Executive Summary:
The Ministry of New and Renewable Energy addressed questions regarding renewable energy initiatives, including MoUs, fund allocation, project status in the North Eastern Region (NER), and training programs. The Ministry has signed MoUs with 32 States/UTs under PM Surya Ghar: Muft Bijli Yojana (PMSGMBY). As of June 2025, various training programs have skilled a significant number of individuals in the renewable energy sector.
Key Points / Main Content:
Memorandums of Understanding (MoUs):
* MoUs have been signed with 32 States/UTs under PMSGMBY to promote grid-connected rooftop solar systems in the residential sector.
* No specific study has been conducted by the Government on employment generation, however, as per CEEW study in July 2019, approx. 9.89 lakh persons are estimated to be employed in rooftop sector.
Financial Allocations:
* State-wise annual fund allocation is not conducted; Central Financial Assistance is released per scheme guidelines.
* 10% of the Ministry's annual Gross Budgetary Allocation is earmarked for the development of the North Eastern Region (NER).
* In 2024-25, the Ministry's Revised Estimates included Rs. 11,100 crore for PMSGMBY and Rs. 2525 crore for PMKUSUM out of total budget allocation of Rs.17,298.44 crore.
* In 2025-26, the Ministry's Budget Estimates include Rs. 20,000 crore for PMSGMBY and Rs. 2600 crore for PMKUSUM out of total budget allocation of Rs. 26,549.38 crore.
Renewable Energy Projects in NER:
* Details of commissioned renewable energy projects (Solar Power and Small Hydro Power) in the NER are provided, with state-specific capacities listed in Annexure.
* Includes capacities commissioned under PMSGMBY and PMKUSUM.
* Lists the number of applications and households covered under PM Surya Ghar: Muft Bijli Yojana (PMSGMBY) as on 20.07.2025, state-wise.
* Details of PMKUSUM components (A, B, and C) including number sanctioned, installed capacity (MW) and sanctioned IPS, state-wise.
Training Programs:
* As of June 2025, 63713 individuals have been trained under the Suryamitra program.
* 1276 individuals have been trained under the Varunmitra program.
* 2160 individuals have been trained under the Vayumitra program.
* 601 individuals have been trained under the Jalurjamitra program.
* Additionally, 1.14 lakh persons have been trained in rooftop installations under PMSGMBY.
Impact Analysis:
States/Union Territories:
Impact: States/UTs are involved in promoting grid-connected rooftop solar systems under PMSGMBY. The NER receives earmarked funds for renewable energy development.
Action Required: States/UTs should adhere to the guidelines of PMSGMBY and PMKUSUM for utilizing Central Financial Assistance.
Private Sector Developers:
Impact: The private sector is primarily responsible for setting up renewable energy projects.
Action Required: Continue developing renewable energy projects in alignment with government schemes and guidelines.
Citizens/Residential Sector:
Impact: The residential sector benefits from the promotion of rooftop solar systems through PMSGMBY.
Action Required: Consider installing grid-connected rooftop solar systems to benefit from the PMSGMBY scheme.
Trainees (Surya Mitra, Varun Mitra, Jal Urja Mitra):
Impact: Trained individuals gain skills in the renewable energy sector, enhancing employment opportunities.
Action Required: Utilize acquired skills for employment and contribute to the growth of the renewable energy sector.
Key Entities Referenced
Ministry of New and Renewable Energy: The Indian government ministry responsible for renewable energy.
Pradhan Mantri Surya Ghar Muft Bijli Yojana: A government scheme (PMSGMBY) to promote grid-connected rooftop solar systems in the residential sector.
Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan: A government scheme (PMKUSUM) related to solar energy and farmers.
North Eastern Region: A region of India that includes states like Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Sikkim and Tripura.
Rajasthan: A state in India mentioned in the context of renewable energy sector and fund allocation.
Shri Shripad Yesso Naik: The Minister of State for New Renewable Energy and Power.
Council on Energy, Environment and Water: An organization (CEEW) that conducted a study on employment related to green energy.
Arunachal Pradesh: A state in the North Eastern Region of India where renewable energy projects have been commissioned.
GOVERNMENT OF INDIA
MINISTRY OF NEW AND RENEWABLE ENERGY
LOK SABHA
UNSTARRED QUESTION NO. 633
ANSWERED ON 23/07/2025
MOUS SIGNED IN RENEWABLE ENERGY SECTOR
633. SHRI DILIP SAIKIA
SHRI LUMBARAM CHOUDHARY
SMT. BIJULI KALITA MEDHI
SHRI GODAM NAGESH
SMT. APARAJITA SARANGI
Will the Minister of NEW & RENEWABLE ENERGY be pleased to state:
(a) the number of Memorandums of Understanding (MoUs) signed in the field of renewable
energy sector in the country including North-Eastern region and Rajasthan along with the
estimated cost (value) involved therein and its expected impact on employment and growth
thereon:
(b) the percentage of Government’s annual plan funds earmarked specifically for the North-
Eastern region and Rajasthan along with the increase in amount of central financial assistance
for the region/State under the Pradhan Mantri Surya Ghar-Muft Bijli Yojana (PM-SGMBY) and
Pradhan Mantri Kisan Urja Suraksha evam Utthaan Mahabhiyan (PM-KUSUM) scheme;
(c) the details of renewable energy projects recently commissioned or under development in
North Eastern Region ; and
(d) the total number of people trained in the said sector under various programmes such as Surya
Mitra, Varun Mitra and Jal Urja Mitra?
ANSWER
THE MINISTER OF STATE FOR NEW & RENEWABLE ENERGY AND POWER
(SHRI SHRIPAD YESSO NAIK)
(a) Presently, most of renewable energy projects are being set up by private sector developers.
However, the Ministry has signed MoUs with 32 States/UTs under PM Surya Ghar: Muft Bijli
Yojana (PM-SGMBY) to promote the installation of grid-connected rooftop solar systems in the
residential sector.
The Government has not carried out any specific study on employment generation. However, as
per the study viz. “Powering jobs growth with green energy” carried out by Council on Energy,
Environment and Water (CEEW) in July, 2019, approx. 9.89 lakh persons are estimated to be
employed in rooftop sector.
(b) State-wise annual allocation of funds is not done by the Ministry and the Central Financial
Assistance is released in accordance with the respective scheme guidelines.
As per the Government guidelines, 10% of the annual Gross Budgetary Allocation of the Ministry
is earmarked towards development of the North Eastern Region (NER).
During 2024-25, the total budget allocation (Revised Estimates) of the Ministry was
Rs.17,298.44 crore, out of which allocation of Rs.11,100 crore was for PM-SGMBY and of
Rs.2525 crore was for PM-KUSUM. During 2025-26, the total budget allocation (BE) of the
Ministry is Rs.26,549.38 crore, out of which allocation of Rs.20,000 crore is for PM-SGMBY
and of Rs.2600 crore is for PM-KUSUM.(c) The details of renewable energy projects commissioned in North Eastern Region are given
as Annexure.
(d) Till June, 2025, a total of 63713 persons have been trained under Suryamitra programme, 1276
persons have been trained under Varunmitra programme, 2160 persons have been trained under
Vayumitra programme and 601 persons have been trained under Jalurjamitra programme.
Additionally, 1.14 lakh persons have been trained in rooftop installations under PM-SGMBY.
*****Annexure
Annexure referred to in reply to part (c) of the Lok Sabha Unstarred Question No. 633 for
23.07.2025
Details of renewable energy projects commissioned and under development in NER
(1) Solar Power and Small Hydro Power
Solar Power capacity Small Hydro Power capacity
S. No. STATE
commissioned* (MW) commissioned (MW)
1 Arunachal Pradesh 14.85 140.61
2 Assam 243.34 34.11
3 Manipur 13.79 5.45
4 Meghalaya 4.28 55.03
5 Mizoram 30.39 45.47
6 Nagaland 3.17 32.67
7 Sikkim 7.56 55.11
8 Tripura 21.71 16.01
Total 339.09 384.46
*Including capacities commissioned under PM-SGMBY and PM-KUSUM
(2) PM Surya Ghar: Muft Bijli Yojana
Sl.No. State No. of applications No. of Households covered
submitted (as on 20.7.2025) (as on 20.7.2025)
1 Assam 3,65,249 25,988
2 Arunachal Pradesh 118 0
3 Manipur 1,153 409
4 Meghalaya 2,377 21
5 Mizoram 1,002 394
6 Nagaland 554 26
7 Sikkim 93 9
8 Tripura 6,229 584
Total 3,76,775 27,431
(3) PM-KUSUM:
Component-A
Component-B (Nos) Component-C (Nos)
S. (MW)
State
No. Sanction Sanctioned
Installed Sanctioned Installed Installed
ed (IPS)
Arunachal
1 0 0 700 577 0 0
Pradesh
2 Assam 2 0 4,000 0 0 0
3 Manipur 0 0 1,150 78 0 0
4 Meghalaya 0 0 3,035 98 0 0
5 Mizoram 0 0 1,700 40 0 0
6 Nagaland 0 0 265 65 0 0
7 Sikkim 0 0 0 0 0 0
8 Tripura 5 0 10,895 4,971 3,600 285