Date: 2026-03-25 Category: LOKSABHA_QNA State: Union Government Country: India

Parliament Question: High-Speed/Bullet Train Corridors

Issued by RAILWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 5374 TO BE ANSWERED ON 25.03.2026 HIGH-SPEED/BULLET TRAIN CORRIDORS 5374. SHRI K E PRAKASH: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government has prepared a long-term plan to expand high- speed rail or bullet train corridors across the country and if so, the details thereof; (b) the details of corridors identified or under consideration including the present status of feasibility studies/Detailed Project Reports; and (c) the details of the estimated financial outlay and funding model proposed for implementing such high-speed rail projects? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (c): Presently, the Mumbai-Ahmedabad High Speed Rail (MAHSR) Project (508 km) is under execution. The Project is passing through the States of Gujarat, Maharashtra and Union Territory of Dadra & Nagar Haveli with 12 stations planned at Mumbai, Thane, Virar, Boisar, Vapi, Billimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati. Entire land (1389.5 Ha.) for MAHSR project has been acquired. All Statutory Clearances have been obtained. All 1651 utilities have been shifted. The delay in land acquisition in the State of Maharashtra has impacted the project till 2021. The land acquisition picked up in 2022 in Maharashtra. Page 1 of 4 §The progress of various major items so far is as under: Item Progress Piers 430 kms. Girder 341 kms. Track Bed 174 kms. OHE Masts 153 kms. The progress of stations is given below:- S.No. Station Status Foundation works completed, Platform slab & 1 Sabarmati roof structural works and finishing works are in progress 2 Ahmedabad Structural works completed and finishing works 3 Anand/Nadiad have been taken up. Foundation work completed, structural works 4 Vadodara and finishing works have been taken up. 5 Bharuch 6 Surat Structural works completed and finishing works 7 Bilimora have been taken up. 8 Vapi 9 Boisar Foundation works have been taken up and in 10 Virar advanced stage. Structural works have been 11 Thane taken up. This is an underground station. Foundation BKC 12 works almost completed and Base Slab has been (Mumbai) taken up. The progress on the River Bridges is as under:- S. River Name Status No. Sub-Structure work completed, 1 Sabarmati River (480m) Superstructure work has been taken up. 2 Meshwa River (120m) 3 Vatrak River (280m) Bridge construction completed. Mohar (Shedhi) River 4 (160m) Page 2 of 411 out of 12 wells completed; 5 spans 5 Mahi River (720m) launched Vishwamitri River 6 (80m) Bridge construction completed. 7 Dhadhar River (120m) 21 out of 25 wells completed; 4 spans 8 Narmada River (1366m) launched 9 Kim River (120m) Bridge construction completed. Foundation work has been taken up, 10 10 Tapi River (720m) out of 12 wells completed 11 Mindhola River (240m) 12 Purna River (360m) 13 Ambika River (200m) 14 Venganiya River (200m) 15 Kaveri River (120m) 16 Kharera River (120m) Bridge construction completed. 17 Auranga River (320m) 18 Par River (320m) 19 Kolak River (160m) Daman Ganga River 20 (360m) 21 Darotha River (80m) 22 Jagani River (360m) Foundation works have been completed 12 Pile Cap and 11 Pier (out of 58) 23 Vaitarna River (2320m) completed. Ulhas River Branch Temporary Access Bridge (TAB) 24 (120m) completed to start the foundation work. Geo-technical Investigation (GTI) has Desai Khadi River 25 been completed and Design work has Bridge (400m) been taken up. The work of the under-sea tunnel (approximately 21 km) has commenced, out of which 4.8 km of tunnel between Ghansoli and Shilphata in Maharashtra has been completed. Page 3 of 4Further, to strengthen national transport infrastructure, provide a fillip to regional connectivity, economic growth, tourism, investment and employment generation, and encourage modal shift from road and air transport to rail, the Government has announced the development of the following seven new High-Speed Rail (HSR) corridors in the Union Budget 2026-27: - (i) Mumbai–Pune (ii) Pune–Hyderabad (iii) Hyderabad–Bengaluru (iv) Hyderabad–Chennai (v) Chennai–Bengaluru (vi) Delhi–Varanasi (vii) Varanasi–Siliguri Being highly capital intensive, the decision to sanction any HSR Corridor/Project depends on many factors such as outcome of DPR, techno- economic feasibility studies and availability of resources such as financing options etc. ***** Page 4 of 4

Continue your research