**Executive Summary**
This document is the answer to Unstarred Question No. 2833 in Lok Sabha, scheduled for December 17, 2025, concerning the merger of Konkan Railway (KRCL) with Indian Railways and related issues. The document outlines the shareholding structure of KRCL, the current train services in the Mangaluru-Mumbai and Mangaluru-Madgaon sectors, and the status of doubling railway tracks. It also addresses delays in Vande Bharat services. The State Governments with KRCL shareholding are required to contribute to capital expenditure.
**Key Points / Main Content**
* **KRCL Structure and Shareholding:**
* KRCL was established in 1990 with five shareholders.
* The shareholding structure is as follows:
* Government of India (Ministry of Railways): 66.35%
* Government of Maharashtra: 15.11%
* Government of Karnataka: 10.30%
* Government of Goa: 4.12%
* Government of Kerala: 4.12%
* Merger of KRCL is dependent on the agreement of the four State Governments.
* **Train Services:**
* Mangaluru-Mumbai sector is served by 28 pairs of train services.
* Mangaluru-Madgaon sector is served by 33 pairs of train services.
* Lists of the trains serving both sectors are provided.
* **Vande Bharat Services:**
* 164 Vande Bharat services operate on the Indian Railways network.
* State-wise distribution of Vande Bharat services is as follows:
* Maharashtra: 24 services
* Karnataka: 22 services
* Goa: 4 services
* Kerala: 6 services (includes Mangaluru-Madgaon and Madgaon-Mumbai routes).
* **Track Doubling:**
* 55 km of track doubling between Roha-Veer and Madgaon-Majorda is completed.
* Doubling the remaining 685 km requires substantial investment from State Governments.
* KRCL has taken up the work of preparing a detailed project report (DPR) for doubling approximately 263 km of identified sections.
* **Railway Project Sanctioning:**
* Several factors determine the sanction of any railway project, including:
* Traffic projections
* Connectivity
* Route augmentation
* State Government demands
* Operational requirements
* Socio-economic considerations
* Availability of funds
**Impact Analysis**
**Stakeholder: State Governments (Maharashtra, Karnataka, Goa, Kerala)**
* **Impact:**
* Need to agree on the merger of KRCL with Indian Railways.
* Required to contribute towards capital expenditure for track doubling to increase capacity.
* **Action Required:**
* Agree on the merger of KRCL with Indian Railways.
* Provide financial contributions for the track doubling project as per their shareholding.
**Stakeholder: Ministry of Railways**
* **Impact:**
* Responsible for the merger of KRCL with Indian Railways, pending State Government approvals.
* Approaching State Governments for capital expenditure contributions.
* Overseeing the preparation of the detailed project report (DPR) for track doubling.
* **Action Required:**
* Facilitate the agreement among the State Governments for the merger.
* Collect financial contributions from State Governments for track doubling.
* Oversee and approve the DPR for track doubling.
**Stakeholder: Citizens of Coastal Karnataka, Kerala, and Goa**
* **Impact:**
* Potential for improved train services due to track doubling.
* Potential for new Vande Bharat services to further improve connectivity.
* **Action Required:**
* None specified in the document.
Key Entities Referenced
Ministry of Railways: The primary ministry involved in the subject matter of the questions, responsible for Indian Railways.
Konkan Railway Corporation Limited (KRCL): A railway corporation operating in the Konkan region, the merging of which with Indian Railways is being discussed.
Vande Bharat: Refers to a type of railway service, the operation of which is facing delays.
Maharashtra: One of the states that owns shares in the KRCL. Location relevant to the scope as KRCL extends to the state of Maharashtra.
Karnataka: One of the states that owns shares in the KRCL. Location relevant to the scope as KRCL extends to the state of Karnataka.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2833
TO BE ANSWERED ON 17.12.2025
MERGING OF KONKAN RAILWAY WITH INDIAN RAILWAYS
2833. SHRI KOTA SRINIVASA POOJARY:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the reason for delay in merging Konkan Railway with
Indian Railways;
(b) whether people of the Coastal Karnataka, Kerala and Goa are
facing reduced train services due to lack of doubling of railway tracks
and if so, the steps taken to conduct a Survey for doubling work of
tracks on this sector;
(c) the details of the specific reasons for the delay in the operation of
Vande Bharat, even though the Railways has agreed to provide the
much-awaited Vande Bharat railway service from Mangalore to
Mumbai;
(d) whether it is a fact that Railway services is limited to the above
Coastal region more than any other region and if so the details
thereof; and
(e) the details of the comprehensive improvements planned for
railway services, including double of tracks in the said region?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Konkan Railway Corporation Limited (KRCL) was
established in 1990 with five shareholders, namely, Ministry of
Railways, Government of Maharashtra, Government of Goa,Government of Karnataka and Government of Kerala. The Konkan
Railway line extends from Roha in Maharashtra to Thokur in
Karnataka which passes through difficult terrain of Western Ghats.
The present shareholding structure of KRCL is as under: -
SN Name of Share holder Share in %
1 Government of India through Ministry of 66.35
Railways
2 Government of Maharashtra 15.11
3 Government of Karnataka 10.30
4 Government of Goa 4.12
5 Government of Kerala 4.12
Merger of KRCL is dependent upon the four State Governments who
have shareholding in KRCL.
Presently, Mangaluru β Mumbai sector is being served by 28 pairs of
train services while Mangaluru - Madgaon sector is presently being
served by 33 pairs of train services as under:
Train serving Mangaluru β Mumbai sector:
SN Train No. & Train Name
1 12431/12432 Thiruvananthapuram Central β Hazrat Nizamuddin
Rajdhani Express
2 12133/12134 Chhatrapati Shivaji Maharaj (T) - Mangaluru
Junction Express
3 12201/12202 Lokmanya Tilak (T) β Thiruvananthapuram North
Garib Rath Express4 12217/12218 Thiruvananthapuram North - Chandigarh Kerala
Sampark Kranti Express
5 12223/12224 Lokmanya Tilak (T) β Ernakulam Duronto Express
6 12283/12284 Ernakulam β Hazrat Nizamuddin Duronto Express
7 12483/12484 Thiruvananthapuram North β Amritsar Junction
Express
8 12617/12618 Ernakulam β Hazrat Nizamuddin Mangala
Lakshadweep Express
9 12619/12620 Lokmanya Tilak (T) - Mangaluru Central
Matsyagandha Express
10 12977/12978 Ernakulam - Ajmer Maru Sagar Express
11 16311/16312 Shri Ganganagar β Thiruvananthapuram North
Express
12 16333/16334 Veraval β Thiruvananthapuram Central Express
13 16335/16336 Gandhidham β Nagercoil Express
14 16337/16338 Okha β Ernakulam Express
15 16345/16346 Lokmanya Tilak (T) β Thiruvananthapuram Central
Netravati Express
16 19259/19260 Thiruvananthapuram North β Bhavnagar (T) Express
17 19577/19578 Jamnagar β Tirunelveli Express
18 20909/20910 Thiruvananthapuram North - Porbandar Express
19 20923/20924 Tirunelveli β Gandhidham Humsafar Express
20 20931/20932 Thiruvananthapuram North β Indore Express
21 22113/22114 Lokmanya Tilak (T) β Thiruvananthapuram North
Express
22 22149/22150 Ernakulam - Pune Express23 22475/22476 Hisar β Coimbatore Express
24 22629/22630 Dadar Central - Tirunelveli Express
25 22633/22634 Thiruvananthapuram Central - Hazrat Nizamuddin
Express
26 22653/22654 Thiruvananthapuram Central β Hazrat Nizamuddin
Express
27 22655/22656 Ernakulam β Hazrat Nizamuddin Express
28 22659/22660 Thiruvananthapuram North - Yog Nagari Rishikesh
Express
Train serving Mangaluru - Madgaon sector:
SN Train No. & Train Name
1 20645/20646 Madgaon β Mangaluru Vande Bharat Express
2 10107/10108 Madgaon β Mangaluru MEMU Express
3 10215/10216 Madgaon β Ernakulam Express
4 11097/11098 Pune β Ernakulam Poorna Express
5 12133/12134 Chhatrapati Shivaji Maharaj (T) β Mangaluru Express
6 12201/12202 Lokmanya Tilak (T) β Thiruvananthapuram North
Garib Rath Express
7 12217/12218 Thiruvananthapuram North - Chandigarh Kerala
Sampark Kranti Express
8 12223/12224 Lokmanya Tilak (T) β Ernakulam Duronto Express
9 12283/12284 Ernakulam - Nizamuddin Duronto Express
10 12431/12432 Thiruvananthapuram Central - Hazrat Nizamuddin
Rajdhani Express11 12483/12484 Thiruvananthapuram North - Amritsar Junction
Express
12 12617/12618 Ernakulam - Hazrat Nizamuddin Mangala
Lakshadweep Express
13 12619/12620 Lokmanya Tilak (T) - Mangaluru Central
Matsyagandha Express
14 12977/12978 Ernakulam - Ajmer Maru Sagar Express
15 16311/16312 Shri Ganganagar β Thiruvananthapuram North
Express
16 16333/16334 Veraval β Thiruvananthapuram Central Express
17 16335/16336 Gandhidham β Nagercoil Express
18 16337/16338 Okha β Ernakulam Express
19 16345/16346 Lokmanya Tilak (T) β Thiruvananthapuram Central
Netravati Express
20 19259/19260 Thiruvananthapuram North - Bhavnagar (T) Express
21 19577/19578 Tirunelveli - Jamnagar Express
22 20909/20910 Thiruvananthapuram North - Porbandar Express
23 20923/20924 Tirunelveli - Gandhidham Humsafar Express
24 20931/20932 Thiruvananthapuram North - Indore Express
25 22113/22114 Lokmanya Tilak (T) β Thiruvananthapuram North
Express
26 22149/22150 Ernakulam - Pune Express
27 22475/22476 Hisar β Coimbatore Express
28 22629/22630 Dadar Central β Tirunelveli Express
29 22633/22634 Thiruvananthapuram Central - Hazrat Nizamuddin
Express30 22653/22654 Thiruvananthapuram Central - Hazrat Nizamuddin
Express
31 22655/22656 Ernakulam - Hazrat Nizamuddin Express
32 22659/22660 Yog Nagari Rishikesh β Thiruvananthapuram North
Express
33 56615/56616 Madgaon β Mangaluru Central Passenger
164 Nos. Vande Bharat services are being operated on the Indian
Railways network. Of these, on originating/terminating basis, 24 nos.
Vande Bharat services are catering to the needs of various stations
located in the State of Maharashtra, 22 nos. services in the State of
Karnataka, 4 nos. services in the State of Goa and 6 nos. in the state
of Kerala, which includes Vande Bharat trains running between
Mangaluru-Madgaon and Madgaon-Mumbai station.
Out of the 739 route km of Konkan Railway jurisdiction, doubling of
about 55 km between Roha- Veer and Madgaon- Majorda sections has
already been completed. To increase the capacity of the balance 685
km route, doubling is required. This requires substantial investment
with the contribution from all the shareholding State Government.
The concerned State Governments have been approached by the
Ministry of Railways for contributing towards capital expenditure in
KRCL as per their share.
In the meanwhile, KRCL has taken up the work of preparation of
detailed project report (DPR) for the doubling of identified sections
(approx 263 km) to increase the capacity of route.Further, sanction of any railway project depends upon many
parameters/factors which include the following:
β’ Anticipated traffic projections and remunerativeness of the
proposed route
β’ First and last mile connectivity provided by the project
β’ Connection of missing links and providing additional route
β’ Augmentation of congested/saturated lines
β’ Demands raised by State Governments/Central Ministries/Public
representatives,
β’ Railwayβs operational requirements
β’ Socio-economic considerations
β’ Overall availability of funds
*****