**Executive Summary**
This document is a response to unstarred question no. 2779 in Lok Sabha concerning the indigenous Kavach system in rail networks. It details various safety measures implemented by the Indian Railways, including the Kavach system, AI-driven predictive maintenance, and fire safety enhancements. The document highlights the reduction in consequential train accidents and accident index over the years. The targeted date to be answered was 17.12.2025.
**Key Points / Main Content**
* **Safety Measures and Accident Reduction:**
* Safety is the highest priority for Indian Railways.
* A steep decline in the number of accidents has been achieved through various safety measures.
* The number of consequential train accidents has reduced from 135 in 2014-15 to 11 in 2025-26.
* The Consequential Accident Index has decreased from 0.11 in 2014-15 to 0.03 in 2024-25.
* Expenditure on safety-related activities has increased, reaching Rs. 1,16,470 Cr in 2025-26.
* **Technological Advancements:**
* Electrical/Electronic Interlocking Systems have been provided at 6,657 stations up to 30.11.2025.
* Interlocking of Level Crossing Gates has been provided at 10,100 Level Crossing Gates up to 30.11.2025.
* Complete Track Circuiting of stations has been provided at 6,663 stations up to 30.11.2025.
* All locomotives are equipped with Vigilance Control Devices (VCD) to improve alertness of Loco Pilots.
* A GPS-based Fog Safety Device (FSD) is provided to loco pilots in fog-affected areas.
* **Kavach Implementation:**
* Kavach is an indigenously developed Automatic Train Protection (ATP) system.
* Kavach was adopted as a National ATP system in July 2020.
* Kavach Version 4.0 has been commissioned on 738 Route km on Palwal - Mathura- Nagda section and Howrah-Bardhaman section.
* Kavach implementation has been taken up on 15,512 RKm covering all GQ, GD, HDN and identified sections of Indian Railways.
* Installation of Station Kavach at each and every station, Installation of RFID Tags throughout the track length, Installation of telecom Towers throughout the section, Laying of Optical Fibre Cable along the track, and Provision of Loco Kavach on each and every Locomotive running on Indian Railways are Key Activities.
* Specialized training programs on Kavach are being conducted.
* Funds utilized on Kavach works up to Oct'25 is Rs. 2,354.36 Crores.
* **Artificial Intelligence and Predictive Maintenance:**
* Pilot initiatives involving AI-driven predictive maintenance of the Signaling system are underway.
* An AI-enabled Intrusion Detection System (IDS) is being implemented to detect elephants on railway tracks.
* IR has adopted technologies like Online Monitoring of Rolling Stock System (OMRS) and Wheel Impact Load Detector (WILD).
* **Fire Safety Enhancements:**
* Provision of minimum two Fire Extinguishers in all coaches.
* Fire Detection & Suppression Systems are provided in fire-prone areas.
* Use of fire-retardant material as per global norms in coaches.
* Fire notices are displayed in all coaches.
* **Elimination of Unmanned Level Crossings:**
* All unmanned level crossings (UMLCs) on Broad Gauge routes have been eliminated by January 2019.
**Impact Analysis**
**Stakeholder: Passengers**
* **Impact:** Enhanced safety and reduced risk of accidents due to the implementation of Kavach, improved fire safety measures, and overall safety enhancements.
* **Action Required:** Be aware of and follow fire safety guidelines and instructions provided in the coaches.
**Stakeholder: Loco Pilots**
* **Impact:** Improved alertness and safety through the Vigilance Control Devices (VCD) and Fog Safety Device (FSD). Assistance from the Kavach system for automatic braking and adherence to speed limits.
* **Action Required:** Undergo specialized training programs on Kavach and use safety devices effectively.
**Stakeholder: Indian Railways Staff**
* **Impact:** Reduced human error through centralized operation of points and signals, interlocking of level crossing gates, and complete track circuiting. Better maintenance practices and technological improvements.
* **Action Required:** Regular counselling and training to maintain safe practices. Adherence to detailed instructions on safety-related issues.
**Stakeholder: General Public/Road Users**
* **Impact:** Increased safety due to the elimination of unmanned level crossings and the provision of road over bridges/road under bridges.
* **Action Required:** Exercise caution while crossing manned level crossings and adhere to traffic regulations.
Key Entities Referenced
Kavach (Automatic Train Protection): An indigenously developed Automatic Train Protection system to enhance safety in train operations.
Ministry of Railways: The Indian government ministry responsible for the country's rail transport.
Indian Railways (IR): The state-owned railway company responsible for rail transport in India.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2779
TO BE ANSWERED ON 17.12.2025
INDIGENOUS KAVACH SYSTEM IN RAIL NETWORKS
†2779. SHRI MITESHBHAI RAMESHBHAI PATEL:
SHRI HASMUKHBHAI SOMABHAI PATEL:
Will the Minister of RAILWAYS be pleased to state:
(a) the targeted date for achieving 100 percent implementation of
the indigenously developed Kavach (Automatic Train
Protection) system across the major rail networks of the
country;
(b) the manner in which the Government is utilising Al and
predictive maintenance tools to bring down the number of
signal failures and accidents;
(c) whether the Government has adopted any new policy
mandating the use of fire retardant materials in all new
passenger coaches and if so, the details thereof; and
(d) the steps taken/being taken by the Government to expedite the
elimination of unmanned level crossings on densely populated
routes?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) Safety is accorded the highest priority on Indian Railways. As
a consequence of various safety measures taken over the
years, there has been a steep decline in the number of
accidents.
--2/--2-
Number of Consequential Train Accidents has reduced as shown in
the table below:-
Year Consequential Accidents
2014-15 135
2025-26 (till date) 11 (90% lesser)
Another important index showing improvement in safety in train
operations is Consequential Accidents Index, the details of which
are as under:-
Consequential Accident Index:
Year Accident Index
2014-15 0.11
2024-25 0.03 (73% lesser)
This index measures number of consequential accidents as a ratio
of total running Kilometers of all trains.
No. of consequential accidents
Index =
No. of trains X million kilometers run
234
165
135
55
31
11
2005-06 2009-10 2014-15 2019-20 2024-25 2025-26 …
niarT
laitneuqesnoC
fo
.oN
stnediccA-3-
The various safety measures taken to enhance safety in train
operations are as under:-
1. On Indian Railways, the expenditure on Safety related
activities has increased over the years as under:-
Expenditure/Budget on Safety related activities (Rs. in Cr.)
2013-14 2022-23 2023-24 2024-25 2025-26
(Act.) (Act.) (Act.)
39,463 87,327 1,01,651 1,14,022 1,16,470
2. Electrical/Electronic Interlocking Systems with centralized
operation of points and signals have been provided at 6,657
stations up to 30.11.2025 to reduce accidents due to human
failure.
3. Interlocking of Level Crossing (LC) Gates has been provided at
10,100 Level Crossing Gates up to 30.11.2025 for enhancing
safety at LC Gates.
4. Complete Track Circuiting of stations to enhance safety by
verification of track occupancy by electrical means has been
provided at 6,663 stations up to 30.11.2025.
5. Kavach is a highly technology intensive system, which requires
safety certification of highest order. Kavach was adopted as a
National ATP system in July 2020. Kavach is provided
progressively in phased manner. Initially, Kavach Version 3.2
was deployed on 1465 RKm of South Central Railway and 80
RKm of North Central Railway. Kavach specification Version 4.0
was approved by RDSO on 16.07.2024. After extensive and
elaborate trials, Kavach Version 4.0 has been successfully
commissioned on Palwal-Mathura-Kota- Nagda section (633Rkm)
on Delhi- Mumbai route and on Howrah-Bardhaman section
(105RKm) on Delhi-Howrah route. Kavach implementation has
been taken up in balance sections of Delhi-Mumbai and Delhi-
Howrah route. Further, Kavach implementation has been taken
up on 15,512 RKm covering all GQ, GD, HDN and identified
sections of Indian Railways.
6. Detailed instructions on issues related with safety of Signalling,
e.g. mandatory correspondence check, alteration work protocol,
--4/--4-
preparation of completion drawing, etc. have been issued.
7. System of disconnection and reconnection for S&T equipment as
per protocol has been re-emphasized.
8. All locomotives are equipped with Vigilance Control Devices
(VCD) to improve alertness of Loco Pilots.
9. Retro-reflective sigma boards are provided on the mast which is
located two OHE masts prior to the signals in electrified
territories to alert the crew about the signal ahead when
visibility is low due to foggy weather.
10. A GPS based Fog Safety Device (FSD) is provided to loco pilots in
fog affected areas which enables loco pilots to know the
distance of the approaching landmarks like signals, level
crossing gates, etc.
11. Modern track structure consisting of 60kg, 90 Ultimate Tensile
Strength (UTS) rails, Prestressed Concrete Sleeper (PSC)
Normal/Wide base sleepers with elastic fastening, fan shaped
layout turnout on PSC sleepers, Steel Channel/H-beam Sleepers
on girder bridges is used while carrying out primary track
renewals.
12. Mechanisation of track laying activity through use of track
machines like PQRS, TRT, T-28 etc. to reduce human errors.
13. Maximizing supply of 130m/260m long rail panels for increasing
progress of rail renewal and avoiding welding of joints, thereby
improving safety.
14. Ultrasonic Flaw Detection (USFD) testing of rails to detect flaws
and timely removal of defective rails.
15. Laying of longer rails, minimizing the use of Alumino Thermic
Welding and adoption of better welding technology for rails i.e.,
Flash Butt Welding.
16. Monitoring of track geometry by OMS (Oscillation Monitoring
System) and TRC (Track Recording Cars).
17. Patrolling of railway tracks to look out for weld/rail fractures.
18. The use of Thick Web Switches and Weldable CMS Crossing in
turnout renewal works.
19. Inspections at regular intervals are carried out to monitor and
educate staff for observance of safe practices.
20. Web based online monitoring system of track assets viz. Track
database and decision support system has been adopted to
--5/--5-
decide rationalized maintenance requirement and optimize
inputs.
21. Detailed instructions on issues related with safety of Track, e.g.
integrated block, corridor block, worksite safety, monsoon
precautions, etc. have been issued.
22. Preventive maintenance of railway assets (Coaches & Wagons)
is undertaken to ensure safe train operations.
23. Replacement of conventional ICF design coaches with LHB
design coaches is being done.
24. All unmanned level crossings (UMLCs) on Broad Gauge (BG)
route have been eliminated by January 2019.
25. Safety of Railway Bridges is ensured through regular inspection
of Bridges. The requirement of repair/rehabilitation of Bridges is
taken up based upon the conditions assessed during these
inspections.
26. Indian Railways has displayed Statutory “Fire Notices” for
widespread passenger information in all coaches. Fire posters
are provided in every coach so as to educate and alert
passengers regarding various Do’s and Don’ts to prevent fire.
These include messages regarding not carrying any inflammable
material, explosives, prohibition of smoking inside the coaches,
penalties etc.
27. Production Units are providing Fire detection and suppression
system in newly manufactured Power Cars and Pantry Cars, Fire
and Smoke detection system in newly manufactured coaches.
Progressive fitment of the same in existing coaches is also
underway by Zonal Railways in a phased manner.
28. Regular counselling and training of staff is undertaken.
29. Concept of Rolling Block introduced in Indian Railways (Open
Lines) General Rules vide Gazette notification dated 30.11.2023,
wherein work of integrated maintenance/ repair/replacement of
assets is planned up to 52 weeks in advance on rolling basis and
executed as per plan.
The details of the Safety related works related to better
maintenance practices, Technological improvements, better
infrastructure and rolling stock etc. undertaken by Railways are
tabulated below:-
--6/--6-
2004-05
S. 2014-15 to 2014-25 Vs.
Item to
No. 2024-25 2004-14
2013-14
Technological Improvements
1. Use of high-quality 57,450 1.43 Lakh Km More than 2
rails Km times
(60 Kg) (Km)
2. Longer Rail Panels 9,917 Km 77,522 Km Nearly 8
(260m) (Km) times
3. Electronic 837 3,691 More than 4
Interlocking Stations Stations times
(Stations)
4. Fog Pass Safety As on As on 288 times
Devices (Nos.) 31.03.14: 31.03.25:
90 Nos. 25,939 Nos.
5. Thick Web Nil 28,301 Nos.
Switches (Nos.)
Better Maintenance Practices
1. Primary Rail 32,260 49,941 Km 1.5 times
Renewal (Track Km
Km)
2. USFD (Ultra Sonic 79.43 2 Crore More than 2
Flaw detection) Lakh times
Testing of Welds
(Nos.)
3. Weld failures (Nos.) In 2013- In 2024-25: 90 %
14: 3699 370 Nos. reduction
Nos.
4. Rail fractures (Nos.) In 2013- In 2024-25: More than
14: 2548 289 Nos. 88%
Nos. reduction
Better Infrastructure and Rolling Stock
1. New Track KM 14,985 34,428 Km More than 2
added (Track Km) Km times
2. Flyovers 4,148 13,808 Nos. More than 3
(RoBs)/Underpasses Nos. times
(RUBs) (Nos.)3. Unmanned Level As on As on Removed
crossings 31.03.14: 31.03.24:Nil
(Nos.) on BG 8,948 (All
eliminated by
31.01.19)
4. Manufacture of LHB 2,337 42,677 More than
Coaches (Nos.) Nos. 18 times
Implementation of Kavach
1. Kavach is an indigenously developed Automatic Train Protection
(ATP) system. Kavach is a highly technology intensive system,
which requires safety certification of highest order (SIL-4).
2. Kavach aids the Loco Pilot in running of trains within specified
speed limits by automatic application of brakes in case Loco
Pilot fails to do so and also helps the trains to run safely during
inclement weather.
3. The first field trials on the passenger trains were started in
February 2016. Based on the experience gained and Independent
Safety Assessment of the system by Independent Safety
Assessor (ISA), three firms were approved in 2018-19, for supply
of Kavach Ver 3.2.
4. Kavach was adopted as National ATP system in July 2020.
5. Implementation of Kavach System involves following Key
Activities:
i. Installation of Station Kavach at each and every station, block
section.
ii. Installation of RFID Tags throughout the track length.
iii. Installation of telecom Towers throughout the section.
iv. Laying of Optical Fibre Cable along the track.
v. Provision of Loco Kavach on each and every Locomotive
running on Indian Railways.
6. Based on deployment of Kavach version 3.2 on 1465 RKm on
South Central Railway and experience gained, further
improvements were made. Finally, Kavach specification version
4.0 was approved by RDSO on 16.07.2024.
--8/--8-
7. Kavach version 4.0 covers all the major features required for the
diverse railway network. This is a significant milestone in safety
for Indian Railways. Within a short period, IR has developed,
tested and started deploying Automatic Train Protection System.
8. Major improvement in Version 4.0 includes increased Location
Accuracy, Improved Information of Signal Aspects in bigger
yards, Station to Station Kavach interface on OFC and Direct
Interface to existing Electronic Interlocking System. With these
improvements, Kavach Ver.4.0. is planned for large scale
deployment over Indian Railways.
9. After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 738 Route km on Palwal –
Mathura- Nagda section (633 Rkm) on Delhi – Mumbai route and
Howrah–Bardhaman section (105 Rkm) Delhi – Howrah route.
Kavach implementation has been taken up in balance sections of
Delhi – Mumbai & Delhi – Howrah corridors.
10. Progress of key items of Kavach on High density routes
including Delhi– Mumbai & Delhi– Howrah corridors are as under:
SN Item Progress
i Laying of Optical Fibre Cable 7129 Km
ii Installation of Telecom Towers 860 nos
iii Station Data Centre 767 Stns
iv Installation of Track side 5672 RKm
equipment
v Provision of Kavach on Locos 4,154
11. Further, track side Kavach implementation work has been taken
up on 15,512 RKm covering all GQ, GD, HDN and identified
sections of Indian Railways.
12. Bids have been invited for equipping another 9,069 locomotives
with Kavach version 4.0. Kavach is being provided progressively
in a phased manner in locomotives.
--9/--9-
13. Specialized training programmes on Kavach are being
conducted at centralized training institutes of Indian Railways to
impart training to all concerned officials. By now more than
40,000 technicians, operators and engineers have been trained
on Kavach technology. This includes 33,000 Loco Pilots &
Assistant Loco Pilots. Courses have been designed in
collaboration with IRISET.
14. The funds utilized on Kavach works so far up to Oct'25 is Rs.
2,354.36 Crores. The allocation of funds during the year 2025-26
is Rs. 1673.19 Crores. Requisite funds are made available as per
the progress of works.
(b): Technological improvements in Indian Railways (IR) are a
continuous process. Some of the Artificial Intelligence based
predictive maintenance applications are as follows:
i. Pilot initiatives involving AI-driven predictive maintenance of
Signalling system is being undertaken over Indian Railways at
some of the stations to evaluate its efficacy. Measurable outcome
includes Standard Failure and Prediction Logics and Alerts
mechanism to be derived from trial results at these stations.
ii. Artificial Intelligence (AI) enabled Intrusion Detection System
(IDS) using Distributed Acoustic System (DAS) for detecting
presence of elephants on Railway tracks is implemented in 141
RKms section on NF Railway and further tenders have been
awarded for 981 RKms section of Indian Railways. The system is
designed to generate alerts for loco pilots, station masters and
Control Room about the movement of elephants in proximity of
railway tracks, for taking timely preventive action.
iii. 1) IR has adopted advanced/improved technologies like Online
Monitoring of Rolling Stock System (OMRS), Wheel Impact
Load Detector (WILD) for predictive maintenance of Rolling
stock.
2) A Memorandum of Understanding has been signed between
IR and Dedicated Freight Corridor Corporation of India
Limited (DFCCIL) in July 2025 for induction of wayside
Machine Vision based Inspection System (MVIS). This is an
AI/ML driven system for detecting hanging parts or missing
components in moving trains.
--10/--10-
3) A Memorandum of Understanding has been signed between
IR and Delhi Metro Rail Corporation to induct Automatic
Wheel Profile Measurement System (AWPMS). The AWPMS
allows for automatic non-contact measurement of train
wheel profile ensuring real-time measurement of wheel
geometry and wear.
(c): The inherent design of rolling stock is done keeping in mind
various safety provisions. Further modification and up-gradation
of coaches to enhance fire safety is a continuous and ongoing
process on Indian Railways (IR). Following measures have been
taken for safety including fire safety in coaches:
i. Provision of Minimum two Fire Extinguishers in all coaches
over Indian Railways.
ii. Fire Detection & Suppression System has been provided in
fire prone areas of Power cars and Pantry cars.
iii. Fire and smoke Detection system has been provided in
coaches as per extant guidelines.
iv. Water mist type fire suppression system is being provided on
pantry cars and power cars in phased manner.
v. Provision of emergency windows in coaches for evacuation
in case of fire.
vi. Use of Fire-retardant material as per global fire-retardant
norms in coaches for seats/berths, panels, flooring,
insulation, toilets etc for improved fire safety.
vii. Use of fire retardant E-beam cable in coaches.
viii. Use of different level of protection in the form of fuses,
Miniature Circuit breaker (MCBs) and Motor protection
Circuit Breakers (MPCBs) in the electrical circuits to prevent
the damage from electrical faults/surges.
ix. Provision of Aerosol based fire suppression system in
electrical cabinets.
x. Further, up-gradation of material in line with global
standards is regularly being carried out with fitment of new
generation material in Amrit Bharat & Vande Bharat Sleeper
trains.
xi. Display of "Fire Notices" for widespread information in all
--11/--11-
coaches to inform and alert passengers regarding various
“Do’s” and “Don’ts” to prevent fire. These include messages
regarding not to carry any inflammable material, explosives,
prohibition of smoking inside the coaches and penalties etc.
xii. Prohibition of flame based cooking in coaches.
Regular maintenance of various fire safety
equipments/components as per the prescribed periodicity
is carried out by the designated officials at Depots/Sheds
for ensuring their proper upkeep.
(d): All unmanned level crossings (UMLCs) on running lines of Broad
Guage (BG) network of Indian Railway including high density
sections have been eliminated by 2019.
Elimination of manned level crossings (MLCs) is a continuous
and dynamic process of Indian Railway. Such works are taken
up on the basis of its impact on safety in train operations,
mobility of trains & impact for road users and feasibility etc.
MLCs are eliminated either by providing Road Over
Bridges/Road Under Bridges (ROBs/ RUBs) in lieu of LCs or
through direct closure (for low traffic LCs) or by diversion of
road traffic to nearby ROB/RUB/LC depending upon the site
conditions.
Nos. of ROBs/ RUBs constructed on Indian Railways during the
period 2004-14 vis a vis 2014-25 (Oct’25) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-25 13,653 Nos.
(Oct’25)
*****