GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4333
TO BE ANSWERED ON 18.03.2026
LONAVLA-PUNE-DAUND RAILWAY CORRIDOR FENCING WORK
4333. DR. AMOL RAMSING KOLHE:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government has undertaken fencing works along
trespassing-prone sections of the Lonavla–Pune–Daund railway corridor
under jurisdiction of the Central Railway and if so, the details thereof;
(b) the total length (in kilometers) identified for fencing in the said corridor,
the cost per kilometer of fencing approved and total project cost
sanctioned;
(c) whether there has been any increase in the estimated project cost due
to delay in execution and if so, the revised cost, reasons for delay and
the agency responsible for same;
(d) whether any safety audit has been conducted for trespassing-prone
sections of the said corridor during the last three years and if so, the
findings thereof; and
(e) the details of the steps taken/proposed to be taken by the Government
to fix accountability for delay and cost escalation, announce a time-
bound completion schedule for fencing work and provide interim safety
measures such as foot overbridges, subways/other protective
infrastructure until the fencing work is completed?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e) Safety of train operations is accorded top priority on Indian
Railways (IR). As one of the important safety measures, provision of
safety fencing has been taken up on routes where the permitted speed
of train operations exceeds 110 kmph, as well as at other vulnerable
§locations, to prevent trespassing and ensure safe train operation.
Pedestrian subways are also being provided with safety fencing in order
to facilitate crossing of railway alignment by cattle, pedestrians and
smaller vehicles.
A work has been sanctioned costing ₹209.38 Cr for providing safety
fencing in entire Lonavala-Pune-Daund route. Work includes construction
of approximately 290 Km fencing with pedestrian subways. Tender has
been awarded for entire length of the section and about 150 Km of
fencing has been completed till date.
Zone-wise details of safety fencing provided along Railway tracks till
date, are as under:
Zonal Railway Length of fencing provided (in Fencing Km)
Central 966
Eastern 754
East Central 730
East Coast 533
Northern 736
North Central 2721
North Eastern 613
Northeast Frontier 153
North Western 1539
Southern 827
South Central 2326
South Eastern 209
South East Central 365
South Western 255
Western 2257
West Central 1415
Total 16398
*****