GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
STARRED QUESTION NO. 277
TO BE ANSWERED ON 11.03.2026
INFRASTRUCTURE DEVELOPMENT IN KATIHAR RAILWAY DIVISION
†*277. SHRI TARIQ ANWAR:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware that Katihar Division of Northeast
Frontier Railway (NFR) appears to be lagging in infrastructure
development and modernisation and if so, the details thereof;
(b) the details of the budget allocated and actual expenditure made by the
Government for the said division during the last five years along with
the project completion rate in comparison to the national average;
(c) whether there is any specific and time-bound plan for the modernisation
of old rolling stock, improvement in signalling system and upgradation
of stations in the said Division and if so, the details thereof; and
(d) whether the Government has assessed the reported decline in rail
connectivity and passenger amenities in the said region and if so, the
details thereof including the action plan formulated to address the said
issue?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): A Statement is laid on the Table of the House.
*****
§STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF STARRED
QUESTION NO.277 TO BE ANSWERED ON 11.03.2026 IN LOK SABHA
(a) to (d): Katihar Division of Northeast Frontier Railway holds significant
strategic and operational importance. Owing to its location, the Katihar
Division handles substantial rail traffic and plays a key role in ensuring
uninterrupted connectivity in the North-Eastern region. Accordingly,
several projects have been taken up in Katihar Division for Infrastructure
upgradations.
Projects recently commissioned falling fully/partly in Katihar Division are as
under:-
S.No. Project Length (In
Km)
1. Araria – Galgalia New Line 111
2. Eklakhi – Balurghat New Line 87
3. Katihar – Jogbani – Barsoi – Radhikapur – 236
Teznarayanpur Gauge Conversion
Some of the main projects falling fully/partly in the Katihar Division which
have been taken up are as under:-
S.No. Project Length (In
Km)
1. Jogbani – Biratnagar New Line 19
Contd….2/--:2:-
2. Balurghat – Hilli New Line 29
3. Kaliaganj – Buniadpur New Line 34
4. Jalalgarh – Kishanganj New Line 51
5. Raiganj – Itahar, Gazole – Itahar, Itahar – 76
Buniadpur New Line
6. Raiganj – Dalkhola New Line 43
7. Katihar – Kumedpur & Katihar – Mukuria 64
Doubling
The status of some of the survey falling fully/partly in the Katihar Division
are as under:-
S.No. Name of the Project (Length) Status
1. Malda Town – Kumedpur 3rd & 4th Line DPR has been
(62 Km) prepared.
2. Kumedpur – Aluabari Road 3rd & 4th Line DPR has been
(129 Km) prepared.
3. Aluabari Road – New Jalpaiguri 3rd & 4th Project has been
Line (57 Km) sanctioned recently.
4. Aluabari Road – Thakurganj Doubling (20 Project has been
Km) sanctioned recently.
5. Thakurganj – Siliguri Doubling (56 Km) DPR has been
prepared.
6. Siliguri – New Jalpaiguri Doubling (7 DPR has been
Km) prepared.
Contd….3/--:3:-
North East Region Railway Budget:
Budget allocation during the last five years has increased significantly.
Budget allocation for infrastructure projects and safety works, falling
fully/partly in North Eastern Region (NER) is as under:-
Period Outlay
2009-14 ₹2,122 crore/year
2025-26 ₹10,440 crore (about 5 times)
Track Construction:
The details of constructing new track falling fully/partly in North Eastern
Region (NER) during 2009-14 and 2014-2025 is as under:-
Period New track Average commissioning of new
Commissioned tracks
2009-14 333 Km 66.6 Km/year
2014-25 1,840 Km 167.27 Km/year (about 2.5 times)
Projects sanctioned:
As on 01.04.2025, 12 Railway projects (08 New Lines, 04 Doubling), of a
total length of 777 Km, costing ₹69,342 crore falling fully/partly in North
Eastern Region (NER) have been sanctioned. The summary is as under:-
Contd….4/--:4:-
Category No. of Total Length Exp. upto
sanctioned Length Commissioned Mar’25
projects (in Km) upto Mar’25 (₹ in Cr.)
(in Km)
New Lines 08 448 113 38,078
Doubling/
04 329 165 3,598
Multitracking
Total 12 777 278 41,676
Recently completed projects:
Projects commissioned falling fully/partly in North East Region, are as
under:
S.No. Project Cost
(₹ in crore)
1 Agartala - Sabroom new line (112 Km) 3,170
2 865
Agartala - Akhaura new line (5 Km)
3 3,019
Rangiya - Murkongselek gauge conversion (510 Km)
4 1,242
Kumarghat - Agartala gauge conversion (109 Km)
5 Lumding - Badarpur - Silchar & Badarpur - Kumarghat 6,500
gauge conversion (412 Km)
6 410
Lumding - Hojai doubling (45 Km)
7 Digaru - Hojai doubling (102 Km)
1,873
8 New Bongaigaon - Agthori doubling (143 Km)
2,048
9 Bogibeel Bridge (92 Km) 5,820
Contd….5/--:5:-
Ongoing Projects:
Some of the main projects falling fully/partly in the North East Region
which have been taken up are as under:-
S.No. Name of the project Cost
(₹ In
crore)
1 Jiribam - Imphal new line (111 Km) 21,886
2 Dimapur - Kohima new line (82 Km) 15,230
3 Murkongselek - Pasighat new line (27 Km) 1,249
4 New Bongaigaon - Goalpara - Guwahati (Kamakhaya) 4,962
doubling (176 Km)
5 Saraighat Bridge doubling (7 Km) 1,474
6 Kamkhya Guwahati 3rd line (6 Km) 395
7 Lumding – Furkating doubling (140 Km) 2,124
8 Furkating – Tinsukia doubling (194 Km) 3,634
Further, during the last three years i.e. 2022-23, 2023-24, 2024-25 and the
current financial year 2025-26, 45 surveys (24 New Line, and 21 Doubling)
of total length 3,590 Km falling in Northeast Frontier Railway including
Katihar Division have been sanctioned.
Completion of Railway project/s depends on various factors which include
the following:
Contd….6/--:6:-
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site
etc.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned
authorities for expeditious land acquisition, forestry and Wildlife
clearances and for resolving other issues pertaining to projects.
Modernization of Rolling stock:
Modernization and Improvement/up-gradation of Rolling Stock to enhance
safety, convenience and comfort of passengers is a continuous and ongoing
process on Indian Railways.
The work of replacement of earlier ICF coaches with safer and more
modern LHB coaches has been taken up in a phased manner.
Technologically superior LHB coaches have better riding, improved
aesthetics and features like Lightweight design, Anti climbing, Air
Contd….7/--:7:-
suspension (Secondary) with failure indication system, stainless steel shell
and disc brake system etc.
Production of LHB coaches during 2014-25 vis-à-vis 2004-14 is as under:
Period LHB coaches manufactured
2004-14 2,337 nos.
2014-25 42,677 nos. (more than 18 times)
With a view to improve travel experience of the passengers, Indian
Railways has introduced indigenously designed and manufactured Vande
Bharat trains with modern coaches, advanced safety features and
passenger amenities. Presently, 162 Vande Bharat Chair Car services are in
operation on the Indian Railway network.
These new Vande Bharat Chair Car Trains have following features:
• Jerk Free Semi-Permanent couplers.
• Fitted with KAVACH
• Centrally controlled Automatic Plug Doors and Fully Sealed wider
gangways.
• Emergency Alarm Push buttons and Talk Back Units on all
Coaches.
• Improved fire safety – Aerosol based fire detection and suppression
system in electrical cabinets and lavatories.
• Higher acceleration with design/operating speed of 180/160 KMPH.
Contd….8/--:8:-
• Driver-Guard communication with voice recording facility & Crash
hardened memory.
• Air conditioning units provided with indigenously developed UV-C
lamp based disinfection system for deactivating 99% harmful
bacteria from conditioned air to improve the hygiene standards
inside the passenger area.
• Better Ride Comfort.
• CCTVs in all Coaches.
• For Divyangjan passengers special lavatory in the driving coaches
on each end.
• Coach condition monitoring System (CCMS) display with remote
monitoring
Further, to cater to long distance travel, IR has introduced the sleeper
variant of Vande Bharat Express. Presently, 2 Vande Bharat Sleeper
services are in operation on the Indian Railway network.
Broad Technological advancements and safety features provided in these
Vande Bharat Sleeper Trains are as below:
• Jerk-Free Semi permanent couplers and Anti Climbers.
• Fitted with KAVACH.
• Higher acceleration with design/operating speed of 180/160 KMPH.
• Crashworthy Design of Car body complying with EN standards.
• Fire barrier doors at the end of each coach for compliance of Fire
Safety standards.
Contd….9/--:9:-
• Aerosol based fire detection and suppression system in electrical
cabinets and lavatories.
• Regenerative braking system for energy efficiency.
• Air conditioning units provided with indigenously developed UV-C
lamp based disinfection system for deactivating 99% harmful
bacteria from conditioned air to improve the hygiene standards
inside the passenger area.
• Centrally controlled Automatic Plug Doors and Fully Sealed wider
gangways.
• CCTVs in all coaches.
• Emergency talk-back unit for communication between Passenger
and Train Manager/Loco Pilot in case of emergency.
• For Divyangjan passengers special lavatory in the driving coaches
on each end.
• Centralized Coach Monitoring System for better condition
monitoring of passenger amenities such as Air conditioning, Saloon
Lighting etc.
• Ergonomically designed ladder for ease of climbing on to upper
berths.
Railways have developed fully non-AC modern train named as Amrit Bharat
express. Presently, 54 services are in operation. These modern trains
comprise of 11 General Class coaches, 8 Sleeper Class coaches, 01 Pantry
car and 02 Luggage cum Divyangjan coaches.
These trains have following enhanced features and amenities:
Contd….10/--:10:-
• Better aesthetics of seat and berths with enhanced look & feel on
the lines of Vande Bharat Sleeper.
• Jerk Free Semi-Automatic Couplers.
• Improved Crashworthiness in coaches by provision of crash tube.
• Provision of CCTV system in all coaches.
• Improved designs of toilets.
• Improved design of Ladder for ease of climbing on to the berth.
• Improved LED Light fitting & Charging Sockets.
• Provision of EP assisted braking system.
• Aerosol based fire suppression system in toilets and electrical
cubicles.
• USB Type-A and Type-C mobile charging sockets.
• Emergency Talk Back system for two-way communication between
Passenger and Guard/Train Manager.
• Non-AC pantry with enhanced heating capacity.
• Fully sealed gangways with quick release mechanism for easy
attachment and detachment.
Namo Bharat Rapid Rail has been introduced to enhance the travelling
experience of suburban and regional commuters for inter-city short
distance movement by harnessing the features of Vande Bharat Trains.
Presently, 4 Namo Bharat Rapid Rail services are in operation on the Indian
Railway network.
The prominent features of Namo Bharat Rapid Rail are as follows:
Contd….11/--:11:-
• Centrally controlled Double Leaf Automatic Sliding Doors.
• CCTVs for safety and passenger surveillance.
• Modular interior with Cushioned Seats and Sealed Flexible
Gangway.
• Emergency Talk back System.
• Continuous LED lighting with Energy Efficient Lighting system.
• FRP Modular Toilets with vacuum evacuation.
• Fully Air-Conditioned trains with AC Driver cab
Improvement of signalling system:
Indian Railway is continuously modernizing current infrastructure of its
signalling system as under:
1. Electrical/Electronic Interlocking Systems with centralized operation
points and signals in place of old mechanical signalling have been
provided at 6665 stations as on 28.02.2026, out of which Electronic
Interlocking have been provided at 3870 stations.
2. Interlocking of Level Crossing Gates (LC) has been provided at 10153
Level Crossing Gates upto 28.02.2026 for enhancing safety at LC Gate.
3. Complete Track Circuiting of stations to enhance safety by verification
of track occupancy by electrical means has been provided at 6,669
stations up to 28.02.2026.
4. Axle counters for automatic clearance of Block Section, BPAC (Block
Proving Axle Counter) are provided to ensure complete arrival of train
without manual intervention before granting line clear to receive next
train and to reduce human element. These systems have been provided
on 6149 Block Sections up to 28.02.2026.
Contd….12/--:12:-
5. Automatic Block Signalling (ABS) that enhances line capacity within
existing track infrastructure has been provided at 6897 Route km upto
28.02.2026.
6. Indian Railways has gone for implementation of indigenously developed
Automatic Train Protection (ATP) system, which required safety
certification of highest order (SIL 4). Kavach has been adopted as a
National ATP system in July 2020.
After extensive and elaborate trials, Kavach Version 4.0 has been
successfully commissioned on 1452 Route Kilometres, covering the high
density Delhi-Mumbai and Delhi-Howrah routes. On the Delhi-Mumbai route
Kavach ver. 4.0 has been commissioned on Junction cabin-Palwal-Mathura-
Nagda section (667 Rkm) & Vadodara-Virar section (336 Rkm), and
Vadodara-Ahmedabad section (96 Rkm) and on the Delhi-Howrah route
Kavach ver. 4.0 has been commissioned on Gaya Sarmatanr section (93
Rkm) and Chota Ambana-Bardhaman-Howrah section (260 Rkm).
Further, track side Kavach implementation work has been taken up on
24,427 RKM covering all GQ, GD, HDN and identified sections of Indian
Railways.
Amrit Bharat Stations:
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their implementation
in phases to improve the stations. The master planning includes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Contd….13/--:13:-
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water booths
Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like ‘One Station
One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1337 stations have been identified for development under Amrit
Bharat Station Scheme, out of which 20 stations (Aluabari Road, Arariya
Court, Balurghat, Barsoi Jn, Bhaluka Road, Dalkhola, Haldibari,
Harishchandrapur, Jalpaiguri, Kaliyaganj, Katihar Jn, Kishanganj,
Kumedpur Jn, Labha, Malda Court, New Jalpaiguri Jn, Salmari, Samsi,
Siliguri Jn. And Thakurganj) of Katihar division, Northeast Frontier Railway,
are located in Bihar and West Bengal.
Contd….14/--:14:-
The names of stations identified for development under Amrit Bharat
Station Scheme in Bihar and West Bengal are as following:
State No. of Name of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi, BapudhamMotihari,
Barahiya, Barauni, Barh, Barsoi Jn, Begusarai, Bettiah,
Bhabua Road, Bhagalpur, Bhagwanpur, Bihar Sharif,
Bihiya, Bikramganj, Buxar, Chakia, Chausa, Chhapra,
Dalsingh Sarai, Darbhanga, Dauram Madhepura, Dehri
On Sone, Dholi, Dighwara, Dumraon, Durgauti, Ekma,
Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn,
Jamalpur Jn, Jamui, Janakpur Road, Jaynagar,
Jehanabad, Jhanjharpur, Kahalgaon, Karhagola Road,
Katihar Jn, Khagaria Jn, Kishanganj, Kudra, Labha,
Laheria Sarai, Lakhminia, Luckeesarai Jn, Madhubani,
Maheshkhunt, Mairwa, Mansi Jn, Masrakh, Mokama,
Motipur, Munger (Monghyr), Muzaffarpur Jn, Nabinagar
Road, Narkatiaganj Jn, Naugachia, Nawadah,
Paharpur, Patliputra, Patna Jn, Piro, Pirpainti, Rafiganj,
Raghunathpur, Rajendra Nagar Terminal (Patna),
Rajgir, Ram Dayalu Nagar, Raxaul, Sabaur, Sagauli,
Saharsa, Sahibpur Kamal, Sakri, Salauna, Salmari,
Samastipur, Sasaram, Shahpur Patoree,
Shivanarayanpur, Simri Bakhtiyarpur, Simultala,
Sitamarhi, Siwan, Sonpur Jn., Sultanganj, Supaul,
Taregna, Thakurganj, Thawe
Contd….15/--:15:-
West 101 Adra, Alipurduar Jn., Aluabari Road, Ambika kalna,
Bengal Anara, Andal Jn., Andul, Asansol Jn., Azimganj,
Bagnan, Bally, Balurghat, Bandel Jn., Bangaon Jn.,
Bankura, Barabhum, Barasat, Barddhaman,
Barrackpore, Belda, Berhampore court, Bethuadahari,
Bhaluka Road, Binnaguri, Bishnupur, Bolpur
Shantiniketan, Burnpur, Canning, Chandan nagar,
Chandpara, Chandrakona Road, Dalgaon, Dalkhola,
Dankuni, Dhulian Ganga, Dhupguri, Digha, Dinhata,
Dum Dum Jn., Falakata, Garbeta, Gede, Haldia,
Haldibari, Harishchandrapur, Hasimara, Hijli, Howrah
Jn, Jalpaiguri, Jalpaiguri Road, Jangipur Road, Jhalida,
Jhargram, Joychandi Pahar Jn, Kaliyaganj, Kalyani,
Kalyani Ghoshpara, Kamakhyaguri, Katwa Jn,
Khagraghat Road, Kharagpur Jn, Kolkata,
Krishnanagar City Jn, Kumedpur Jn, Madhukunda,
Madhyamgram, Malda Court, Malda Town, Mecheda,
Medinipur (Midnapore), Nabadwip Dham, Naihati Jn,
New Alipurduar, New Cooch Behar, New Farakka Jn,
New Jalpaiguri Jn, New Mal Jn, Ondagram, Panagarh,
Pandabeswar, Panskura Jn, Purulia Jn, Rampurhat Jn,
Ranaghat, Sainthia Jn, Salboni, Samsi, Santragachi,
Sealdah, Shalimar, Shantipur, Sheoraphuli Jn., Siliguri
Jn., Sitarampur, Siuri, Sonarpur Jn., Suisa, Tamluk,
Tarakeswar, Tulin, Uluberia
Contd….16/--:16:-
Development works at railway stations under Amrit Bharat Station Scheme
in Bihar and West Bengal have been taken up at a good pace and the works
have been completed at Anara, Barabhum, Haldia, Joychandi Pahar Jn,
Kalyani Ghoshpara, Kamakhyaguri, Panagarh, Pirpainti,Siuri, Tamluk and
Thawe.
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Bihar:
Arariya Court station: The structural work of new station building,
platform shelter at platform no. 1, approach road and boundary wall
have been completed. The works of lift, circulating area, 12 m Foot Over
Bridge and finishing work of new station building have been taken up.
Barsoi Junction station: The works of dismantling of old quarters and
shifting of utilities have been completed. The works of station building,
circulating area and 12 m Foot Over Bridge have been taken up.
Kishanganj station: The works of platform surfacing at platform no. 1&2,
drinking water taps at platform no. 1&2, improvement of circulating
area, parking at second entry, approach road and boundary wall have
been completed. The works of horticulture and 12 m Foot Over Bridge
have been taken up.
Salmari station: The works of improvement of station building,
extension and raising of platform no. 1 and platform shelter at platform
Contd….17/--:17:-
no. 1 have been completed. The works of circulating area and 3 m Foot
Over Bridge have been taken up.
Thakurganj station: The works of raising of platform no. 1, platform
surfacing at platform no. 2, platform shelter at platform no. 1 & 2 and 12
m Foot Over Bridge have been completed. The works of platform
surfacing at platform no. 1, toilet at platform no. 2, coach indication
board and train indication board have been taken up.
West Bengal:
Balurghat station: The works of improvement of station building,
portico, extension of platform, waiting room, circulating area and
approach road have been completed. The works of lift and 12 m Foot
Over Bridge have been taken up.
Haldibari station: The works of extension of platform, platform
surfacing at platform no. 1, platform shelter, improvement of waiting
room, toilet, circulating area, parking, boundary wall and 12 m Foot
Over Bridge have been completed. The works of portico have been
taken up.
Jalpaiguri station: The works of extension and platform surfacing of
platform no. 1, platform shelter, boundary wall and 12 m Foot Over
Bridge have been completed. The works of circulating area, lift and
escalator have been taken up.
Contd….18/--:18:-
New Jalpaiguri station: The works of parcel/Rail Mail Service office,
structural work of departure building up to fourth floor, arrival-01
building and arrival-02 building, podium parking-01 have been
completed. The structural work of departure building of fifth and sixth
floor, elevated road, podium parking-02, air concourse and finishing
work of arrival-01building have been taken up.
Further, development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on category
of station/condition/traffic handled etc.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport clearance
etc. The progress also gets affected due to brownfield related challenges
such as shifting of utilities (involving water/sewage lines, optical fibre
cables, gas pipe lines, power/signal cables, etc.), infringements, operation
of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines,
etc. and these factors affect the completion time.
Development / Upgradation / Modernization of stations including Amrit
Bharat Station Scheme is generally funded under Plan Head-53 ‘Customer
Amenities’. The details of allocation and expenditure under Plan Head-53
are maintained Zonal Railway-wise and not work-wise or station-wise or
state-wise.
Contd….19/--:19:-
Bihar is covered under the jurisdiction of four railway zones, namely,
Eastern Railway, Northeast Frontier Railway, North Eastern Railway and
East Central Railway. These zones have been allocated₹ 6,599 crore under
Plan Head-53 for the last four years and the current year. The expenditure
incurred under Plan Head-53 by these zones for the last four years and
current year (up to January, 2026) is ₹6,051 crore.
West Bengal is covered under the jurisdiction of four railway zones, namely,
Eastern Railway, Northeast Frontier Railway, South Eastern Railway and
Metro Railway. These zones have been allocated ₹4,458 crore under Plan
Head-53 for the last four years and the current year. The expenditure
incurred under Plan Head-53 by these zones for the last four years and
current year (up to January, 2026) is ₹4,150 crore.
*****