GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6092
TO BE ANSWERED ON 01.04.2026
HIGH SPEED/SEMI HIGH-SPEED RAIL NETWORK IN KERALA
6092. SHRI KODIKUNNIL SURESH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government proposes to develop a high-speed or semi high-
speed rail network in the State of Kerala;
(b) if so, the details of the proposals examined for such projects, including
the corridors identified, estimated cost and present status;
(c) whether the implementation/feasibility study/planning of any such
project has been entrusted to the Delhi Metro Rail Corporation or the
National High Speed Rail Corporation Limited or any others and if so,
the details thereof;
(d) whether the Government has issued any formal authorization or
advisory role to any previously served Managing Director of DMRC in
relation to planning, feasibility studies or implementation of high-speed
or semi high-speed rail projects in Kerala; and
(e) if so, the details thereof including the current status of such
engagement or consultation?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Increasing Railway Network in Keralam:-
To augment & improve the railway network in Keralam, the following
surveys have been sanctioned for preparation of Detailed Project Report
(DPR) by Indian Railways:-
S. No. Route Length (Km)
1 Shoranur-Mangalore 3rd & 4th Line 307
Page 1 of 5
§2 Coimbatore-Shoranur 3rd & 4th line 99
3 Shoranur – Ernakulam 3rd Line 106
4 Ernakulam-Kayankulam 3rd line (via
115
Kottayam)
5 Kayankulam-Thiruvanathapuram 3rd Line 105
6 Thiruvanathapuram-Nagercoil 3rd Line 71
7 Mararikulam - Alappuzha Doubling 13
After firming up of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines cannot be fixed.
Keralam Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling
fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2025-26 ₹3,042 crore (more than 8 times)
Projects Sanctioned:-
As on 01.04.2025, 06 projects (02 new line and 04 doubling) of 266 km
length, costing ₹9,415 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Balance Expenditure
projects Length Commissioned to upto March
complete 2025
( ₹ in Crore)
New line 02 146 km 0 km 146 km 309
Doubling /
04 120 km 26 km 94 km 2,941
multitracking
Total 06 266 km 26 km 240 km 3,250
Page 2 of 5Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
Keralam are as under:
S.
Project Cost (₹ in Crores)
No.
1. Dindigul-Pollachi-Palghat & Pollachi-Coimbatore
1,360
gauge conversion (217 km)
2. Quilon-Tirunelveli-Tiruchendur gauge
1,122
conversion (357 km)
3. Mulanturutti-Kuruppantara doubling (24 km) 303
4. Chenganur-Chingavanam doubling (27 km) 436
5. Ambalapuzha-Haripad doubling (18 km) 346
6. Kurruppanthara-Chingavanam doubling (27 km) 749
Ongoing Projects:-
Some of the projects falling fully/partly in Keralam which have been taken
up are as under:-
S. No. Project Cost (₹ in Crores)
1. Tirunnavaya –Guruvayur new line (35 Km) 138
2. Angamali-Sabarimala new line (111 km) 3,801
3. Ernakulam-Kumbalam doubling (8 km) 595
4. Kumbalam-Thuravur Patch doubling (16 km) 803
5. Trivandrum- Kanyakumari doubling (87 km) 3,786
6. Shoranur - Vallathol doubling (10 km) 367
7. Palakkad Town – Parli bypass line (2 Km) 164
8. Alappuzha- Ambalapuzha doubling (13 Km) 324
9. Turavur – Mararikulam doubling (21 km) 451
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 476 ha
Land Acquired 65 ha (14%)
Balance Land to be acquired 411 ha (86%)
Page 3 of 5Railway had deposited ₹1,975 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:-
S. Name of the project Total Land Balance
No. land acquired Land to be
required (in Ha) acquired
(in Ha) (in Ha)
1. Angamali - Sabarimala new line (111 416 24 392
km)
2. Ernakulam-Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam-Turavur Patch doubling 10 9 1
(16 km)
4. Shoranur - Vallathol doubling (10 km) 5 0 5
ROBs/RUBs in Keralam:-
To improve safety in train operations and mobility for road users, Indian
Railways have taken up construction of Road Over Bridges (ROBs)/ Road
Under Bridges (RUBs) across tracks in accelerated manner.
The number of ROBs/RUBs constructed across tracks on Indian Railways
during the period 2004-14 vis a vis 2014-26 (upto Jan’26) is as under:
Period ROBs/RUBs constructed
2004-14 4,148 Nos.
2014-26 (upto 14,024 Nos. (including 121 Nos. In the State of
Jan’26) Keralam)
As on 01.02.2026, 138 Nos. Road Over Bridges/Road Under Bridges (ROBs/
RUBs) across railways tracks have been sanctioned at the cost of ₹ 4,835
crore in the State of Keralam which are at various stages of planning and
execution. Out of these, 106 Nos. ROBs/RUBs are delayed on account of
the State Govt. The details are as under:
S. No. Reason ROBs/RUBs
(in No.)
1. Delay in Land Acquisition by State Govt. 38
Page 4 of 52. Finalization of Alignment by State Govt. 63
3. Law & order/ Public Protest/Court cases etc. 2
4. Agency yet to be fixed 3
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
Sanctioning of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s including ROBs/RUBs depends on various
factors which include the following:
Land acquisition by State Government
Forest clearance
State Governments’ consent for closure of LC, fixing of approach
alignment and approval of General Arrangement Drawing (GAD) for
ROBs/RUBs
Removal of encroachments
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****