GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6373
ANSWERED ON 2nd APRIL, 2026
INADEQUATE MAINTENANCE OF NHs
†6373. DR. SAMBIT PATRA:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मंत्री
be pleased to state:
(a) whether the Government has received complaints regarding the
lack of quality construction by contractors on certain sections of
National Highways (NHs) across the country;
(b) if so, the details of the action taken against the erring contractors
thereof;
(c) whether the Government has received complaints regarding
inadequate and improper maintenance of NHs by the concessionaires
after construction in the State of Odisha during the last five years;
(d) if so, the details of the complaints received and the action taken
thereon;
(e) the details of the remedial measures taken at the national level to
ensure quality construction and maintenance of National Highways;
and
(f) whether any amendment has been made in the policy to penalize
erring contractors and incentivize those performing exceptionally and
if so, the details thereof?
1ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (f) As per information provided by the executing agencies of the
National Highways (NHs), major deficiencies/ damages in NH stretches
have been reported for 67 projects / stretches in the last three years
and current year. State / Union Territory (UT) – wise details of major
deficiencies/ damages on NH stretches including NHs in the State of
Odisha observed in the last three years and current year along with
status of its rectification works and action taken against contractors,
concessionaires, consultants etc. are placed at Annexure-I. Actions
against defaulting agencies have been taken up as per the provisions
of the Contract/ Concession agreement in cases of deficiencies/
damages, such as termination of contract agreement, levying of
penalties/ liquidated damages, debarment/ blacklisting, declaring as
non-performers etc.
Action taken against Contractors/ Concessionaires for non-
compliance of maintenance obligations in NH works in the State of
Odisha in the last 5 years and current year is placed at Annexure-II.
Development and maintenance of NHs is a continuous process.
All efforts are made to ensure that the NHs are constructed as per
stipulated quality standards specified in the Indian Roads Congress
(IRC) specifications and codes. To ensure that highway construction
adheres to stipulated quality standards, Consultants (Authority’s
Engineer/ Independent Engineers- AE/IE) are appointed by the
executing agencies for day-to-day supervision of works at site.
Officials of executing agencies undertake inspections from time to
time and ensure adherence of conformity of quality of the work done
by the Concessionaire/ Contractors with stipulated requirements.
2NHs development projects are executed on mainly three modes
i.e. (i) Build Operate and Transfer (BOT), (ii) Hybrid Annuity Model
(HAM) and (iii) Engineering Procurement and Construction (EPC), for
which design and maintenance responsibilities as per project scope is
vested with the Contractor/ Concessionaire.
The Government has prioritized the maintenance of existing NHs
network and inter-alia evolved a mechanism to ensure Maintenance
and Repair (M&R) of all NHs sections through accountable
maintenance agency. Concession period including maintenance for
projects on BOT is 15 to 20 years and on HAM is generally 15 years.
Concessionaire is responsible for maintenance of the respective NHs
stretches within the concession period of the project. Only in case of
EPC projects, Defect Liability Period (DLP) is 5 years for the
bituminous pavement works and 10 years for concrete pavement
works. For Toll-Operate-Transfer (TOT) and InvIT (Infrastructure
Investment Trust) projects, concession period including maintenance
is 20 to 30 years. Concession period for Projects on Operate, Maintain
and Transfer (OMT) is generally 9 years.
For all remaining sections of NHs stretches, where DLP has
ended or is not under any concession period of BOT/HAM/TOT/InvIT
project, Government has taken a policy decision to undertake
maintenance works through Performance Based Maintenance Contract
(PBMC) or Short Term Maintenance Contract (STMC). While STMC
works are generally undertaken for a contract period of 1-2 year,
PBMC works are undertaken for a contract period of about 5-7 years.
Remedial work to repair or reconstruct damages during
construction or in the Defect Liability Period (DLP)/ Concession period
is the responsibility of the Contractor/ Concessionaire at their own
cost as per provisions of contract agreement except in those cases
where the Contract Agreement has been terminated in which case the
securities provided are forfeited.
3The Government has additionally taken the following
initiatives for improvement of quality control systems in
implementation of NHs works: -
i. Adoption of Automated & Intelligent /Machine-aided Construction
(AI-MC) in NH projects;
ii. Assessments of road conditions through Network Survey
Vehicle (NSV) mandated for all NHs and Expressway works at the time
of completion and every six months thereafter, which is monitored
through electronic platform. NSV system for road condition
assessment has been revamped using analytics for enforcement of
contractual provisions during Operation and Maintenance (O&M)
through dedicated central cell;
iii. Operationalization of a centralized system called NHAI One
App for Monitoring and rectification of highway defects which enables
geo-tagging of defects along with photographs;
iv. Analysis of High-Resolution Imagery collected from Drone
Surveys in Drone Analytics Monitoring System (DAMS) integrated with
Artificial Intelligence/ Machine Learning algorithms for periodic
evaluation of progress and quality of ongoing NHs works from time to
time;
v. Deployment of Mobile Quality Control Vans (MQCVs)
equipped with Non-Destructive Testing Equipment on pilot basis in
four States, namely in Gujarat, Rajasthan, Odisha and Karnataka, for
diagnostic assessment of overall health and quality of works from time
to time during project implementation phases;
vi. Deployment of Third-Party Quality Auditors for independent
quality audits of NH works on a case-to-case basis;
vii. Action initiated for Contractor/Concessionaire Rating
System for NH projects aimed at creating transparent mechanism for
evaluating performance of contractors/ concessionaires based on key
parameters, such as, timely completion, Quality of work, Maintenance
performance, Safety compliance, Dispute management,
Subcontracting practices etc.
4ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PART (a) TO (f) OF LOK
SABHA UNSTARRED QUESTION NO. 6373 ANSWERED ON 2nd APRIL,
2026 ASKED BY DR. SAMBIT PATRA REGARDING INADEQUATE
MAINTENANCE OF NHs
State / Union Territory (UT) – wise details of collapses / major
deficiencies/ surface defects on NHs along with reasons for defect/
collapse, status of its rectification works and action taken against
contractors, concessionaires, consultants etc. during the last three
years and current year:
S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Permanent solution to
Slip Zones on Papu –
Yupia – Hoj – Potin
section of NH-713A &
Rectification of
NH-13 at Km 31.000
defective work initiated
(Hoj Market), Km
Arunachal by the Contractor.
1 38.300 (Yabi Village), 2024 RE wall Collapsed
Pradesh Penalty of 5% of
Km 39.000 (Waterfall),
contract value imposed
Km 39.700 (Appa
on Contractor.
Crusher) and Km
40.300 (Crusher Point)
in the state of
Arunachal Pradesh
Six-laning of Concessionaire
Vijayawada bypass commenced the
from Chinna Autupalli rectification work based
(Design Ch.0+000) to
Defects in the on recommendation
Andhra
2 Gollapudi (Design Ch. 2024 construction of RE /suggestion of RE wall
Pradesh
30+000) in Vijayawada wall. Expert.
– Gundugolanu Section Rs.10,99,235/- was
of NH-16 in the State recovered as damages
of Andhra Pradesh from Concessionaire.
under Bharatmala
5S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Pariyojana on Hybrid
Annuity Mode
6 laning of existing 4-
lane road from
Kalaparru (Design Km
1050.680) to Chinna
Avutupalli (Design Km
1076.480) of NH-5
including 6-lane Contractor rectified
Hanuman Junction defects at his own cost.
Bypass from (Existing Defects in the
3 Km 1055.680 to Km 2025 construction of RE Show-cause notices
1060.800) (Design wall. issued to Contractor as
Ch.0.000 to Ch.6.720) per Contractual
(Total Design Length: provisions.
27.40 Km) in the State
of Andhra Pradesh
under NHDP Phase-V
under Bharatmala
Pariyojana on EPC
Mode (Package-2)
Four Laning of
Simaria-Khagaria
Section of NH-31 from
Km. 206.050 to Km. Issues reported by
Repair works taken up
266.282 (Design CRRI in quality of
by Contractor as
Bihar 4 Chainage) and 2023 Concrete of
recommended in CRRI
(Existing Chainage superstructure in
report
Km. 209.945 to Km. bridge at Km 264.946
270.000 of NH-31) in
the State of Bihar on
EPC Mode
6S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Varanasi - Mohania
(GTRIP/5; Package -
IV A): 4L of existing Major deficiencies in Damages of INR 25 Cr
5 2023
2L section from km. 65 structural elements imposed on Contractor
to km. 317 of NH-2 in
UP and Bihar on NH-2
Project Manager &
Bridge Engineer of the
Falling of concrete Concessionaire were
Chhapra-Hajipur
from the deck slab of suspended.
Section of NH-19
Major Bridge at km Reconstruction
6 (New NH-31) 2023 145+280 and Falling
completed by
of Concrete from the
concessionaire at their
Deck Slab of ROB at
own cost.
Ch 157+860.
Umagaon-Saharsa
PKG-IV Chief Project Manager
& Engineer (Launching)
7 (Kosi Bridge & 2024 A girder collapsed of Contractor suspended.
approach Road)
during construction.
4-Laning of Simga-
Sargaon Section of
Cracks in Cement Rectifications initiated at
8 NH-200 (New NH- 2024
Concrete Panels cost of EPC Contractor.
130) from Km 48+580
to Km 91+026
Rehabilitation &
Upgradation 2-lane
Chhattisgarh
with paved shoulders
The work is in Defect
configuration of
Damage in slab of Liability Period and
9 Bilaspur Urdawal 2025
Minor bridge taken up by Contractor
section in km 241.553
at his own cost.
to 312.60 = 71.0476
km (Masanialala to
Rengapali) on NH 200
(New NH 49)
7S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
(Package-III)(Borai
river MNB at km
217.358)
Some portion of deck Arbitration notice issued
slab fallen down with to Contractor for
Flyover and underpass
settlement of the recovery of damages.
10 at Hero Honda Chowk 2024
bituminous surface Process of Rectification
NH 48
(MCW-01) on RHS and repair works
at Ch. 36+350 initiated.
Authority has imposed
damages amounting to
Rs.48,61,243/- on the
contractor for delayed
maintenance.
Delhi-Vadodara Rectification of rutting
11 2024 Rutting
Expressway Pkg. 2 has been taken up by
Contractor and majority
Haryana
of the rutted portion has
been rectified.
Authority has imposed
damages amounting to
Rs. 42,95,049/- on the
contractor for delayed
Delhi-Vadodara maintenance.
12 2024 Rutting
Expressway Pkg. 3 Rectification of rutting
has been taken up by
Contractor and majority
of the rutted portion has
been rectified.
Ruts, cracks and Penalty of ₹2.8 crore
Sanchore-Santalpur surface deformation/ has been imposed on the
Gujarat 13 2025
Package-4 Distress was Contractor along with a
observed recently recommendation for
after rains in June debarment up to one
8S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
month 2025, severe year or until successful
rutting at some rectification, whichever
locations. is later. Contractor has
taken up repair/
restoration works. The
Project Director of
NHAI was suspended.
Four Laning of
Mahulia-Baharagora-
JH/WB Border Section
of NH- 33 (from
Km.277+ 500 to
Km.333+500) & NH-
Cracked PQC panels, Rs. 1.55 Cr penalty
Jharkhand 14 06 (from Km.199+200 2024
Potholes imposed on Contractor.
to Km.183+587)
(Length of 71.61Km)
in the State of
Jharkhand on EPC
Pattern under NHDP
Phase –III.
Concessionaire has
Two/Four Laning of Km 337+670 to taken up repair/
BRT Tiger Reserve Km337+680 RE restoration works as per
15 2025
Boundary to Bengalore Block of length 10 recommendation of
Section of NH-948 mts collapsed report submitted by IISC
Bangalore.
Karnataka
Four laning of Goa- 2024 Incident of collapse
Karnataka Border to of three spans of
Kundapur section of Kaali Bridge.
Contractor debarred for
16 NH-66 (formerly NH- Inadequate slope
1 month on Aug 2024.
17) from Km. 93.700 stability works.
to Km. 283.300 in the
State of Karnataka
Kerala NH Connectivity to Distress in pile Penalty of Rs. 30.74 Cr
17 2025 foundation was was imposed on
ICTT at Vallarpdam
observed at Bridge Contractor
from Kalamassery to
no. 07 & 08 Ch.
9S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Vallarpadam NH 966A 7+960 and Ch. 9+067
(BHS)
Damages in the pile
foundation Ch.
398+400 and
398+989 (RHS)
Sub-standard work
Concessionaire debarred
(Minor Bridge works,
Kodugallur to for 1 year. Rectification
18 2025 backfill material for
Edappally NH 66 works taken up at cost of
RS Wall, Poor safety
contractor.
precautions, delayed
grouting of girders,
bulging of bearing)
or poor quality
(Defective RE
Panels)
Authority has suspended
the Concessionaire and
its promoter from future
Soil nailing collapsed
Chengala- bidding for 01-month
incident occurred at
19 Neeleshwaram Section 2025 period. Debarment also
Ch. 58+035 to Ch.
of NH-66 issued to
58+100 (RHS) on
Concessionaire. Senior
16.06.2025 with no
Bridge Engineer of AE
casualties.
removed from site.
Rectification work
Unprotected soil slip
carried out and traffic
Neeleshwaram- in the cut section
restored with
20 Thaliparambha Section 2025 with debris
precautionary
of NH-66 deposition on
barricading in median
carriageways.
portion.
NHAI - Six laning Debarment of Contractor
from start of and Independent
21 RE wall collapsed
Valanchery bypass to Engineering firm from
2025
Kappirikkad section of participating in
NH – 66 (old NH-17) ongoing/future bidding
10S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
from Design Ch. for 01 month period or
298+500 (Ex. km completion of
304.250) to Design investigation by the
Chainage 335+850 expert Committee
(Ex. km 349.260) in whichever is later.
the state of Kerala on
Hybrid Annuity Mode
under Bharatmala
Pariyojana
Penalty of Rs. 15.35
Collapse of 4 PSC Lakhs imposed. Bridge
22 Thuravoor-paravoor 2025 Girders during Engineer & Team
constructions Leader of AE were
Terminated.
Six Laning of Start of Failure/Collapse of
Kollam Bypass to scaffolding of Minor
Penalty of Rs. 9.55 lakhs
Kadambattukonam Bridge (under
23 2025 imposed on
from Km.486+000 to construction) at
Concessionaire
Km.517+800 of NH-47 Km.Ch.
(New NH-66) in the 497+370(RHS)
State of Kerala on
Hybrid Annuity Mode Failure of RE Wall
Rectification initiated by
24 under 2025 Ch. 504+400 to
Concessionaire.
BharatmalaPariyojna 504+500(LHS)
Toppling of two PSC
girders at span P-
6L Elevated Corridor 202-P-203
along with
development of
Contractor and AE
existing 4 lane road at Failure on part of AE
25 2025 debarred from future
ground level from to review efficacy of
bidding for 1 month.
Aroor to Thuravoor material being used
Thekku section of NH in launching and not
66 ensuring application
of approved
launching scheme.
11S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Soil nailing collapse
Rectification initiated by
26 Azhiyur-Vengalam 2024 At Km:191(LHS) and
Concessionaire.
Km:193(RHS
Rectification works
Ramanattukara-
27 2025 Defects in RE wall initiated by Contractor at
Valanchery
his own cost.
Damaged portion
Retaining wall
dismantled and
Thaliparamba- sliding and defects in
28 2026 rectification works
Muzhapilangadu ground improvement
initiated by
works.
Concessionaire.
Penalty of Rs. 119 Cr
4-laning of Bhopal- imposed on Contractor.
Madhya Premature failure of
29 Bioara section of NH- 2025 Rectification work
Pradesh pavement.
46 initiated at the cost of
Contractor.
Balance work for 4-
Panel cracking, poor
laning of Panvel to
riding quality, Contractor has taken up
30 Indapur section from 2024
bumps, poor rectification works.
km.0.0 to km.42.3 of
diversions etc.
NH-66 - EPC
The Performance BG of
Contractor is forfeited.
31 Mehkar-Ajispur Road 2024 Cracked panels
Process initiated for
Maharashtra rectification of damages.
Contractor has initiated
32 Bhokar-Sarsam 2024 Cracked panels actions for rectification
of damages.
Contractor has initiated
33 Sillod-Fardapur 2024 Cracked panels actions for rectification
of damages.
12S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Rehabilitation and
upgradation & NH-66
(Erstwhile NH-17)
form km 241+300 to
281+300 (Arawali to Contractor has initiated
Depression & cracks
34 Kante Section) to four actions for rectification
in PQC
lane with paved 2025 of damages.
shoulder in the state of
Maharashtra under
NHDP-IV on Hybrid
Annuity Mode.
Rehabilitation &
Upgradation of NH-66
(Old NH17) from Km
281+300 to Km
332+200 (Kante to PQC cracks and Contractor has replaced
35 2024
Waked section) to four settlement. cracked panels.
lanes in the state of
Maharashtra under
NHDP-IV on Hybrid
Annuity Mode.
Rehabilitation and up-
gradation of NH-66
(Old NH-17) form km
332/200 to km 367/200
Contractor has initiated
(Watul to Talgaon Full depth Cracks in
36 2024 actions for rectification
Section) to four lanes PQC
of damages.
in the State of
Maharashtra under
NHDP-IV on EPC
Mode.
13S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Rehabilitatyion & up
gradation for Talere
Gaganbawada
Kolhapur Road (NH-
166G) stretches start
from Ch. 6/00 Km. to
Ch. 11/00 Km. and Ch.
19/300 Km. (Start of Contractor has initiated
37 Karul Ghat) to 35/300 2025 Cracks in PQC actions for rectification
Km. (End of of damages.
Gaganbawada) of NH-
166G to 2 lane paved
shoulder/2 lane
configuration lane,
length 21.00 Km. in the
state of Mahrashtra on
EPC Mode.
Rehabilitation and Up-
gradation to Two lanes
with paved shoulder
Rectification of damages
from Karad to Tasgaon
38 2024 Cracked panels taken up at risk and cost
NH 266 from Km. 0/00
of Contractor.
to 58/830 in the State
of Maharashtra on EPC
mode
Upgradation to two Post
lane with paved construction defects
shoulder are observed in the
IIT Bombay has been
from Salaikhurd Rigid Pavement i.e.
appointed for Technical
to Tiroda Km 120/100 formation of
39 2024 Investigation of defects
to 163/200 (Design Longitudinal &
and suggestion of
Km 44/00 to Lateral cracks,
remedial measures.
87/00) of NH 753 on Opening of Central
EPC Mode in the state Joints, Settlement of
of Maharashtra Panels etc.
Rutting, Raincuts, Penalty imposed on each
Rajasthan 40 Delhi Vadodara 2024
potholes & settlement contractor amounting to
Expressway NE-4
Rs. 50 Lakhs for non-
14S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Pkg.06 rectification of defects in
the stipulated time frame
as per provision of
contract agreement.
Delhi Vadodara
41 Expressway NE-4 2024
Pkg.07
Delhi Vadodara
42 Expressway NE-4 2024
Pkg.08
Delhi Vadodara
43 Expressway NE-4 2024
Pkg.09
Construction of 6-lane
access-controlled
Greenfield highway
from km 28+70 to Km.
(i) Damage of Rs. 50.00
53+0 of Sangariya
Lakhs imposed upon the
(near Chautala)-Rasisar Deficiencies in riding
Contractor.
(near Bikaner) section quality and
44 2024 (ii) Two key personnel
of NH-754K as a part settlement at some
of Authority Engineer
of Amritsar-Jamnagar locations observed
team were terminated
Economic Corridor in
due to poor supervision.
the State of Rajasthan
under Bharatmala
Pariyojana -Phase-I
(AJ/SR-Package-2)
Penalty of Rs. 1.00 Cr.
Construction of 6-lane
imposed and warning for
access controlled
Failure of the nose debarment action for any
Greenfield highway
structure while future instances upon the
from km 53+000 to
45 2024 launching of 83 mtr Contractor was issued.
Km.
single span truss
88+000 of Sangariya
Debarment of
bridge
(near Chautala)-Rasisar
fabrication team and
(near Bikaner) section
Designer team issued for
of NH-754K as a part
the period of 02 years in
15S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
of Amritsar-Jamnagar NHAI works.
Economic Corridor in
Penalty of Rs. 20 Lakhs
the State of Rajasthan
and warning for
under Bharatmala
debarment action for any
Pariyojana-Phase-I
future instances upon the
(AJ/SR-Package-3)
Authority Engineer.
Debarment of Senior
bridge Engineer
deployed by the
Authority Engineer
issued for a period of 2
years in NHAI works.
Damages amounting to
Rs. 1.06 Cr. imposed for
delayed maintenance.
Delhi-Vadodara Rutting & settlement Also, IIT Kharagpur has
46 2024
Expressway Pkg. 4 of approach been engaged for
detailed study for
permanent rectification
of defects.
Damages amounting to
Rs. 88.32 lakhs imposed
for delayed
maintenance. Bulging of
RE wall has been
rectified as per
Rutting, settlement of suggestions of CRRI.
Delhi-Vadodara
47 2024 approach & bulging Majority of the rutting
Expressway Pkg. 5
of RE wall has been rectified.
Further, in addition to
above, IIT Kharagpur
has been engaged for
detailed study for
permanent rectification
of defects.
16S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Delhi-Vadodara
Greenfield Alignment
Stretch is operational
(NH-148N) (Pkg-16)
w.e.f. 30.11.2023 and
(Ch. 427.300 to
at some locations the EPC Contractor has
48 Ch.452.420) [Major 2024
settlements observed rectified damages. R
bridge over Takli river
in approaches of
near Nayagaon Jageer
structure
village to
Rajasthan/MP Border]
Construction of
Post-completion,
proposed 2-lane ROB
structural defects
and its approaches in Contract has been
have been observed
lieu of existing level terminated. Debarment
in the deck slab of
49 crossing no. C-64 at 2024 of contractor taken up.
the ROB due to
km. 172.990 on Bid for rectification
honeycombing
Jodhpur–Ajmer Road works invited.
caused by poor
on NH-65 in District
workmanship.
Nagaur Rajasthan
The RE wall blocks
4-laning of
portion of the A2
Sethiyathope -
(Thanjavur) side
50 Cholpauram section 2025 approach (LHS side) The rectification work
from Km 65.960 to Km have been completed by the
116.440 disconnected from Concessionaire at their
the geo grid and own cost.
fallen down.
The RE wall panel
portion of the A1
4-laning of Thanjavur - (Thanjavur) side
Based on report of
Trichy section from approach (LHS side)
51 2023 Expert Committee,
Km 80.000 to Km have been
restoration work using
136.490 disconnected from
soil nailing completed
the geo grid and
by Contractor.
fallen down.
17S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Construction of 4 lane
green field highway The project is under
Cracks observed over
from km 35.00 to construction, the repair
DBM due to
49.155 of NH-731A and rectification work
52 2025 percolation of rain
with paved shoulder on taken up by the
water in some
Uttar Hybrid Annuity Mode concessionaire at its own
stretches.
Pradesh in the State of Uttar cost.
Pradesh.
Cracks in PQC Panel Contractor has initiated
Lucknow Ring Road
53 2024 in length of 2.886 process for rectification
Pkg-3A
Km. of damages.
Uttar Contractor has initiated
4L of Haridwar-Nagina
Pradesh & 54 2023 PQC panel cracks process for rectification
section of NH-74
Uttarakhand of damages.
Construction,
Operation and
Maintenance of 2-Lane
Bi- Directional Rectification measures
Silkyara Bend Barkot taken up by the EPC
Tunnel with escape contractors at its own
passage including Collapse at cavity in cost.
Uttarakhand 55 approaches on 2023 under construction
Dharasu–Yamunotri Silkyara Tunnel.
section between Ch. Actions as per the
25.400 Km and Ch. Investigation Committee
51.000 Km falling Report initiated.
along NH-134 (OLD
NH-94) in the state of
Uttarakhand
i) Rectification works
Construction of 4-
initiated by Contractor.
Laning of Puruliya Cracks have
Amount of Rs. 20.00
Bypass Section from developed in the
West Bengal 56 2025 Lakh withheld from
Km. 84.030 to Km. newly constructed
Contractor's bill.
94.345 of NH-32 PQC.
(length 10.315 Km) in
ii) Key personal of AE
the State of West
has been debarred for a
18S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Bengal on EPC Mode period of one year.
Four laning with paved
shoulders of NH-6
from Chichra to
Kharagpur Km
185.150 to Km Rectification works
Cracks in PQC
57 134.400 including 2023 completed at cost of
panels
rehabilitation of EPC Contractor.
existing four lane from
Km 134.400 to Km
129.600 in the state of
West Bengal
Failure of membrane
pad of Pot – PTFE
bearing on P2 of
Ahiron Bridge (Ch.
257+440 LHS MJB-
truss). Also, a level Rs. 26.19 lacs penalty
Four laning of
difference up to imposed on
Berhampore – Farakka
58 2024 90mm had been Concessionaire.
Section of NH-12 (old
observed between Rectification work
NH-34)
expansion joint of completed.
deck-I and deck-II
along with missing of
some anchoring bolts
of connecting gusset
plates.
Four laning of Farakka Crack at the bottom
– Raiganj Section of of the deck slab at
Rectification work
NH-12 (old NH-34) km 325+060 of the
59 2024 initiated by
Mahananda Bridge
Concessionaire.
(LHS). The crack
was located under the
fast lane between
19S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
span P1 & P2 (PSC
Girder).
At RHS Pier 4 of
MJB at 325+223,
piles are exposed and
heavy reinforcement
were exposed.
Exposed
reinforcement were
corroded.
Four laning of Rectification initiated by
Rutting, Potholes,
60 Berhampore – Farakka 2025 Concessionaire at his
Cracks
Section of NH-12 (old own cost.
NH-34)
Six Laning of National
Corridor NH-19 from
Palsit to Dankuni (up
to NH-6 Connector) Toll has been suspended.
from km 588.870 to 2 key personnel of IE
61 2026 Collapse of RE Wall
km 652.700 in the state and Concessionaire
of West Bengal under suspended.
Bharatmala Pariyojana
to be executed on BOT
(Toll) basis.
1. Faulty Design in 1. For Faulty Design at
Bridge at km. Km 96+326, penalty
96+326: imposed of Rs.30 Lakhs
on the Concessionaire
Chandikhole-Bhadrak and Rs.5 Lakhs on the
Odisha 62 2023
Section of NH-16 2. Bridge at km. Independent Engineer.
79+614: Team Leader of IE and
Key Personnel of
The span A1-P1 had
Concessionaire
dislodged from the
suspended.
pier P2 due to
20S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
breaking of the
cantilever
2. For Bridge at km.
Portion of the pier 79+614:
cap and had fallen on
Penalty of Rs.5 crore
the ground.
imposed on the
Contractor and Penalty
of Rs.20 lakh imposed
Appearance of wide
on the Supervision
cracks (up to 3-4mm)
Consultant.
in the pier cap on
grid “P2”.
Debarment of DPR
Consultant for 1 year.
Damages of deck
slab and girders of
the dislodged span.
The cost of entire
remedial measures /
reconstruction recovered
from the
Concessionaire.
Construction of 6-lane
Standalone Flyovers at
Bongaigaon,
Chapaguri, Pathsala,
Falling of one PSC
Simlaguri Chowk and
Girder at Baihata Penalty imposed on
Baihata Junctions on
Assam 63 2024 Flyover (Span P1- Contractor. Contractor
stretches of NH-31 &
P2), resulting in the debarred for 4 months.
NH-31C [new NH-27
death of one person.
(EW)] in the State of
Assam under
Bharatmala Pariyojana
on EPC basis
21S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
Two Lane with paved
shoulders configuration
Penalty of Rs.
in Jowai-Meghalaya
Slippage of 20,00,000/- imposed on
Assam Border Section
Bituminous concrete Contractor and
of NH - 44 from Km
Meghalaya 64 2025 for a length of rectification work
69.200 to Km 173.200
approximate 10-15 carried out by
(design Ch 171.455 ) in
mtrs Contractor at his own
the state of Meghalaya
cost.
Construction of
Dwarka Expressway
Package-1, from Shiv
Murti Intersection at P8-P9 of flyover part
Km 20 of NH-8 till of Shiv Murti Remedial measures
Delhi 65 road under Bridge 2023 interchange on completed by
(RUB) near Dwarka Dwarka Expressway Contractor.
Sector-21(From Km - toppled.
0.600 to 5.300) in the
state of Delhi on EPC
mode
Rehabilitation of km
181.00 to Km 206.00
section in Andaman
Trunk Road of NH-4 to
Intermediate Lane with Distress, sinking of
Rectification works
66 hard shoulder in the 2024 pavement at various
completed.
union Territory of locations.
Andaman & Andaman & Nicobar
Nicobar islands (Total length
Islands 25.00 km) on EPC
Mode” (Package-VII)
Construction of 4 Nos. Punching in Deck The EPC contractor has
of Minor Bridges at Slab (LHS) of the carried out the necessary
67 Km 21.717, Km 2024 minor bridge across rectifications at their
23.150, Km 88.300, BD Nallah at Km own expense including
Km 92.100 of NH- 223 88+300 and other replacement of slab as
(New NH-4) quality issues recommended by CRRI-
22S. Year of Details of Major
State Name of the Project Action Taken
No. incident damages / defects
connecting South including bad CSIR report.
Andaman and Baratang workmanship.
Island in the Union
Territory of Andaman
& Nicobar Islands on
EPC mode.
23ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PART (a) TO (f) OF LOK
SABHA UNSTARRED QUESTION NO. 6373 ANSWERED ON 2nd APRIL,
2026 ASKED BY DR. SAMBIT PATRA REGARDING INADEQUATE
MAINTENANCE OF NHs
Action taken against Contractors/ Concessionaires for improper
compliance of maintenance obligations in NH works in the State of
Odisha in the last 5 years and current year:
S. Name of the Completed project/ Project under O&M/ TOT Action taken on Contractor on
No. Contract account of Improper Maintenance
of NH after completion of work/
during O&M
Penalty of Rs.1.37 Crs has been
4/6-laning of stretch from Puintola to Icchapuram section of imposed on TOT concessionaire
1
NH16 towards breach of O&M obligations
as per contract.
Completion of Balance Work Panikoili – Rimuli section of NH-Work amounting to Rs. 1.52 Cr
215 (New NH-20) from Km.0.000 to Km.163.000 (Design executed through a separate
2
Chainage Km0.000 to 166.173) in the state of Odisha in contractor on the risk & Cost of the
single percentage item rate Contract Contractor.
Work executed through separate
3 Four laning of Angul-Sambalpur Sambalpur Section of NH-55 contractor on the risk & Cost of
Contractor.
Deduction of Rs. 2 Lacs from
Four langing Sambalpur- Bargarh/Chhatishgarh Border Section Contractor’s Bill for non- functional
4
of NH-53 street light and non-compliance of
NSV Observation.
5 VUPs at Balikuda, Sikharpur and Badachana on Bhubaneswar-Work amounting to Rs. 3.78 Cr
Chandikhole Section of NH-16 executed through a separate
contractor on the risk & Cost of
Contractor.
*****
24