See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RURAL DEVELOPMENT
DEPARTMENT OF RURAL DEVELOPMENT
LOK SABHA
UNSTARRED QUESTION NO. 5203
ANSWERED ON 24/03/2026
IMPLEMENTATION OF PMGSY IN TAMIL NADU
5203. Shri Malaiyarasan D:
Will the Minister of RURAL DEVELOPMENT be pleased to state:
(a) the total number of rural roads constructed and upgraded under
the Pradhan Mantri Gram Sadak Yojana (PMGSY) in Tamil Nadu
during the last three years, including the number of villages
connected to all-weather roads;
(b) the funds allocated and utilized for the implementation of
PMGSY during the last three years in Tamil Nadu, including the
status of ongoing projects;
(c) whether the Government has introduced any innovations or new
technologies in road construction under the Pradhan Mantri
Gram Sadak Yojana (PMGSY) to ensure better durability, cost-
effectiveness and environmental sustainability, if so, the details
thereof;
(d) the steps taken to improve maintenance of roads constructed
under PMGSY to ensure long-term usability and prevent road
deterioration in rural areas; and
(e) whether the Government is considering any expansion or reform
to the PMGSY, if so, the details thereof?
ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI KAMLESH PASWAN)
(a): The unit of connectivity under the Pradhan Mantri Gram Sadak
Yojana (PMGSY) is a habitation rather than a revenue village.
Accordingly, data regarding village-wise connectivity is not
maintained under the scheme. As on 19.03.2026, all-weather road
connectivity under PMGSY-I has been sanctioned for a total of 1,985
habitations in the state of Tamil Nadu. Out of these, all 1,985
habitations (100%) have been successfully connected. Since full
connectivity has already been achieved, no additional habitations
have been connected during the last three years in Tamil Nadu.
Page 1 of 3During the last three years and current year, a total of 1167 roads of
4717 km road length & 64 Long Span Bridges (LSBs) have been
completed in the State of Tamil Nadu under PMGSY.
(b): The funds allocated and utilized for the implementation of
PMGSY during the last three years and current year in Tamil Nadu are
as below:-
(Rs. in Crore)
2022-23 2023-24 2024-25 2025-06 Total
Central share 613.70 411.36 638.66 499.78 2163.50
release/allocation
Utilized/Expenditure* 532.36 777.78 741.43 1,417.26 3,468.83
* including state share also
(c): Under PMGSY, in order to promote cost-effectiveness and new
construction technologies in the construction of rural roads,
including new materials/waste materials/ locally available materials,
Ministry of Rural Development (MoRD)/National Rural Infrastructure
Development Agency (NRIDA) had issued ‘Guidelines on Technology
Initiatives', in May 2013. In order to promote innovations/latest
technologies on large scale for wider adoption of new/ green
technology in rural roads in a much systematic manner, MoRD/ NRIDA
has revised the above guidelines and brought “Vision Document on
New Technology Initiatives & Guidelines-2022. Under PMGSY, around
1,76,327 km of roads works has been sanctioned using new/green
technology out of which 1,32,914 km has been completed till date.
(d): Under PMGSY, maintenance of rural roads is the responsibility
of the State/UT. The Ministry had issued guidelines for maintenance
of roads constructed under the programme. Under PMGSY, roads are
covered under a 5-year maintenance contract to be entered into
along with a construction contract with the same contractor as per
the Standard Bidding Document (SBD). Since the design life of PMGSY
roads is ten years, the States have to undertake further five years of
maintenance. A MoU has been signed with States/UTs to emphasize
on maintenance of roads constructed under PMGSY. The Ministry has
also implemented e-MARG i.e. software module for maintenance
payments to the contractor during the defect liability period. The post
five-year construction module of eMARG incorporates initial
rehabilitation, renewal, pre-renewal routine maintenance, post-
renewal maintenance and emergency repair works, as required.
Maintenance funds to service the contract are required to be
budgeted by the State Governments and placed at the disposal of the
State Rural Roads Development Agencies (SRRDAs) in a separate
Page 2 of 3maintenance account. On expiry of this 5 year post construction
maintenance, PMGSY roads are required to be placed under Zonal
maintenance contracts consisting of 5 year maintenance including
renewal as per cycle, from time to time.
(e): Pradhan Mantri Gram Sadak Yojana-IV (PMGSY-IV) has been
launched in 2024 for construction of 62,500 km of all-weather roads
(single lane) to provide connectivity to about 25,000 unconnected
rural habitations of population size 500+ in plains, 250+ in North East
& Hill States/UTs, special category areas (Tribal Schedule V,
Aspirational Districts/ Blocks, Desert areas) and 100+ in Left Wing
Extremism (LWE) affected districts, as per Census 2011. All
States/UTs have conducted a fresh survey to identify eligible
habitations through the Gram Sadak Survey app under PMGSY-IV,
which is specifically designed for transparency and accuracy. The
Ministry has started sanctioning projects under PMSY-IV and is
closely working with States/UTs for the timely sanctioning of
targeted road projects under PMGSY-IV. As on date, the habitation
coverage, number of roads/LSBs and length sanctioned under
PMGSY-IV is given below.
S.No. State/UT Sanctioned
PMGSY-IV
No. of Road Length No. of No. of
Roads (km) Bridges Habitations
1 Chhattisgarh 774 2,426.875 0 780
2 Himachal 294 1,538.058 0 429
Pradesh
3 Jammu & 316 1,781.334 0 429
Kashmir
4 Rajasthan 1,216 3,218.971 1 1216
5 Sikkim 96 384.267 0 107
6 Uttarakhand 184 1,228.198 0 780
7 Assam 758 1522.273 62 828
Total 3638 12,099.98 63 4569
*****
Page 3 of 3