KESRIDEVSINH JHALA, SMT. REKHA SHARMA, SHRI MITHLESH KUMAR
REGARDING " GANGA EXPRESSWAY AND ACCESS-CONTROLLED CORRIDORS "
Commissioning status of ongoing expressway works
Physical Original
Sl Length Actual/ Likely date of
Expressway progress Target date of
No in Km commissioning
in % commissioning
6L Elevated Kanpur - Lucknow
1 (Expressway) Pkg-1 from Km. 17.52 93.55 30.07.2025 31.03.2026
10+980 to Km. 28+500
6L Greenfield Kanpur - Lucknow
2 (Expressway) Pkg II from km. 45.244 99.77 08.05.2025 28.02.2026
28.500 to km. 73.744
Construction of 6-lane Greenfield
Varanasi-Ranchi-Kolkata
Expressway (Pkg-1) from
junction with NH-19 & Varanasi
3 27 26.72% 24.11.2026 19.05.2027
Ring Road near Rewasa village to
Junction with Chandauli-
Chainpur road near Khianti
village
Delhi-Amritsar-Katra Expressway
4 44.6 80.70% 25.09.2024 31.05.2026
Pkg-14
Delhi-Amritsar-Katra Expressway
5 35.15 88.50% 25.09.2024 31.07.2026
Pkg-15
Delhi-Amritsar-Katra Expressway
6 20.385 92% 26.09.2024 20.06.2026
Pkg-16
Delhi-Amritsar-Katra Expressway
7 26.8 53.90% 13.06.2025 15.09.2026
Pkg-17
Delhi-Amritsar-Katra Expressway
8 15.3 51.82% 19.11.2025 26.08.2026
Pkg-18
Delhi Vadodara Expressway
9 32.83 72% 31.08.2024 31.03.2026
Section of NE-4 Package-26
Delhi Vadodara Expressway
10 26.35 94% 14.02.2024 28.02.2026
Section of NE-4 Package-27Delhi Vadodara Expressway
11 25.23 96% 15.11.2023 31.03.2026
Section of NE-4 Package-28
Delhi Vadodara Expressway
12 19.46 95% 18.05.2023 28.02.2026
Section of NE-4 Package-31
Vadodara Mumbai Expressway
13 24.57 95.00% 31-10-2021 31-03-2026
Section of NE-4 Package V
Vadodara Mumbai Expressway
14 36.93 98.90% 11-12-2023 30-11-2024
Section of NE-4 Package VI
Vadodara Mumbai Expressway
15 27.50 97.05% 09-11-2023 31-12-2024
Section of NE-4 Package VII
Vadodara Mumbai Expressway
16 35.40 4.85% 02-03-2026 Contract terminated
Section of NE-4 Package VIII
Vadodara Mumbai Expressway
17 26.60 21.75% 13-10-2025 30-06-2026
Section of NE-4 Package IX
Vadodara Mumbai Expressway
18 24.60 36.25% 21-03-2024 15-11-2026
Section of NE-4 Package X
Ahmedabad - Dholera (Pkg I)
from km. 0.00 to km. 22.00)
19 22.00 99.8 11.01.2024 31.01.2026
[Sardar Patel Ring Road -
Sindhrej Village]
Ahmedabad - Dholera (Pkg II)
from km. 22.00 to km. 48.52)
20 26.52 99.58 21.01.2024 15.02.2026
[Sindhrej Village - Vejallka
Village]
Bangalore-Chennai Expressway
21 27.1 98.99 15.05.2024 04.09.2025
Phase I, Package-I of NE-7
Bangalore-Chennai Expressway-
22 27.1 99.8 16.05.2024 04.09.2025
Phase I, Package-II of NE-7
Bangalore-Chennai Expressway-
23 17.5 99.97 31.05.2024 04.09.2025
Phase I, Package-III of NE-7
4 lane Bangalore to Chennai
24 Expressway (Gudipala to 24.0 94% 28.05.2024 28.02.2026
Walajahpet) section of NE-7 (P-1)4 lane Bangalore - Chennai
25 Expressway (Walajahpet - 24.5 93% 14.07.2024 30.04.2026
Arakonam) section of NE-7 (P-2)
4 Lane Bangalore Chennai
Work stopped due to
Expressway (Arakonam to
26 25.5 54% 29.07.2024 financial constraints of
Kancheepuram) section of NE-7 -
Concessionaire.
(P-3)
4 Bangalore – Chennai
Expressway (Kanchepuram to
27 31.7 84% 09.07.2024 31.07.2026
Sriperumbudur) section of NE-7
(P-4)
Ujjain-Garoth Partial Expressway
28 136.5 99% 31.12.2023 06.09.2025
(NH-752D)
Bangalore Chennai Expressway
PCC has been issued w.e.f
from km.71.000 to Km 96.000
29.12.2025. However,
29 (Bethamangala in the state of 25 98.45 09.10.2024
this corridor is not yet
Karnataka to Byreddypalli)
opened to traffic.
(Phase-II Pkg-I)
Bangalore Chennai Expressway
from km 96.000 To 127.000
30 31 82.75 07.06.2025 17.06.2026
(Byreddypalli to Bangarupalem)
(Phase-II Pkg-II)
Bangalore Chennai Expressway PCC has been issued w.e.f
from km.127.000 to Km 156.000 07.08.2025. However,
31 29 99.46 03.10.2024
(Bangarupalem to Gudipala this corridor is not yet
section) (Phase-II Pkg-III) opened to traffic.
32 Delhi Amritsar Katra Package-1 34 99.91 26.12.2023 04.11.2025
33 Delhi Amritsar Katra Package-2 26.8 99.89 13.01.2024 25.12.2024
34 Delhi Amritsar Katra Package-5 37.67 99.2 22-05-2024 28.02.2026
Delhi Amritsar Katra Package-6 30.91 95.35% 21.05.2024 Project completed on
35 09.05.2024. Traffic not
commissioned yet
Delhi Amritsar Katra Package-7 36.94 95.33% 09.07.2024 25.03.2026
36
Delhi Amritsar Katra Package-8 35.09 31.08% 13.03.2025 Project is under
37
Foreclosure/Termination
38 Delhi Amritsar Katra Package-9 43.04 70.60% 16.07.2024 30.06.2026
Delhi Amritsar Katra Package-10 39.5 62.99% 09.07.2024 Project is under
39
Foreclosure/Termination
Delhi Amritsar Katra Package-11 43.02 43.45% 14.11.2024 Project is under
40
Foreclosure/Termination41 Delhi Amritsar Katra Package-12 35.28 25.77% 20.02.2027 20.02.2027
Delhi Amritsar Katra (Amritsar 16.9 28.64 16.04.2026 31.03.2028
42
Connectivity) Spur-1
Delhi Amritsar Katra (Amritsar 30.5
43 Connectivity) Spur-2 Contract terminated
Delhi Amritsar Katra (Amritsar 28.07 29.7 26.10.2024 30.11.2026
44
Connectivity) Spur-3
Delhi - Vadodara [End of
Interchange on NH-166 near
45 village Mui to Hardeoganj village 26.45 94.62% 21.05.2023 31.03.2026
near Indergarh (Ch 292.95 to
319.40), NE-4 (Package-10]
Delhi - Vadodara [Junction with
NH-12 to Start of Bridge near
46 8.3 90.03% 04.01.2024 31.03.2026
Manoharpura] (Ch 419.00 to
427.30), NE-4 (Package-15]
Construction of 8-lane access
controlled Expressway from km.
47 77 to 103.400 (Ganjad to Talasari 26.40 99.85 17-05-2024 28.02.2026
section of VME), Pkg-XI on
HAM basis.
Construction 8-lane access
controlled Expressway from km.
48 50.700 to 77 (Masvan to Ganjad 26.30 97.91 22-03-2024 28.02.2026
section of VME), Pkg-XII on
HAM basis.
Construction 8-lane access
controlled Expressway from km.
26.582 to 50.70 of Main
49 Expressway and km.0 to 3 of 27.18 91.20 08-02-2024 31.03.2026
SPUR (Shirsad to Masvan section
of VME), Pkg-XIII on HAM
basis.
Construction 8-lane access
controlled Expressway from km.
50 3.000 to 20.200 (Shirsad to Akloli 17.20 90.06 11-05-2024 28.02.2026
section –SPUR of VME), Pkg-
XIV on HAM basis.
Construction 8-lane access
controlled Expressway from km.
51 20.200 to 38.200 (Akloli to Amne 18.00 90.05 11-05-2024 28.02.2026
section –SPUR of VME), Pkg-
XV on HAM basis.Construction 8-lane access
controlled Expressway from km.
52 38.200 to 45.200 (Borivali to 7.00 88.00 31.03.2024 31.03.2026
sange Secton - SPUR of VME),
Pkg-XVA on HAM basis.
Construction of 8-lane access
controlled Expressway from km.
53 45.200 to 69.800 (Amne to Bhoj 24.60 92.70 31-10-2024 31.03.2026
section - SPUR of VME) basis,
Pkg-XVI on HAM basis.
Construction 8-lane access
controlled Expressway from Km
54 69.700 to Km 79.783(Bhoj to 9.98 84.25 17-07-2025
31.03.2026
Morbe -Spur) Section of VME,
Pkg-XVII on HAM basis.
Surat-Nashik-Ahmednagar-
55 Solapur-MH/KTN Border 36.40 36.44 02.10.2026 02.10.2026
(Greenfield stretch Package-XIV)
*****