GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5483
TO BE ANSWERED ON 25.03.2026
MEERUT-BIJNOR RAILWAY LINE
†5483. SHRI ARUN GOVIL:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the preparation of the Detailed Project Report (DPR) has
commenced following the approval of the Final Location Survey (FLS) in
August 2022 for the railway line from Meerut to Bijnor via Mawana and
Hastinapur;
(b) if so, the timeline for its completion;
(c) whether the construction of this rail line is likely to impact the Meerut-
Delhi Rapid Rail and Meerut Metro;
(d) if so, the details of the Government's assessment of this impact; and
(e) the details of the estimated impact on tourism in the historic city of
Hastinapur due to the construction of this rail line?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Meerut and Bijnor are connected on existing Indian Railway
Network via Hapur & Gajraula. To provide additional connectivity, survey
for Daurala (Meerut) – Hastinapur - Bijnor (64 km) new rail line was
sanctioned. The survey has been completed and Detailed Project Report
(DPR) has been prepared.
After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary
approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As
§ Page 1 of 6sanctioning of projects is a continuous and dynamic process, exact
timelines cannot be fixed.
The Delhi – Meerut Namo Bharat RRTS corridor and Meerut Metro corridor
has been completed and commissioned. The alignment of Daurala (Meerut)
– Hastinapur – Bijnor new rail line (64 km) is not affected by RRTS corridor.
Uttar Pradesh :
Railway Budget:
Budget allocation for infrastructure projects and safety works, falling
fully/partly in the State of Uttar Pradesh is as under:
Period Outlay
2009-14 ₹1,109 crore/year
2025-26 ₹19,858 crore (Nearly 18 times)
Track construction:
The details of constructing new tracks falling fully/partly in the State of
Uttar Pradesh during 2009-14 and 2014-25 is as under:
New Track Average Commissioning of new
Period
Commissioned tracks
2009-14 996 Km 199 Km/year
2014-25 5272 Km 479 Km per year (More than 2
times)
Projects sanctioned:
As on 01.04.2025, 49 projects (10 New Line, 02 Gauge Conversion and 37
Doubling) of 3,807 Km length, costing ₹62,360 crore falling fully/partly in
the State of Uttar Pradesh are sanctioned. The summary is as under:-
Page 2 of 6Category No of Total Length Exp
Projects Length Commissioned upto
(km) (km) Mar'25
(Rs. in Cr.)
New Line 10 1227 340 10517
Gauge Conversion 02 67 - 281
Doubling/Multitracking 37 2513 983 19813
Total 49 3807 1323 30611
Recently completed projects:
Details of some of the recently completed projects falling fully/partly in the
State of Uttar Pradesh are as under:
S. Cost
Project
No. (Rs. in Cr.)
1 Meerut-Muzaffarnagar Doubling (55 Km) 430
Bahraich-Nanpara-Nepal Ganj Gauge Conversion (56
2 342
Km)
3 Ballia-Ghazipur city Doubling (65 Km) 650
4 Ghazipur city-Tarighat New Line (17 Km) 1766
5 Gonda-Gorakhpur Loop Gauge Conversion (260 Km) 863
6 Gonda-Bahraich Gauge Conversion (60 Km) 318
7 Barabanki-Akbarpur Doubling (161 Km) 1700
Kaptanganj-Thawe-Chhapra Gauge Conversion (234
8 819
Km)
9 Pilibhit-Shahjahanpur Gauge Conversion (83 Km) 589
10 Indara-Dohrighat Gauge Conversion (34 Km) 213
11 Lucknow-Pilibhit Gauge Conversion (263 Km) 1634
12 Bhadoi-Janghai Doubling (31 Km) 168
13 Lahota-Bhadoi Doubling (39 Km) 184
14 Etawah-Mainpuri New Line (58 Km) 313
15 Phaphamau-Prayagraj Doubling (14 Km) 212
16 Muzaffarnagar–Tapri Doubling (52 Km) 525
17 Utretia-Raibareilly Doubling (66 Km) 662
18 Raibareilly-Amethi Doubling (60 Km) 668
19 Alamnagar-Utretia Doubling (20 Km) 358
20 Bhimsen—Jhansi Doubling (206 Km) 2620
Domingarh-Gorakhpur-Kusumhi - 3rd Line and
21 508
Gorakhpur-Nakaha Jungle Doubling (21 Km)
22 Malhaur-Daliganj Doubling (13 Km) 183
Page 3 of 6S. Cost
Project
No. (Rs. in Cr.)
23 Ruma Chakeri- Chandari 3rd Line (13 Km) 177
Bareilly-Pilibhit-Tanakpur Gauge Conversion (102
24 313
Km)
25 Rosa-Sitapur Cantt-Burhwal Doubling (181 Km) 2094
26 Jaunpur- Akbarpur (Tanda) Doubling (77 Km) 676
27 Ramna- Renukut-Singrauli Doubling (160 Km) 2436
28 Janghai- Phaphamau Doubling (47 Km) 414
29 Varanasi-Madhosingh-Prayagraj Doubling (120 Km) 2018
30 Karaila Road- Shaktinagar Doubling (32 Km) 763
31 Deoband (Muzzafarnagar)-Roorkee (27 Km) 1289
32 Agra-Etawah New Line(110 Km) 427
33 Phephna-Indara, Mau-Shahganj Doubling (150 Km) 1778
Ongoing projects:
Some of the projects falling fully/partly in the State of Uttar Pradesh which
have been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Barabanki-Burhwal 3rd Line (27 Km) 426
2 Burhwal- Gonda Kacheri 4th line (56 Km) 796
3 Burhwal-Gonda 3rd Line (62 Km) 1118
4 Bahraich- Khalilabad New Line (240 Km) 4940
5 Katra-Ayodhya Dham Doubling (10 Km) 466
6 Pt. Deen Dayal Upadhyaya- Prayagraj 3rd Line (150 2649
Km)
7 Billi-Chunar Doubling (102 Km) 1424
8 Chhapra-Ballia Doubling (65 km) 1046
9 Unchhar-Amethi New Line (66 Km) 1229
10 Etah-Kasganj New Line ( 29 Km) 389
11 Gorakhpur- Valmikinagar Doubling (96 Km) 1121
12 Varanasi-Pt. Deen Dayal Upadhyaya 3rd and 4th Line 2464
(15 Km)
13 Jhansi-Khairar-Manikpur & Khairar-Bhimsen 4330
Doubling (431 Km)
14 Sahjanwa-Dohrighat New Line (81 Km) 1320
Page 4 of 615 Kuberpur-Yamuna Bridge 3rd line (10 Km) 170
16 Prayagraj (Iradatganj)-Manikpur 3rd Line (84 km) 1508
17 Dilkusha-Malhaur 3rd Line (8 km) 164
18 Bypass/Chord line at Ayodhya Cantt. (between 97
Salarpur-Masodha) (6 Km)
19 Didarganj - Shahganj - Bilwai Chord line (6 km) 137
20 Varanasi Shivpur 3rd line (6 Km) 76
21 Jaunpur Jn.- Zafarabad Doubling (6 Km) 177
22 Bhatni - Aurnihar Doubling (117 km) 2529
23 Mathura-Jhansi 3rd line (274 km) 5924
24 Agra Fort and Bandikui Doubling (150 km) 988
25 Janghai-Pratapgarh- Amethi Doubling (87 km) 1197
26 Barabanki-Malhaur - 3rd & 4th Line (33 km) 407
27 Phaphamau-Unchahar Doubling (72 km) 971
28 Aunrihar - Varanasi City 3rd Line (31 Km) 76
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Page 5 of 6Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s
*****
Page 6 of 6