GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3011
TO BE ANSWERED ON 11.03.2026
NEW/ONGOING/PENDING RAILWAY PROJECTS ACROSS THE COUNTRY
†3011. SHRI ARUN KUMAR SAGAR:
SHRI THARANIVENTHAN M S:
SMT. MANJU SHARMA:
SHRI AJAY BHATT:
SHRI MANSUKHBHAI DHANJIBHAI VASAVA:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Railways has received proposals from States including
Uttarakhand and if so, the details of proposals approved and pending so
far along with the reasons therefor;
(b) the details of the action taken by the Government thereof;
(c) the details of the new/ongoing/pending railway projects in the country
particularly in Rajasthan during the last three years including their
present status/reasons for delay and the time since these projects are
pending, State, zone and project-wise;
(d) the number of projects lagging behind their time schedule, the project-
wise reasons for delays and the cost escalations under these projects;
(e) the details of the allocated funds for each project and expenditure
incurred so far particularly Tamil Nadu including Arani Lok Sabha
Constituency during the last three years and the current year;
(f) the number of the projects stalled/pending due to lack of funds;
(g) whether there has been significant increase in the expenditure of these
projects, if so, the details thereof;
..P/2
§-:2:-
(h) the expected timeline for the completion of these projects and their
anticipated impact on improving railway infrastructure; and
(i) the details of the steps being taken to ensure timely execution and
prevent delays in these projects?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOG
(SHRI ASHWINI VAISHNAW)
(a) to (i): Railway projects are surveyed /sanctioned/executed Zonal Railway
wise and not State-wise /District wise as the Railway projects may span
across State/district boundaries.
Proposals/requests/suggestions/ representations, both formal and informal
for Railway projects/Works across the country are received on the basis of
demands raised by State Governments, Members of Parliament, Ministries
of Central Government, elected representatives, Railways’ own
requirements, organizations/rail users etc. At various levels including
Railway Board, Zonal Railways, Division Office etc. As receipt of such
proposals/complaints/suggestions is a continuous and dynamic process,
centralized compendium of such requests is not maintained. However,
these are examined and action as found feasible and justified is taken from
time to time.
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure
projects (154 New Line, 33 Gauge Conversion and 244 Doubling) of total
length 35,966 Km, costing approx. 6.75 lakh crore are sanctioned. The
summary is as under:-
..P/3-:3:-
Total Length
Total Exp upto
No of Length Commissioned
Category Mar'25
Projects NL/GC/DL till Mar'25
( in Cr)
(km) (Km)
New Lines 154 16,142 3,036 1,45,318
Gauge
33 4,180 2,997 22,753
Conversion
Doubling /
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railway’s website.
The details of commissioning/laying of new track across Indian Railways is
given below:-
New track
Average commissioning of new tracks
Period
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
During last 3 years (2022-23, 2023-24, 2024-25) and current Financial Year
2025-26, 982 no. Surveys (295 New line, 13 Gauge Conversion and 674
Doubling) of total length 67,010 Km have been sanctioned across Indian
Railways.
Uttarakhand:
Budget allocation for Infrastructure projects and safety works, falling fully/
partly in Uttarakhand is as under:
..P/4-:4:-
Period Outlay
2009-14 Rs 187 Crore/year
2025-26 Rs 4,641 Crore (nearly 25 times)
As on 01.04.2025, 03 New Lines, covering total length of 216 Km costing Rs
40,384 crore falling fully/partly in the State of Uttarakhand are sanctioned,
out of which 16 Km length has been commissioned and an expenditure of Rs
19,898 crore has been incurred upto March’ 2025. The summarized details
are as under:-
Category No. Of Total Length Expenditure upto
projects Length Commissioned March 2025
(in Km) (in Km) ( in crore)
New
03 216 16 19,898
Lines
To provide rail connectivity to Chardham, Rishikesh-Karnaprayag new rail
line project (125 km) has been sanctioned.
The project alignment passes through Dehradun, Tehri Garhwal, Pauri
Garhwal, Rudrapryag and Chamoli Districts of Uttarakhand and will provide
rail connectivity to Devprayag and Karnaprayag religious and tourist spots
with Rishikesh and National Capital of India.
The alignment of the project predominantly passes through tunnels. The
project involves construction of 16 Main line tunnels of 104 km length and 12
Escape tunnels of about 98 km length. So far, Main line tunnels of 99 km
length and 09 Escape Tunnels of over 94 km length have been completed.
..P/5-:5:-
To increase progress of works, 08 Adits in various tunnels were also
identified. These adits created additional work faces of tunnel excavation
expediting early completion of long tunnels. Works of all 8 Adits (5 km) have
also been completed.
The project also involves construction of 19 Important/Major Bridges. 8 out
of 19 Important/Major Bridges have also been completed. Works in balance
bridges have also been taken up.
To further extend the rail connectivity to Gangotri, Yamunotri, Kedarnath and
Badrinath, survey has been completed. However, the project alignment lies
near the main Central thrust of Himalayas which is highly seismically active.
Rajasthan:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Rajasthan is as under:-
Period Outlay
2009-14 682 crore/year
2025-26 9,960 crore (Nearly 15 times)
The details of commissioning/laying of new track falling fully/partly in the
State of Rajasthan during 2009-14 and 2014-25 is as under:-
Period New Track Average commissioning of new
Commissioned tracks
2009-14 798 Km 159.60 Km/year
2014-25 3,815 Km 346.82 Km/year (More than 2 times)
..P/6-:6:-
As on 01.04.2025, 28 Railway projects (13 New Lines, 05 Gauge Conversion
and 10 Doubling), of total length of 3,409 Km costing ₹43,918 crore falling
fully/partly in the State of Rajasthan, are sanctioned. The summary is as
under:-
Category No. of Total Length Expenditure upto
projects Length Commissioned March 2024
(in Km) (in Km) ( in Cr)
New Lines 13 981 196 5769
Gauge
5 1252 788 6829
Conversion
Doubling/
10 1176 254 6357
Multitracking
Total 28 3,409 1,238 18,954
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railway’s website.
Details of some of the recently completed projects falling fully/partly in the
State of Rajasthan are as under:
S.No. Name of Project Latest Cost
( in crore)
1 Bangurgram-Ras New Line (28 km) 175
2 ThaiyatHamira-Sonu New Line (58 Km) 350
3 Suratpura- Sriganganagar Gauge Conversion (241 Km) 896
4 Sadulpur-Bikaner & Ratangarh-Degana Gauge 886
Conversion (438 Km)
..P/7-:7:-
S.No. Name of Project Latest Cost
( in crore)
5 Jaipur -Churu & Sikar-Loharu Gauge Conversion (320 1105
Km)
6 Bhagat ki Kothi-Luni Doubling (28 Km) 128
7 Rani-Keshav Ganj Doubling (59 Km) 290
8 Guriya-Marwar & Karjoda-Palanpur Doubling (49 Km) 251
9 Rani-Marwar Doubling (52 Km) 346
10 Abu Road-Swaroop Ganj Doubling (26 Km) 195
11 Abu Road-Sarotra Road Doubling (24 Km) 152
12 Alwar-Bandikui Doubling (60 Km) 450
13 Ajmer-Bangurgram Doubling (48 Km) 375
14 Bangurgram-Guriya Patch Doubling (47 Km) 395
15 Degana-Rai ka Bagh Doubling (146 Km) 809
16 Bina-Kota Doubling (283 Km) 2476
17 Nimach-Chittaurgarh Doubling (56 Km) 560
18 Dausa-Gangapur City Doubling (93 Km) 950
19 Phulera-Degana Doubling (108 Km) 702
20 Churu-Ratangarh Doubling (43 Km) 423
21 Khatuwas-Narnaul Doubling (24 Km) 313
Some of the main projects falling fully/partly in the State of Rajasthan which
have been taken up are as under:
S.No. Name of Project Cost
( in crore)
1 Nimach-Badi Sadri New Line (48 Km) 495
..P/8-:8:-
2 Taranga Hill-Abu Road New Line (116 Km) 2798
3 Ramganjmandi-Bhopal New Line (277 Km) 5073
4 Pushkar-Merta New Line (51 Km) 800
5 Ringus-Khatu Shyam Ji New Line (17 Km) 254
6 Merta city-Ras New Line & Bye Pass at Merta Road 947
Station
(56 Km)
7 Gwalior-Sheopurkalan Gauge Conversion with 2913
extension to Kota (284 Km)
8 Dholpur-Sirmuttra Gauge Conversion with extension to 747
Gangapur City (145 Km)
9 Mavli-Devgarh Madariya Gauge Conversion (83 Km) 969
10 Mathura-Jhansi 3rd Line (274 Km) 5924
11 Agra Fort-Bandikui Doubling (150 Km) 988
12 Sawaimadhopur-Jaipur Doubling (131 Km) 1204
13 Churu-Sadulpur & Luni-Bhildi Doubling (330 Km) 3554
14 Ajmer-Chanderiya Doubling (178 Km) 1635
15 Bye Pass line at Sawaimadhopur (14 Km) 304
16 Rewari-Khatuwas Doubling (28 Km) 352
17 Bye Pass line at Marwar (4 Km) 71
18 Bypass line at Churu (5 Km) 63
19 Bypass line at Samdari (1 Km) 26
20 Ramdevra-Pokhran new line (13 Km) 189
21 Lalgarh-Bikaner East Cabin doubling (11 Km) 279
22 Ringas-Sikar Doubling (50 Km) 470
..P/9-:9:-
In last three years, 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 59 surveys (25 new line & 34 doubling) of total length 5,666 Km
falling fully/partly in the State of Rajasthan have been sanctioned in the
state of Rajasthan.
Tamil Nadu
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Tamil Nadu is as under:
Period Outlay
2009-14 ₹879 crore/year
2025-26 ₹ 6,626 crore (more than 7.5 times)
As on 01.04.2025, 15 projects (09 new line, 03 gauge conversion and 03
doubling) of 1,700 km length, costing ₹22,808 Crore, falling fully/partly in
the State of Tamil Nadu, are sanctioned. The summary is as under:-
Category No. of Total Length Length Expenditure
sanctioned (in km) Commissioned upto Mar’ 25
projects upto Mar’25 (₹ in Cr.)
(in km)
New Line 9 812 24 1,337
Gauge Conversion 3 748 604 3,471
Doubling 3 140 37 2,783
/Multitracking
Total 15 1,700 665 7,591
..P/10-:10:-
Zone-wise/year-wise details of all Railway projects are made available in
public domain on Indian Railway’s website.
Details of some of the recently completed projects falling fully/partly in
Tamil Nadu are as under:
Cost
S.N. Project
( in Crores)
1 Dindigal-Palani-Pollachi gauge conversion (121 km) 610
2 Pollachi-Palghat gauge conversion (56 km) 350
3 Pollachi-Podhanur gauge conversion (40 km) 400
4 Quilon-Tirunelveli-Tiruchendur gauge conversion (357
1,122
km)
5 Mayiladuturai-Thiruvarur-Karaikkudi gauge conversion
1,338
(187 km)
6 Madurai-Bodiyakannur gauge conversion (90 km) 593
7 Chengalpattu-Villupuram doubling (102 km) 670
8 Tiruvallur-Arakkonam 4th line (27 km) 83
9 Chennai Central-Basin Bridge doubling (2 km) 31
10 Thanjavur-Ponmalai doubling (48 km) 370
11 Villupuram-Dindigul doubling (273 km) 2,000
12 Chennai Beach-Korukkupet 3rd line (5 km) 168
13 Chennai Beach-Attipattu 4th line (22 km) 293
14 Omalur-Metturdam Patch doubling (29 km) 327
15 Chengalpattu-Villupuram and Tambaram-
1,122
Chengalpattu-3rd line (133 km)
..P/11-:11:-
Cost
S.N. Project
( in Crores)
16 Salem-Magnesite Junction-Omalur doubling (11 km) 115
17 Madurai- Maniyachi-Tuticorin doubling (160 km) 1,891
18 Maniyachi-Nagercoil doubling (102 km) 1,752
19 Chennai Beach-Chennai Egmore doubling (4 km) 272
20 Karaikal-Peralam new line (23 km) 373
21 Northern End Port connectivity to Karaikal Port (1 km) 18
To improve connectivity in Arani following works have been taken up:
S.N Project Cost
( in Crore)
1 Tindivanam-Nagari new line (184 km) 3,631
2 Tindivanam-Tiruvannamalai new line (71 Km) 1400
Some of the other projects falling fully/partly in the State of Tamil Nadu
constituency which have been taken up are as under:
Cost
S.N Project
( in Crores)
1 Morappur-Dharmapuri new line (36 km) 359
2 Nagapattinam-Tiruturaipundi new line (43 km) 742
3 Trivandrum-Kanyakumari doubling (87 km) 3,785
4 Arakkonam yard 3rd & 4th line (6 km) 98
5 Irugur-Podanur doubling (11 km) 277
6 Tambaram-Chengalpattu 4th Line (30 km) 757
..P/12-:12:-
Cost
S.N Project
( in Crores)
7 Attipattu-Gummidipundi 3rd & 4th line (23 km) 365
8 Perambur-Ambattur 5th & 6th line (6 km) 182
9 Tirupati-Pakala-Katpadi doubling (104 km) 1332
10 Attipattu-Puttur new line (88 km) 1700
11 Chennai – Cuddulore via Mahabalipuram new line (179 2670
Km)
In last three years i.e. 2022-23, 2023-24, 2024-25 and current financial year
2025-26, 29 surveys (06 new line and 23 doubling) covering a total length of
2,478 km has been sanctioned falling fully/partly in the State of Tamil Nadu.
Execution of important infrastructure projects falling fully/partly in the
State of Tamil Nadu are held up due to delay in land acquisition. Status of
land acquisition in Tamil Nadu is as under:
Total Land required for Projects in Tamil Nadu 4,326 ha
Land Acquired 1,052 ha (24%)
Balance Land to be acquired 3,274 ha (76%)
Support of the Government of Tamil Nadu is needed to expedite the land
acquisition.
Details of some major projects which are delayed due to land acquisition
are as under:-
..P/13-:13:-
SN Name of the project Total land Land Balance
required acquired Land to be
(in ha) (in ha) acquired
(in ha)
1. Tindivanam-Tiruvannamalai 276 33 243
new line (71 km)
2. Attiputtu-Puttur new line (88 189 0 189
km)
3. Morappur-Dharmapuri new line 92 45 47
(36 km)
4. Mannargudi-Pattukkottai new 196 0 196
line (41 km)
5. Thanjavur-Pattukottai new line 152 0 152
(52 km)
Further, Rameshwaram – Dhanushkodi new line (18 km) was sanctioned at a
cost of 734 Cr. The Foundation Stone of the project was laid on 01.03.2019.
However, the project could not be started because the land acquisition has
not been undertaken by the State Govt. of Tamil Nadu.
Government of India is geared up to execute projects, however success
depends upon the support of Government of Tamil Nadu.
Sanction of any railway project depend upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
..P/14-:14:-
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned authorities for
expeditious land acquisition, forestry and Wildlife clearances and for
resolving other issues pertaining to projects.
*****