GOVERNMENT OF INDIA
MINISTRY OF CIVIL AVIATION
LOK SABHA
UNSTARRED QUESTION NO. : 851
( TO BE ANSWERED ON THE 23rd July 2026 )
GREENFIELD AIRPORT IN DHANBAD
851. SHRI DULU MAHATO
Will the Minister of CIVIL AVIATION
be pleased to state:-
(a) whether the Government has completed any official technical feasibility
study for Dhanbad Airport, if so, the details thereof and if not, the reasons
therefor;
(b) the reasons for not convening a joint stakeholders' meeting so far despite
repeated representations from public representatives and whether the
Government proposes to prescribe any timeline in this regard and if so, the
details thereof;
(c) whether the Government admits that the lack of air connectivity since 1987
in this region is the result of administrative inaction affecting industrial
development and pilgrims visiting ‘Shri Sammed Shikharji’ and if so, the details
thereof;
(d) the details of the action taken so far on the letters sent to the State
Government and the alternative strategy of the Ministry for desired progress in
this regard; and
(e) the clear roadmap for the project and the time by which it is likely to be
completed?
ANSWER
Minister of State in the Ministry of CIVIL AVIATION
(Shri Murlidhar Mohol)
(a) to (e): As per Greenfield Airports (GFA) Policy, 2008, if any Airport
developer including the State Government desires to develop a Greenfield
airport, they are required to identify a suitable site and get the Pre-feasibility
Study conducted and submit a proposal to the Central Government for 'Site
Clearance' followed by 'In-Principle' approval.
On the request of State Government of Jharkhand, a Pre-feasibility study for
development of a Greenfield airport at Baliapur (Dhanbad) was carried out by
multi-disciplinary team of Airports Authority of India in 2017 and the report
was submitted to State Government.Proposal seeking 'Site Clearance' under GFA Policy for establishment of a
Greenfield Airport at Dhanbad has not been received.
As per GFA Policy, the responsibility for implementation of the Greenfield
airport projects including land acquisition, Rehabilitation & Resettlement,
funding etc. lies with the concerned airport developer or the State Government,
as the case may be. The timeline for completion of the airport projects depends
upon several factors such as land acquisition, availability of mandatory
clearances, financial closure etc.
******