GOVERNMENT OF INDIA
MINISTRY OF JAL SHAKTI
DEPARTMENT OF WATER RESOURCES, RIVER DEVELOPMENT & GANGA REJUVENATION
RAJYA SABHA
UNSTARRED QUESTION NO. 1045
ANSWERED ON 09.02.2026
INTERLINKING OF RIVERS AND MAJOR IRRIGATION PROJECTS
1045 SHRI RYAGA KRISHNAIAH:
SHRI KESRIDEVSINH JHALA:
SHRI AMAR PAL MAURYA:
SHRI SHAMBHU SHARAN PATEL:
SHRI BABURAM NISHAD:
SHRI MITHLESH KUMAR:
Smt. MAMATA MOHANTA:
Will the Minister of Jal Shakti be pleased to state:
(a) the status of river interlinking projects that recorded progress or approvals during the last three years;
(b) whether milestones have been achieved in priority links such as Ken–Betwa project;
(c) whether environmental or rehabilitation issues have affected implementation schedules;
(d) if so, the details thereof;
(e) the amount of cost sharing between the Centre and States is being managed; and
(f) the projected benefits in terms of irrigation and drinking water availability?
ANSWER
THE MINISTER OF STATE FOR JAL SHAKTI
(SHRI RAJ BHUSHAN CHOUDHARY)
(a) to (f) Government of India formulated National Perspective Plan (NPP) in year, 1980 for Inter-Basin
Water Transfer and 30 Interlinking of Rivers (ILR) Projects have been identified under NPP (16 link
projects under Peninsular component and 14 link projects under Himalayan component). National Water
Development Agency (NWDA) has been entrusted with the work of ILR.
The Details of projects including the priority links, along with their projected benefits in terms of
irrigation and drinking water availability, that recorded progress or approvals during the last three years is
enclosed at Annexure.
The Ken-Betwa Link Project is the only priority link that has entered the implementation stage. It has
an estimated cost of ₹ 44,605 crore, with ₹ 39,317 crore of central support and is planned to be completed in
period of 8 years by March 2030. The Polavaram Irrigation Project (PIP), which includes the Godavari
(Polavaram)-Krishna (Vijayawada) link, has received cumulative Central Assistance of ₹ 20,658 crore.
An Environmental Impact Assessment (EIA) is undertaken for every interlinking of river project during
the preparation of FR and DPR to assess environmental and socio-economic impact. After participating
States sign implementation agreements, proposals are submitted for appraisal and consideration of central
support. A comprehensive EIA was taken up for Ken Betwa Link Project. Environmental issues have not
affected implementation schedule of this project.
The Cost-sharing arrangements between the Centre and States are not uniform and are determined
individually for each project.
***
1ANNEXURE
ANNEXURE REFERRED TO IN REPLY TO PART (a) to (f) OF UNSTARRED QUESTION
NO. 1045 TO BE ANSWERED IN RAJYA SABHA ON 09.02.2026 REGARDING
“INTERLINKING OF RIVERS AND MAJOR IRRIGATION PROJECTS”.
DETAILS OF LINK PROJECTS THAT RECORDED PROGRESS OR RECEIVED
APPROVALS DURING THE LAST THREE YEARS ALONG WITH ITS BENEFITS.
Sl. Name States Annual Domestic Hydro Year of Status
No benefitIrrigation & power comple
ed (Lakh ha) Industria (MW) tion of
l (MCM) FR/DP
R
1. Ken-Betwa link Uttar 10.62 (UP- 194 103 DPR Govt. of India has approved
Project (KBLP) Prades 2.51 MP. - MW complet the implementation of
h (UP) 8.11) (Hydro ed in KBLP in December 2021
& ) & 2018 with an estimated cost of Rs
Madhy 27MW 44605 crore (year 2020-21
a (Solar) price level) with central
Prades support of Rs 36,290 crore
h (MP) through a Special Purpose
Vehicle viz; Ken Betwa
Link Project Authority
(KBLPA). Honourable
Prime Minister has laid the
foundation stone for project
on 25.12.2024.
The project is to complete
by March 2030.
2. Godavari Telang 2.38 232 26 DPR 1. DPR for this modified
(Inchampalli) -ana complet proposal was circulated to
Krishna ed in party States in January 2024
(Nagarjunasagar) January, 2. Draft MoA for
link 2024 implementation was
3. Krishna Andhra 1.71 236 40 DPR circulated among party
(Nagarjunasagar)Prades complet states in April 2024.
- Pennar h (AP) ed in
(Somasila) link January,
2024
4. Pennar AP 0.51 43
(Somasila) - DPR
Cauvery Tamil complet
(Manimuktha) Nadu 1.14 618 ed in
link January,
Puduch 2024
-- 62
erry
5. Modified MP & Benefits as Benefits - MoA Memorandum of
Parbati- Rajasthper MoA: as per for Understanding (MoU) for
Kalisindh- an MP - 6.11 MoA: implem preparation of DPR was
Chambal link Rajasthan –MP- entation signed by both the States
4.03 (71.39 has (MP and Rajasthan) on
Total = drinking been 28.01.2024.
210.15 lakh +21.50 signed Memorandum of
ha industrial) in year Agreement (MoA) for
= 92.9 2024 implementation has been
Rajasthan signed in December 2024.
–(1744.16 DPRs of components of
drinking Rajasthan have been
+ 205.75 completed and uploaded on
industrial) e-PAMS Portal of CWC.
= 1949.91
T otal =
2043
MCM
6. Krishna Karnat 0.69 464.51 ---- DPR Completed in September 2025.
(Almatti) – aka
Pennar link
AP 1.57 10.1- ----
Drinking
water
22.3-
Industrial
7. Bedti - Varda Karnat 1.05 38 ---- DPR Presently, PFR of
link aka completed in alternate link has been
September submitted to State in
2022. August 2025.
8. Godavari Telang TOTAL Telangana90.0 DPR completed in March 2024
(SSMP/Inchamp ana & 4.74 - 26.8
alli) -Krishna AP Telangana -
(Pulichintala) 0.36
link AP - 4.38 AP -
319.7
9. Godavari AP 4.36 665 960 DPR was Benefits included here
(Polavaram) - completed in are the total benefit
Krishna 2005 under Polavaram
(Viayawada) link Irrigation project.
(Polavaram
irrigation
project)
10. Krishna AP 1.79 58 11 DPR
(Srisailam) – completed in
Pennar link March 2024
11. Kosi-Ghaghra Bihar, Total 8.35 0 -- FR
link U.P & 6.05 – completed in
Nepal Bihar March 2023
1.20 – U.P
Nepal -1.10
12. Gandak - Ganga U.P & Total - 700 4375 FR
link Nepal 34.58 (Dam completed in
U.P -28.80 PH) & June 2024
Nepal -5.78 180
(Canal
PH)
13. Chunar-Sone Bihar Total - 0.60 -- -- FR completed
Barrage link & U.P Bihar - in September,
0.10 2025
U.P. - 0.49
*****