See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF MICRO, SMALL AND MEDIUM ENTERPRISES
LOK SABHA
UNSTARRED QUESTION NO. 3027
TO BE ANSWERED ON 06.08.2026
IMPLEMENTATION OF MSE-CDP
3027. SHRI KESINENI SIVANATH:
Will the Minister of MICRO, SMALL AND MEDIUM ENTERPRISES be pleased to state:
(a) the details and the total number of proposals received and approved under Micro & Small
Enterprises–Cluster Development Programme (MSE-CDP) since its inception, year-wise, State-
wise and district-wise for Andhra Pradesh;
(b) the funds allocated, released and utilised, since its inception, year-wise and State-wise;
(c) the physical status of approved projects and the timeline targeted for completion, State-wise
and district-wise for Andhra Pradesh;
(d) the measures taken to ensure skilling of women entrepreneurs to form self-employment
generating clusters in different sectors such as textiles; and
(e) the issues faced in implementation of the scheme and the measures taken to address the
same?
ANSWER
MINISTER OF STATE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
(SUSHRI SHOBHA KARANDLAJE)
(a) to (c): The details of total number of proposals approved under Micro & Small Enterprises–
Cluster Development Programme (MSE-CDP) since its inception, year-wise, State-wise and
district-wise in Andhra Pradesh along with funds allocated, released and status, is given at
Annexure.
(d): Under the Entrepreneurship and Skill Development Programme (ESDP) scheme during the
last five Financial Years, total 42,211 number of training programmes were conducted involving
19,54,701 participants including 6,66,327 women beneficiaries in different sectors.
(e): The issues faced in implementation of the projects are addressed in coordination with the
State Government and the concerned Implementing Agency.
*******Annexure
Annexure referred to in reply of part (a) to (c) of Lok Sabha Unstarred Question No. 3027 for
answer on 06.08.2026.
Details of total number of proposals approved under Micro & Small Enterprises–Cluster
Development Programme (MSE-CDP) since its inception, year-wise, State-wise and district-wise in
Andhra Pradesh along with funds allocated, released and status:
A. Completed Common Facility Centres (CFCs)
Total
GoI
Project GoI Year of
Name of the Year of Grant Status
S. District Cost grant Completion
Project approval Approved
No. released
Rs. in lakh
Imitation
Jewellery
1. Industry Krishna 2007-08 127.85 61.43 48.2 2011-12 Completed
Cluster,
Machilipatnam
Gold Ornament
(Jewellery)
2. Krishna 2013-14 259.68 225.16 225.16 2017-18 Completed
Cluster,
Vijayawada
Printing Cluster, East
3. 2021-22 1476 1033.2 1033.2 2025-26 Completed
Kakinada Godavari
Gold Ornament
4. Cluster, Krishna 2021-22 800 614.52 614.52 2025-26 Completed
Jaggayyapeta
Pulses & Pulses
Products
Cluster,
East 1483.0
5. Machavaram 2021-22 1038.14 1038.14 2025-26 Completed
Godavari 6
village,
Rayavaram
Mandal
B. Completed Infrastructure Development (ID) Projects
Total
GoI
Project GoI Year of
Name of the Year of Grant Status
S. District Cost grant Completion
Project approval Approved
No. released
Rs. in lakh
New Industrial
Estate at 2006-07
1. Kurnool 1994-95 328 131 65.5 Completed
Nandial Distt.
MandalNew Industrial
2006-07
2. Estate at Tada Nellore 1998-99 404.69 161.87 94 Completed
Distt.
New Industrial
Estate at 2008-09
3. Krishna 2002-03 370 148 147.19 Completed
Vijayawada,
Distt.
Up-gradation of
JRD Industrial
2019-20
4. Estate at Krishna 2013-14 767.62 614.1 552 Completed
Kanuru,
Vijayawada
New Industrial
2023-24
5. Estate at Kadapa 2017-18 2202.47 736.48 229.5589 Completed
Kopparthy IP
Up-gradation of
Industrial Estate 2019-20
6. Srikakularn 2017-18 355.77 284.62 200 Completed
at
Amudalavalasa
Up-gradation of
ID centre at Vishakhapa 2021-22
7. 2018-19 490.64 245.32 200 Completed
Autonagar, tnam
Gajuwaka
New
Infrastructure East 2022-23
8. 2018-19 690.91 414.55 284.196 Completed
Development at Godawari
Peddapuram
Up-gradation of
2022-23
9. ID centre at Prakasam 2018-19 1055.84 500 200 Completed
Singarayakonda
New Industrial
2023-24
10. Estate at Chittor 2018-19 833.71 666.96 349.016 Completed
Gandrajupalli
Up-gradation of
ID centre at SPSR 2023-24
11. 2018-19 2202.57 800 272.4 Completed
Autonagar, Nellore
Vedayapalem
Up-gradation of
2025-26
12. Industrial Estate Guntur 2021-22 691.97 416.75 261.5517 Completed
at (Autonagar)C. Ongoing Common Facility Centres (CFCs)
Total
GoI
Year of Project GoI
Grant
Name of the approv Cost grant Status
S. No District Approved
Project al released
(Rs. in Lakh)
Furniture
2021-
1. Manufacturing Rajamundry 1498.41 1048.88 943.992 Ongoing
22
Cluster
Hosiery &
Readymade 2021-
2. Nellore 822.98 576.08 518.472 Ongoing
Garments 22
Cluster
2024-
3. Printing Cluster Tirupati 2519.26 1763.48 - Ongoing
25
Food Processing 2024-
4. Srikakulam 2994 2095 - Ongoing
Cluster 25
Coconut Cluster,
2025-
5. Yalamanchili West Godavari 2997.45 2098.21 - Ongoing
26
Mandal
Gold Ornaments
2025-
6. Cluster, Guntur 999.36 799.49 - Ongoing
26
Mangalagiri
D. Ongoing Infrastructure Development (ID) Projects
GoI
Project Total GoI
Grant
Name of the Year of Cost grant Status
S. No District Approved
Project approval released
(Rs. in Lakh)
Up-gradation of
Industrial Estate
1. Krishna 2021-22 817.44 572.21 200 Ongoing
(Jewellery) at
Machilipatnam
Up-gradation of
2. Growth Centre at Anantapuram 2021-22 715.06 443.71 200 Ongoing
Hindupur
Up-gradation of
3. Industrial Estate at West Godavari 2023-24 1010 800 720 Ongoing
Tanuku
Up-gradation of
existing Industrial
4. Vizianagaram 2023-24 646.08 516.86 200 Ongoing
Estate at
NellimarlaDevelopment of
Flatted Factory
Complex (FFC) at
5. Atchutapuram, Visakhapatnam 2023-24 1343.91 1032.56 200 Ongoing
Gurajapalem
Village, Rambilli
Mandal
FFC at
Peddapuram,
Bhimavaram
6. Kakinada 2023-24 1330 931 465.5 Ongoing
Village
&Samalkot
Mandal
New Industrial
Estate at Pagali
7. (Block-II), Pagali Tirupati 2023-24 1030 721 360.5 Ongoing
Village, Yerpedu
Mandal
New Industrial
Estate at
8. Kurnool 2023-24 2140 1050 525 Ongoing
Guttapadu,
OrvakalMandal
FFC at IP,
9. Visakhapatnam 2023-24 757 529.9 264.95 Ongoing
Pedagantyada
New Industrial
10. Estate at 5- Chittoor 2023-24 1430 1001 500.5 Ongoing
Venkatapuram
New Industrial
Estate at
11. Y.S.R. Kadapa 2023-24 1525.49 1050 945 Ongoing
Gopavaram
Village & Mandal
New Industrial
Estate at
12. Prakasam 2023-24 1076.41 753.49 678.141 Ongoing
Chandalur, Darsi
Mandal
New Industrial
Estate at
Jagadurthy,
13. Nandyal 2023-24 1045.99 732.19 366.095 Ongoing
Jagadurthy
Village, Dhone
Mandal
New Industrial
Estate (phase-III)
at
14. Krishna 2023-24 1470 1029 926.1 Ongoing
Veerapanenigude
m(V),
Gannavaram
New Industrial
Estate at
Kalavacharla
15. East Godavari 2023-24 2065 1050 945 Ongoing
(Greenfield),
Rajanagaram
MandalFlatted Factory
Complex (FFC) at
16. Pydibhimavaram, Srikakulam 2023-24 1460 1022 511 Ongoing
Ranastalam
Mandal
New Industrial
Estate at
17. Kappalabanda Sri Sathya Sai 2023-24 1171.13 819.79 409.89 Ongoing
Village,
Puttaparthi Mandal
New Industrial
18. Anakapalli 2023-24 2686 1050 525 Ongoing
Estate at Koduru
New Industrial
Estate at
Narampeta, S.P.S.R.
19. 2023-24 2343 1050 525 Ongoing
Narampeta Nellore
Village, Atmakur
Mandal
New Industrial
Estate at
Thatiguntapalli
20. Annamayya 2023-24 1592.53 1050 525 Ongoing
Village,
Valmikipuram
Mandal
Up-gradation of
Industrial Estate at
21. Autonagar Prakasam 2025-26 1095 600 300 Ongoing
Throvagunta,
Ongole Mandal
New Industrial
Estate at
22. Brahmanapalle Kurnool 2025-26 851.99 596.39 298.195 Ongoing
Village, Orvakal
Mandal
Flatted Factory
Complex at UDL
23. 2, Nagamangalam Chittoor 2025-26 1527 1050 525 Ongoing
Village, Palamaner
Mandal
Flatted Factory
Complex at
Brahmanapalle,
24. Kurnool 2025-26 1295.92 907.14 453.57 Ongoing
Brahmanapalle
Village, Orvakal
Mandal