GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
RAJYA SABHA
UNSTARRED QUESTION NO. 3439
ANSWERED ON 23.03.2026
IMPLEMENTATION AND FUND UTILISATION UNDER THE NAMAMI GANGE
PROGRAMME
3439. SHRI SANJAY SINGH:
Will the Minister of Jal Shakti be pleased to state:
(a) total funds allocated, released, utilised under the Namami Gange Programme since its inception, year-
wise and State-wise;
(b) State-wise and project-wise details of the sanctioned projects, including cost of each project, amount
released so far, expenditure incurred, physical progress and expected date of completion;
(c) total amount of unspent balance currently lying with implementing agencies, State Governments and
executing bodies, year -wise and State-wise;
(d) whether any projects have faced cost escalation, time overruns or re-tendering and the details thereof;
and
(e) the mechanism in place for independent third-party audit of fund utilisation and outcome verification?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) to (c) There is no State-wise allocation of funds under the Namami Gange Programme. The year-wise
budgetary provisions (Revised Estimates) and the amount disbursed by the National Mission for Clean
Ganga (NMCG) under Namami Gange Programme, since its inception, i.e., Financial Year (FY) 2014-15
to till 15 March 2026, are at Annexure I.
Disbursements by NMCG, to various agencies for implementation of projects/interventions compiled
State-wise as per project location, during the above period [FY 2014-15 to FY 2025-26 (up to 15 March
2026)] are at Annexure-II.
The unspent balance reported in Utilization Certificates against grants released by the NMCG up to
31 March 2025 is ₹146.87 crore (as on 15 March 2026). Balance outstanding from major agencies is at
Annexure-III. In the current financial year, the NMCG has assigned limits / released ₹2,102.99 crores till
15 March 2026 to various agencies. Assigned Limits, if not utilized by 31 March 2026, shall lapse.
1The details of State-wise and project-wise sanctioned sewage infrastructure projects, including cost of
each project, amount released so far, expenditure incurred, physical progress and expected date of
completion are at Annexure-IV.
(d) Out of 62 sewage infrastructure projects, 10 projects are delayed by less than one year while 9
projects are delayed by more than 1 year.
Additionally, 22 projects have been finalized after retendering.
Cost escalation is not incurred in all delayed projects. If delay is not attributable to the Contractor,
price escalation is paid as per contract conditions, which may or may not result in additional cost,
depending upon final value of price escalation determined on actual completion of project. If delay is
attributable to the Contractor, damages are imposed and there is no additional cost due to delay. For cost
revision a revised Administrative Approval and Expenditure Sanction (AA&ES) is issued after following
the applicable procedures. For the 62 ongoing projects, cost revision with revised AA&ES has been issued
for 12 projects.
(e) Audit of Annual Accounts of the NMCG is conducted by the Comptroller and Auditor General of
India (C&AG) in accordance with the “The River Ganga (Rejuvenation, Protection and Management)
Authorities Order, 2016” dated 07 October 2016. The C&AG also conducts Compliance/Inspection Audit
and Performance Audit of the NMCG periodically. In addition, Audit of expenditure incurred under World
Bank assisted projects of the Namami Gange Programme is carried out annually by the C&AG. Internal
Audit is conducted by the Internal Audit Wing of the Department of Water Resources, River Development
and Ganga Rejuvenation under the Ministry of Jal Shakti.
***
2ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF UNSTARRED QUESTION
NO. 3439 TO BE ANSWERED IN RAJYA SABHA ON 23.03.2026 REGARDING
“IMPLEMENTATION AND FUND UTILISATION UNDER THE NAMAMI GANGE
PROGRAMME”.
Year-wise Budgetary Provision (Revised Estimate) and disbursements by the NMCG
(₹ in crore)
F.Y. Budgetary Provision (Revised Estimate) Disbursement by NMCG
2014-15 2,053.00 170.99
2015-16 1,650.00 602.30
2016-17 1,675.00 1,062.81
2017-18 3,023.42 1,625.01
2018-19 2,370.00 2,626.54
2019-20 1,553.44 2,673.09
2020-21 1,300.00 1,339.97
2021-22 1,900.00 1,892.70
2022-23 2,500.00 2,258.98
2023-24 2,400.00 2,396.10
2024-25 3,000.00 2,589.11
2025-26 2,687.00 2,102.99
(up to 15.03.2026)
Note :-
(i) NMCG transited to the Treasury Single Account (TSA) system from the financial
year (FY) 2021-22. Prior to NMCG’s transition to the TSA, grants released to the
NMCG by the Government of India were non-lapsable and unspent grants carried
forward from previous years were disbursed in subsequent years.
(ii) Unspent grants amounting to Rs. 1,127.99 crore have been refunded by various
implementing/ executing agencies to the Consolidated Fund of India.
3ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF UNSTARRED QUESTION NO. 3439 TO BE ANSWERED IN RAJYA SABHA ON
23.03.2026 REGARDING “IMPLEMENTATION AND FUND UTILISATION UNDER THE NAMAMI GANGE PROGRAMME”.
Yearly disbursement under Namami Gange Programme State-wise
Financial Year 2014-15 to 15 March 2026
Sl.No. States 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26*
(Rupees in crore)
1 Uttarakhand 4.26 37.04 44.03 242.49 328.94 122.28 124.82 150.75 108.97 143.86 76.20 158.01
2 Uttar Pradesh 74.58 153.35 585.15 550.12 823.77 876.68 472.46 588.14 705.21 796.26 1,225.05 1,130.31
3 Bihar - 124.23 88.07 367.18 673.03 1,185.17 193.84 292.93 873.39 837.13 420.97 214.00
4 Jharkhand 0.97 27.83 49.53 21.72 86.73 30.50 28.09 13.61 3.89 32.60 157.14 46.66
5 West Bengal 73.85 185.49 117.25 246.17 227.62 70.60 105.06 220.34 255.52 150.52 319.41 252.77
6 Madhya Pradesh - 3.39 6.50 - - - - - - 9.50 38.45 43.20
7 Delhi - 4.96 2.17 81.57 310.69 214.47 235.00 405.00 77.33 161.18 39.99 -
8 Haryana - 30.00 52.73 6.88 - - - - - - - -
9 Rajasthan - - 20.00 - 1.25 - - 50.00 - - - -
10 Himachal Pradesh - - - - - 1.25 2.50 - - - -
(*15 March 2026)
Note 1: State-wise disbursements indicated above include funds released to (I) State Missions for Clean Ganga for Sewage Treatment Plants (STPs) and
associated infrastructure, (ii) State Forest Departments for Afforestation and Biodiversity Projects, (iii) STP Projects implemented on Hybrid Annuity
Mode, (iv) Central Public Sector Enterprises for RFD/Ghat Projects, (v) D/o Drinking Water & Sanitation and State Rural Sanitation Missions for
SBM/ODF interventions in Ganga Grams and (vi) Industrial Pollution Abatement Projects.
Note 2: Out of the disbursement/release by the NMCG, unspent grants amounting to Rs.1127.99 crore have been refunded by various
implementing/executing agencies to the Consolidated Fund of India
4ANNEXURE-III
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF UNSTARRED QUESTION NO.
3439 TO BE ANSWERED IN RAJYA SABHA ON 23.03.2026 REGARDING “IMPLEMENTATION
AND FUND UTILISATION UNDER THE NAMAMI GANGE PROGRAMME”.
Unspent balance available with major Agencies against the grants-in-aid released up to 31 March 2025
(as on 15March 2026)
(₹ in crore)
Agency Unspent Balance
Jajmau Tannery Effluent Treatment Association 84.16
Banthar Industrial Pollution Control Company 35.96
Uttar Pradesh State Waste & Sanitation Mission 13.58
Indian Institute of Technology (BHU) Varanasi 4.67
West Bengal State Rural Development Agency 2.56
Uttar Pradesh Forest Department 2.54
Central Bureau of Communication (formerly D.A.V.P.) 1.00
5ANNEXURE-IV
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (c) OF UNSTARRED QUESTION NO. 3439 TO BE ANSWERED IN RAJYA SABHA ON
23.03.2026 REGARDING “IMPLEMENTATION AND FUND UTILISATION UNDER THE NAMAMI GANGE PROGRAMME”.
Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
Uttar Pradesh
1 Prayagraj Sewerage & Non-Sewerage schemes for Pollution abatement of River Completed
199.26 174.7 100
Ganga at District-'B' & 'E' of Prayagraj
2 Prayagraj Sewerage & Non-Sewerage schemes for Pollution abatement of River Completed
106.08 89.85 100
Ganga at District-'A' of Prayagraj
3 Prayagraj 142 Sewerage work in Swerage District-E at Prayagraj 138.25 100 Completed
4 Prayagraj 42.4 14 mld STP at Salori, Prayagraj 34.93 100 Completed
5 Prayagraj 170.95 Sewerage System in Sewerage District-C & Allahpur, Prayagraj 167.87 100 Completed
6 Prayagraj 299.4 Sewerage Works in Sewerage District-A of Prayagraj 291.48 100 Completed
7 Prayagraj 300.84 Sewerage system with Sewer network-(District B) at Prayagraj 294.09 100 Completed
8 Prayagraj Sewer Network in District E of Prayagraj -Part 2 (Additional Work) Completed
52.78 50.43 100
under Component "A"
9 Prayagraj Interception, Diversion and Treatment Works for Naini (District G) Completed
767.59 276.97 100
Phaphamau (District F) and Jhunsi at Prayagraj (HAM)
10 Prayagraj Rehabilitation and Operation & Maintenance of existing Sewage Completed
904 281.04 100
Treatment Infrastrcture at Prayagraj (HAM)
11 Varanasi JICA assisted Ganga Action Plan Phase-II Project at Varanasi (EAP - Completed
100
JICA) Construction of 140 MLD STP at Dinapur at Varanasi
12 Varanasi Construction of interceptor sewers, relieving trunk sewer & rising mains Completed
100
at Varanasi
13 Varanasi Construction of 3 pumping stations (Chaukaghat, Phulwariya & Sariya) Completed
659.62 597.67 100
at Varanasi
14 Varanasi Rehabilitation of old trunk sewer at Varanasi 100 Completed
15 Varanasi Rehabilitation of 5 Ghat pumping stations and STPs at Dinapur & Completed
100
Bhagwanpur at Varanasi
16 Varanasi Non Sewerage, Institutional Development & Other works at Varanasi 100 Completed
17 Garmukteshwar 46.51 Sewerage system & STP works at Garmukteshwar 44.58 100 Completed
6Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
18 Moradabad 330.05 Sewerage system & STP works (Phase I ) at Moradabad 289.22 100 Completed
19 Moradabad Pollution Abatement Works for River Ram Ganga at Moradabad Completed
149.23 35.56 100
(Sewerage Zone-2) (HAM)
20 Kannuaj 43.66 Sewerage system & STP works (Phase II) at kannuaj 40.67 100 Completed
21 Narora 48.45 Sewerage scheme at Narora, Bulandshar 47.69 100 Completed
22 Anup Shahar 75.79 Sewerage Works in Anup Shahar, Buland Shahar 70.82 100 Completed
23 Bithoor, Sewerage scheme and STP at Bithoor Kanpurnagar, (UP) Completed
13.4 10.96 100
Kanpurnagar
24 Ramana Sewerage Treatment Plant (STP) for Assi-BHU Sewerage District at Completed
161.31 138.06 100
(Varanasi) Ramana (HAM)
25 Ramnagar Interception,diversion of Drains & Sewage Treatment works at Completed
72.91 35.47 100
(Varanasi) Ramnagar
26 Kanpur City 63.8 Interception/Diversion of Sisamau Nala of Kanpur City 60.36 100 Completed
27 Kanpur Sewerage Works in Sewerage District 1 of Kanpur Completed
430.49 463.08 100
( District 1 )
28 Pankha-Kanpur Rehabilitation of existing Sewage Treatment Infrastructure , Completed
967.23 Development of sewage Treatment Plant at Pankha (30 MLD) along with 254.98 100
appurtenant works at Kanpur (HAM)
29 Vrindavan Rehabilaition of Sewerage Infrastructure & Augmenation/Upgradation Completed
42.82 24.52 100
at vrindavan
30 Unnao Interception,diversion of Drains & Sewage Treatment works at Unnao Completed
102.2 52.01 100
(HAM)
31 Shuklaganj, Interception,diversion of Drains & Sewage Treatment works at 2026-27
65.18 27.62 97
Shuklaganj (HAM)
32 Mirzapur Interception, Diversion and Treatment Works for abatement of Pollution Completed
147.33 91.45 100
of River Ganga at Mirzapur (HAM)
33 Chunar 2.7 Faecal Sludge Management for pollution abatement at Chunar (FSTP) 2.24 100 Completed
34 Farrukhabad Interception, Diversion & Sewage Treatment Works in Farrukhabad- Completed
261.12 177.62 100
Fategarh (HAM)
35 Mathura Rehabilaition/Renovation of Mathura sewerage scheme : Construction of Completed
460.45 315.3 100
30 MLD STP at Masani (Mathura) (HAM)
7Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
36 Mathura 292.56 I&D and STP Works for balance drains at Mathura (HAM) 4.81 75 2026-27
37 Ayodhya- Interception & Diversion (I&D) of drains at Ayodhya Completed
37.67 21.24 100
Faizabad
38 Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, Completed
221.66 97 100
District Ayodhya (Interception & Diversion with STP) (HAM)
39 Sultanpur 70.18 Interception & Diversion with STP at Sultanpur 47.2 100 Completed
40 Kasganj 76.73 Interception & Diversion with STP at Kasganj 43.31 100 Completed
41 Agra Interception & Diversion with Rehabilitation of sewerage scheme at 2026-27
842.25 208.63 79
Agra (HAM)
42 Muzaffarnagar 234.03 Interception & Diversion works and STP at Muzaffarnagar (HAM) 141.79 100 Completed
43 Budhana 48.76 Interception & Diversion works and STP at Budhana (HAM) 29.15 100 Completed
44 Bareilly 271.39 Interception & Diversion works and STP at Bareilly (HAM) 182.26 100 Completed
45 Jaunpur 206.05 Interception & Diversion works and STP at Jaunpur 152 100 Completed
46 Meerut 690.71 Pollution Abatement Works for River Kali Meerut (HAM) 13.34 47 2026-27
47 Baghpat 77.36 Interception & Diversion and STP works of Baghpat Town 37.43 100 Completed
48 Firozabad 51.08 Firozabad Sewerage Scheme (Interception & Diversion) works 29.94 100 Completed
49 Etawah 140.6 Sewerage Scheme (Interception & Diversion) works at Etwah 60.09 100 Completed
50 Lucknow 240.93 Interception & Diversion and STP works at Lucknow 117.65 100 Completed
51 Ghazipur 165.99 Sewerage,Sewage Treatment works at Ghazipur (HAM) 85.46 100 Completed
52 Kairana 78.42 Interception & Diversion works for Kairana 34.39 100 Completed
53 Bijnor 0.39 Faecal Sludge Management (Co-treatment) at Bijnor 0.13 100 Completed
54 Saharanpur Interception & Diversion (I&D) and Sewage Treatment Plant works at 2027-28
577.23 10.27 7
Saharanpur (HAM)
55 Varanasi 308.09 I&D and STP Works for Assi-BHU Area (Phase II), Varanasi 86.62 98 2025-26
56 Chhata 56.15 I&D and STP Works at Chhata 2.11 11 2026-27
57 Kosi 66.59 I&D and STP Works at Kosi 1.53 35 2026-27
58 Vrindavan 77.7 I&D and STP Works Vrindavan 24.36 89 2025-26
59 Hathras 128.91 I&D and STP works at Hathras 11.05 39 2026-27
60 Lucknow 264.67 Interception & Diversion and STP works at Lucknow, Phase-II Part-I 7.22 6 2026-27
61 Prayagraj Interception & Diversion of Balance 7 drains and Augmentation of 2026-27
475.98 62.4 69
Rajapur STP at Prayagraj
8Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
62 Prayagraj Interception and diversion of balance discharge of 13 drains and 2025-26
331.75 81.92 91
augmentation of Salori STP
63 Banat 48.71 I&D and STP works at Banat 4.02 48 2026-27
64 Babri & I&D and STP works at Babri & Bantikhera 2026-27
55.47 1.38 8
Bantikhera
65 Thanabhawan 97.19 I&D and STP works at Thanabhawan 6.32 49 2026-27
66 Shamli 206.02 I&D and STP works at Shamli 15.44 51 2026-27
67 Hapur 49.06 I&D and STP works at Hapur 0.71 25 2026-27
68 Prayagraj Interception and Diversion of Balance Discharge of 02 Drains and 50 2026-27
186.47 8.48 45
MLD STP at Naini Prayagraj
69 Lucknow Interception & Diversion and STP works at Lucknow, Phase-II Part-II 2027-28
351.03 - -
(HAM)
70 Deoband 134.71 Interception & Diversion and STP works at Deoband - - 2027-28
71 Dalmau Faecal Sludge Management for Pollution Abatement Works at Dalmau, 2027-28
4.4 - -
Raibareli (FSTP)
72 Gulaothi 50.99 Interception & Diversion and STP works at Gulaothi - 3 2027-28
73 Aligarh 496.02 Interception & Diversion and STP works at Aligarh (HAM) - - 2027-28
74 Manikpur Faecal Sludge Management for pollution abatement of River Ganga at 2027-28
8.56 - -
Manikpur, (FSTP)
75 Pt. DDU Interception & Diversion and STP works at Pt. DDU Chandauli (HAM) 2027-28
262.78 - -
Chandauli
76 Bhadohi 127.26 Interception & Diversion of Drains/nalas and STPs works at Bhadohi - - 2027-28
77 Varanasi (Durga Interception & Diversion and 60 MLD STP works for Durga Drain at 2027-28
274.31 - -
Drain) Varanasi (HAM)
78 Moradabad Interception & Diversion of drains of Moradabad Zone-3 & Zone-4 with 2027-28
420.41 - -
STP & other appurtenant works at Moradabad (HAM)
79 Kanpur 138.11 Interception & Diversion of 14 drains of Kanpur City - - 2027-28
80 Agra Tapping of balance drains & augmentation of sewage pumping stations 2027-28
126.41 - -
(SPSs) at Agra
Bihar
81 Begusarai 230.06 Sewer Network, SPS and STP at Begusrai 261.82 97 2026-27
9Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
82 Buxar 257.03 I & D and STP works at Buxer 17.29 39 2027-28
83 Hajipur 305.19 Sewer Networks, SPS and STP at Hajipur 346.46 95 2026-27
84 Munger 522.85 Sewer Networks, SPS and STP at Munger 428.71 100 Completed
85 Patna-Beur 93.94 Sewage Treatment Plant - Beur for Patna, Bihar 69.96 100 Completed
86 Patna Beur 225.77 Sewerage system with Sewer network,Patna Beur 369.66 100 Completed
87 Patna- Sewage Treatment Plant - Karmalichak for Patna, Bihar Completed
90.94 68.39 100
Karmalichak
88 Patna-Saidpur 184.93 Saidpur STP and adjoining Network for Patna, Bihar 184.77 100 Completed
89 Patna-Saidpur 560.42 Saidpur Sewer Network, Patna, Bihar 491.14 100 Completed
90 Patna- Sewerage system with Sewer network ,Patna Karmalichak Completed
277.42 336.59 100
Karmalichak
91 Patna-Pahari 191.62 Sewage Treatment Plant at Pahari - Patna, Bihar 125.65 100 Completed
92 Patna-Pahari 230.48 Sewerage scheme at Pahari (Zone IVA (S)), Patna, Bihar 215.48 100 Completed
93 Patna-Pahari 356.37 Sewerage scheme at Pahari Zone V, Patna, Bihar 312.96 100 Completed
94 Mokama 73.4 Interception, Diversion & Sewage Treatment Plant works at Mokama 51.53 100 Completed
95 Barh 61.85 I&D and STP Project at Barh (Patna) 41.8 100 Completed
96 Patna- Sewage Treatment Plant (50MLD) and Sewerage Network(150 km)in 2026-27
578.89 171.79 55
Kankarbagh Kankarbagh-Patna (HAM)
97 Patna -Digha Sewage Treatment Plant (100MLD) and Sewerage Network(288 km)in 2026-27
824 396.71 57
Digha-Patna (HAM)
98 Maner 69.77 Interception & Diversion & Sewage Treatment Plant for Maner Town 43.48 100 Completed
99 Danapur Interception & Diversion & Sewage Treatment Plant for Danapur Town 73.94 100 Completed
204.50
100 Phulwari Interception & Diversion & Sewage Treatment Plant for Phulwarishariff Completed
13.54 100
shariff-Patna Town
101 Fatuha Interception and Diversion and STP works in Fatuha 16.41 100 Completed
102 Sultanganj 60.22 Interception, Diversion & Sewage Treatment Plant works at sultanganj 35.45 100 Completed
103 Naugachia 82.51 Interception, Diversion & Sewage Treatment Plant at Naugachia 49.11 100 Completed
104 Bhagalpur 413.29 Interception and Diversion and STP works in Bhagalpur (HAM) 123.1 97 2026-27
105 Kahalgaon 48.2 Interception and Diversion and STP scheme in Kahalgaon 23.8 84 2026-27
106 Sonepur 47.41 Interception and Diversion and STP works in Sonepur 29.47 100 Completed
107 Chhapra 357.8 Interception and Diversion and STP works in Chhapra 153.66 100 Completed
10Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
108 Bakhtiyarpur 84.93 Interception and Diversion and STP works in Bakhtiyarpur 62.73 100 Completed
109 Barahiya 59.28 Interception and Diversion and STP works in Barahiya 1.44 3 2026-27
110 Dehri 63.89 Interception and Diversion and STP works at Dehri 7.46 34 2026-27
111 Supaul 76.69 I&D and STP Works at Supaul - 16 2026-27
112 Motihari 149.16 Interception & Diversion and STP scheme at Motihari - - 2027-28
113 Daudnagar 42.25 Interception & Diversion of drains and STP works at Daudnagar - - 2027-28
114 Lakhisarai 94.13 Interception & Diversion and STP scheme at Lakhisarai town - - 2027-28
115 Jamui 77.39 Interception & Diversion and STP scheme for Jamui - 5 2027-28
116 Raxual 78.78 Interception & Diversion of drains and STP scheme for Raxaul - - 2027-28
117 Katihar 356.99 Interception & Diversion of drains and STP scheme for Katihar (HAM) - - 2027-28
118 Arrah 328.29 Interception & Diversion and STP scheme for Arrah (HAM) - - 2027-28
119 Muzaffarpur 77.4 Interception & Diversion and STP scheme for Muzzafarpur - - 2027-28
Delhi
120 Delhi -YAP-III Rehabilitation of Trunk Sewer No.4 Completed
- Kondli zone 87.43 49.4 100
(K1)
121 Delhi -YAP-III Rehabilitation of Trunk Sewer No.5 Completed
- Kondli zone 83.4 75.42 100
(K2)
122 Delhi -YAP-III Rehabilitation and upgradation of Kondli Phase-I STP (45 MLD), Phase- Completed
- Kondli zone 239.11 II STP (114 MLD) & Phase-III STP (45 MLD) 268.13 100
(K3)
123 Delhi -YAP-III Rehabilitation of Rising Mains Completed
- Kondli zone 59.13 56.43 100
(K4)
124 Delhi -YAP-III Rehabilitation of Trunk Sewers Completed
-Rithala zone 43.92 21.39 100
(R1a)
125 Delhi -YAP-III Rehabilitation of Rising Main Completed
-Rithala zone 45.4 48.54 100
(R1b)
11Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
126 Delhi -YAP-III Rehabilitation and up-gradation of Phase-I STP (182 MLD) Completed
-Rithala zone 211.79 208.71 100
(R2)
127 Delhi -YAP-III Construction of 564 MLD (124 MGD) Waste Water Treatment Plant Completed
- Okhla zone 665.78 (WWTP) 782.51 100
(O)
128 Coronation Construction of 318 MLD (70 MGD) WWTP with 10 years O & M on Completed
515.07 388.08 100
Pillar, Delhi DBO basis at Coronation Pillar, Delhi
129 Mehrauli Construction of 4.5 MLD STP along with other allied works at Sector-A, 2027-28
35.83 - -
Vasant Kunj to feed treated water to Shamsi Talab at Mehrauli, Delhi
130 Coronation Conveyance of treated sewage from Coronation Pillar STP to the River 2027-28
518.88 - -
Pillar, Delhi Yamuna
Jharkhand
131 Sahibganj 99.36 Sewerage scheme and STP 134.33 100 Completed
132 Rajmahal 56.76 Sewerage scheme and STP 57.02 100 Completed
133 Phusro 61.05 I & D and STP Project 27.51 88 2026-27
134 Ramgarh 284.8 I&D and STP scheme at Ramgarh 79.68 60 2026-27
135 Dhanbad 808.33 I&D and STP Works at Dhanbad (HAM) 1.85 - 2027-28
Haryana
136 Panipat 129.51 Sewerage and Sewage Treatment Plant (STP) at Panipat 128.45 100 Completed
137 Sonepat 88.36 Sewerage and Sewage Treatment Plant (STP) at Sonipat 89.49 100 Completed
138 Kota 258.48 Environmental Improvement Plan for River Chambal at Kota 181.86 97 2026-27
Himachal Pradesh
139 Paonta Sahib Sewerage scheme for Zone II & III of Paonta Town in Tehsil Poanta Completed
11.57 3.75 100
Sahib,District Sirmour
Uttarakhand
140 Badrinath 7.259 Interception and Diversion (I&D) at Badrinath 7.25 100 Completed
141 Badrinath Pollution Abatement works (Interception and Diversion with STP) at Completed
18.23 9.47 100
Badrinath
142 Devprayag 3.664 Sewage Treatment Plant (STP) at Devprayag 3.5 100 Completed
143 Devprayag 7.269 Interception and Diversion (I&D) Devprayag 7.18 100 Completed
12Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
144 Devprayag Restoration and Reconstruction of Sewerage Scheme due to disaster in Completed
4.5 4.1 100
Devprayag
145 Joshimath 9.61 Interception and Diversion (I&D) at Joshimath 9.46 100 Completed
146 Joshimath 62.4 Interception and Diversion (I&D)with STP at Joshimath 40.72 100 Completed
147 Gopeshwar 10.18 Interception and Diversion (I&D) at Gopeshwar 9.73 100 Completed
148 Chamoli- Interception & Diversion and STP, at Chamoli Completed
64.34 33.34 100
Gopeshwar
149 Rishikesh 7.23 Sewerage Scheme at Triveni Ghat at Rishikesh 4.36 100 Completed
150 Rishikesh 158 Interception and Diversion (I&D)with STP Rishikesh 112.69 100 Completed
151 Tapovan Sewerage system and STP for Tapovan area Completed
24.12 15.55 100
(Tehri)
152 Tapovan upgradation of 3.50 MLD STP at tapovan Completed
2.19 0.73 100
(Tehri)
153 Haridwar 24.84 Sewerage Scheme at Ahbab Nagar Jwalapur Zone E-2 at Haridwar 16.98 100 Completed
154 Haridwar 24.91 Construction of 18 mld STP at Sarai, Haridwar 20.69 100 Completed
155 Haridwar Sewage Treatment Plant (STP) at Jagjeetpur(68MLD) & Sarai(14MLD) Completed
273.37 163.71 100
(HAM)
156 Haridwar Tetiary treatment of existing 27 MLD STP at Jagjeetpur & Upgradation Completed
32.65 14.87 100
of existing 18 MLD STP at Sarai
157 Haridwar 116.28 Interception and Diversion works at Sarai & Jagjeetpur 95.77 100 Completed
158 Haridwar Laying of Sewer Lines in Arihant Vihar & New Vishnu Garden, Kankhal Completed
4.68 3.35 100
in Haridwar
159 Gangotri 10.48 Sewerage System and STP for Gangotri Dham 7.83 100 Completed
160 Gangotri Restoration and Reconstruction of Sewerage Scheme due to disaster in Completed
0.45 0.45 100
Gangotri
161 Uttarkashi Restoration and Reconstruction of Sewerage Scheme due to disaster in Completed
4.84 3.48 100
Uttarkashi
162 Uttarkashi 10.03 Upgradation of 2MLD STP (Gyansu) Uttarkashi 3.94 100 Completed
163 Karanprayag Interception and Diversion (I&D) / Sewage Treatment Plant (STP) at Completed
12.01 9.03 100
Karanprayag
164 Rudraprayag 13.14 Interception and Diversion (I&D) / Sewage Treatment Plant (STP) at 9.92 100 Completed
13Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
Rudraprayag
165 Rudraprayag 23.37 I & D and STP for Gauri Kund and Tilwada, District Rudraprayag 6.87 55 2026-27
166 Kirtinagar Pollution Abatement works for River Alaknanda (STP creation of Completed
4.23 2.32 100
10KLD & 50KLD) at Kirtinagar
167 Srinagar 22.51 Interception & Diversion and STP at srinagar 16.56 100 Completed
168 Srinagar 15.4 Upgradation of Existing STP (3.5 MLD ) at srinagar 4.81 100 Completed
169 Nandprayag 6.46 Interception & Diversion and STP at nandprayag 4.52 100 Completed
170 Muni Ki Reti 80.45 Rising main (500m) and STP of 12.5MLD at muni ki reti 51.64 100 Completed
171 Muni Ki Reti 8.67 Sludge Management Plant at Chorepani, Muni Ki Reti 4.61 100 Completed
172 Muni Ki Reti 94.06 I & D and STP works at Muni ki reti Neelkanth 24.25 75 2026-27
173 Swargashram 5.2 Upgradation of Existing STP (3.0 MLD ) at swargashram 2.4 100 Completed
174 Dehradun Interception & Diversion Works for Rispana & Bindal River in Completed
63.75 47.29 100
Dehradun
175 Ramnagar Interception & Diversion of Nallas Discharging in Kosi River at Completed
55.06 34.73 100
Ramnagar
176 Srikot- Pollution Abatement of River Alaknanda at Srikot-Gangnali Part A Completed
7.86 4.56 100
Gangnali
177 Udham Singh (I&D) and STP work of 06 nos. Polluted River Stretches at Udham Completed
223.43 110.85 100
Nagar Singh Nagar
178 Haridwar Co-Treatment of Septage at existing STPs of Haridwar-150 KLD (100 Completed
11.12 KLD Jagjeetpur + 50 KLD Sarai), Rishikesh-50 KLD, Srinagar 30 KLD 7.33 100
and Devprayag-5.0 KLD
179 Devprayag, Repair and Restoration (Protection works) in existing STPs/Sewerage Completed
Karanprayag network and its appurtenant works damaged during natural calamity
0.87 0.62 100
and Chamoli-
Gopeshwar
180 Dehradun 78.99 I&D with STP works at Sapera Basti, Dehradun 27.33 87 2026-27
181 Kotdwar 135.27 Pollution Abatement Works (I&D with STP) for Khoh River at Kotdwar 13.44 25 2026-27
West bengal
182 Gayeshpur 168.67 Sewerage system & STP at Gayeshpur 156.34 100 Completed
183 Kalyani 57.87 Sewerage system & STP at Kalyani 118.01 100 Completed
14Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
184 Bhatpara 228.52 Sewerage system & STP at Bhatpara 328.84 100 Completed
185 Halisahar 332.56 Sewerage scheme & STP Halishar 282.26 100 Completed
186 Budge-Budge 225.45 Sewerage System and STP at Budge-Budge 170.8 100 Completed
187 Barrackpore 341.68 Sewerage system with Sewer network and STP at Barrackpore 311.46 100 Completed
188 Kancharapara Interception & Diversion with STP at Kachrapara Completed
48.77 29.44 100
(Barrackpore)
189 Barrackpore Design and Build of I & D structure. including Lock Gate and it's all Completed
0.93 - 100
Municipality appurtenant structures as well as allied works at Barrackpore
190 Tolly's Nullah Pollution Abatement work for Rejuvenation of River Adi Ganga, Kolkata 2027-28
817.3 - 5
(Adi Ganga) (Tolly's Nullah)
191 Howrah Pollution Abatement Works for River Ganga at Howrah(Interception & Completed
100
Diversion with STP) (HAM)
192 Bally Pollution Abatement Works for River Ganga at Bally under Howrah Completed
100
595.72 Municipal Corporation (HAM) 252.85
193 Kamarhati and STP & Sewer network at Kamrahati and baranagar (HAM) Completed
Baranagar 100
Municipalities
194 Nabadwip Interception & Diversion Network for existing drains falling in river Completed
61.23 37.79 100
Ganges including STP at Nabadwip
195 Berhampore Pollution Abatement works for River Ganga at Behrampore- Municipal 2025-26
51.21 0 92
Town (Interception & Diversion)
196 Jangipur Pollution Abatement Works for River Ganga at Jangipur Completed
68.47 53.82 100
Municipality
197 Kolkata Pollution Abatement Works for River Ganga at Kolkata municipality
7.56 7.56 40
(Installation of New Penstock/construction) 2026-27
198 Kolkata Pollution Abatement Works for River Ganga at Kolkata (Garden Reach)
289.02 36.47 64
(HAM) 2026-27
199 Maheshtala 286.97 Pollution Abatement works for River Ganga at Maheshtala (HAM) 105.19 100 Completed
200 Hooghly- Pollution Abatement works for River Ganga at Hooghly Chinsurah- 2026-27
161.99 96.8 93
Chinsurah Municipal Town
201 Hoogly 86.61 Rejuvenation of existing STPs alongwith lifting stations & pumping 38.28 100 Completed
15Sewage Infrastructure Projects list As of Feb-2026
SR Towns Sanctioned Name/Nature of works Expenditure Overall Tentative
No. Cost /Released Physical year of
(Rs. in crore) (in Cr.) Progress c o mpletion
(%)
station at Hoogly
202 Burdwan Faecal Sludge Management for abatement of pollution in River Ganga 2027-28
10.35 - -
(FSTP)
203 North 24 Rejuvenation of existing STPs alongwith lifting stations & pumping Completed
65.54 51.29 100
Parganas stations at North 24 Parganas
204 North Pollution Abatement Works for River Ganga at North Barrackpore 2026-27
154.27 20.58 99
Barrackpore (HAM)
205 keorapukur 124.38 Rehabilitation of existing STP keorapukur - - 2027-28
206 Chakdah 121.66 Interception and Diversion with STP at Chakdah 28.15 91 2026-27
207 Krishnanagar 91.88 Interception and Diversion with STP at Krishnanagar 4.37 14 2026-27
208 Bansberia Pollution Abatement Sewerage Infrastructure (Integrated Septage 2026-27
4.56 - 51
Treatment Plant) at Bansberia (FSTP)
209 Murshidabad 92.85 Interception and Diversion with STP at Murshidabad - - 2027-28
210 Katwa Interception and Diversion with STP, 14 MLD STP with co-treatment 2027-28
133.46 - -
10.5 KLD at Katwa
211 Uttarpara- Pollution Abatement Integrated Septage Treatment Plant for Uttarpara- 2027-28
8.04 - -
Kotrung Kotrung (FSTP)
212 Pujali Integrated Septage Treatment Plant for Pujali, South 24 Parganas District 2027-28
5.77 - -
(FSTP)
213 Bhatpara Installation of Chlorination Unit in Rejuvenated STPs (WSP/ASP) at 2027-28
4.61 - -
Bhatpara
214 24 Installation of chlorination units in 9 existing STPs 2027-28
PARAGANAS 18.93 - -
NORTH
215 Siliguri 361.86 I&D of Drains with Construction STP at Siliguri - - 2027-28
Madhya Pradesh
216 Indore 511.15 Interception and Diversion with STP at Indore - 11 2027-28
217 Ujjain 101.57 Interception & Diversion with STP works at Ujjain - - 2027-28
218 Nagda 65.98 Interception & Diversion with STP works at Nagda - 2 2027-28
*****
16