Date: 2026-02-04 Category: Not Applicable State: Union Government Country: India

Parliament Question: New Railway Lines in Telangana

Issued by RAILWAYS · Not Applicable

Research with AI Agent Chat with Document Generate Summary Translate Helpful Share Add to Project Create Task

Executive Summary & Key Takeaways

**Executive Summary** This document is a response to Unstarred Question No. 698 in the Lok Sabha regarding new railway lines in Telangana, to be answered on February 4, 2026. It details the budget allocation, commissioning of new tracks, completed projects, sanctioned projects, and surveys in the State of Telangana. The report also outlines the challenges faced, including delays in land acquisition. **Key Points / Main Content** * **Budget Allocation and Commissioning:** * Budget allocation for infrastructure projects and safety works in Telangana has significantly increased in recent years. * The outlay for 2009-14 was Rs. 886 Cr/Year (including Andhra Pradesh) and for 2025-26 is Rs. 5,337 Cr. * From 2009-14, 87 Km of new track was commissioned (17.4 km/year), while from 2014-25, 774 Km were commissioned (70.4 km/year). * **Completed Projects:** * Several projects falling fully/partly in Telangana have been completed, including: * Peddapalli-Nizamabad new line (178 Km) at Rs. 926 Cr. * Jaggayyapeta-Janpahad new line (48 Km) at Rs. 737 Cr. * Akkanapet – Medak new line (17 Km) at Rs. 205 Cr. * Bhadrachalam Road-Sattupalli new line (56 Km) at Rs. 990 Cr. * Secunderabad- Mehboobnagar Doubling (85 Km) at Rs. 1,266 Cr. * Multi- Modal Transport System (MMTS) Phase-II, Hyderabad (103 Km) at Rs. 1,156 Cr. * Byepass line at Peddapalli (2 Km) at Rs. 37 Cr. * **Sanctioned Projects:** * As of 01.04.2025, 20 railway projects (6 New Lines and 14 Doubling) of a total length of 2,166 Km, costing ₹35,045 crore falling fully/partly in the State of Telangana have been sanctioned. * 548 Km length has been commissioned and an expenditure of ₹11,550 crore has been incurred upto March, 2025. * Sanctioned projects include Manoharabad-Kothapalli new line (151 Km), Malkangiri-Pandurangapuram new line (174 Km), Kazipet -Vijaywada - 3rd line (220 Km). * **Surveys Sanctioned:** * 57 surveys (18 New Line and 39 Doubling) covering a total length of 5,665 Km have been sanctioned. * These surveys include lines from Vikarabad-Krishna (122 Km), Gadwal-Dornakal via Kalwakurthy (316 Km), Kacheguda-Jaggayyapeta (250 Km), Patancheru-Adilabad (320 Km), Bodhan-Latur Road (128 Km), and Akkanapet Bypass (128 Km). * **Challenges:** * Project sanctioning depends on parameters like traffic projections, connectivity, congestion, and demands. * Execution delays due to land acquisition, with 764 Ha (33%) of land still to be acquired. * Completion depends on land acquisition by the State Government, forest clearance, shifting utilities, statutory clearances, geological conditions, law and order, and working months. **Impact Analysis** **Government of Telangana** * **Impact:** The document addresses the Government of Telangana's proposals for new railway lines and provides updates on the status of sanctioned and completed projects. Delays in land acquisition could hinder further progress. * **Action Required:** Address the issues related to land acquisition to expedite railway project completion. **Ministry of Railways** * **Impact:** The document provides an overview of the railway infrastructure development in Telangana, including budget allocation, completed projects, and future plans. * **Action Required:** Continue to monitor project progress, address the factors causing delays, and ensure timely completion of sanctioned projects.

Key Entities Referenced

Ministry of Railways: The primary government body responsible for railway projects mentioned in the document. Telangana: The Indian state where the new railway lines and projects are located. NITI Aayog: Government of India think tank involved in the appraisal and approval of railway projects.
Official Source Record View Original Source →
See Full Document Text
GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA UNSTARRED QUESTION NO. 698 TO BE ANSWERED ON 04.02.2026 NEW RAILWAY LINES IN TELANGANA 698. SHRI EATALA RAJENDER: Will the Minister of RAILWAYS be pleased to state: (a) whether the Government of Telangana has sent various proposals of new routes including 1. Vikarabad-Krishna(122Km) 2. Kalwakurthy-Macherla(120km) 3. Gadwal-Dornakal(316km) 4. Kacheguda-Jaggayyapeta(250km) 5. Patancheru-Adilabad(320km) 6. Bodhan-Latur Road(128km) 7. Akkanapet Bypass(128km) 8. Pandurangapuram-Badrachalam Road(13 km) (b) if so, the details and the action taken thereon; and (c) the details of the funds sanctioned/spent for the said project? ANSWER MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND ELECTRONICS & INFORMATION TECHNOLOGY (SHRI ASHWINI VAISHNAW) (a) to (c): Budget allocation in the recent years has increased significantly. Budget allocation for infrastructure projects and safety works, falling fully/partly in the State of Telangana is as under: Contd…2-2- Period Outlay 2009-14 Rs. 886 Cr./Yr.(including Andhra Pradesh) 2025-26 Rs. 5,337 Cr. The details of commissioning/laying of new track falling fully/partly in the State of Telangana during 2009-14 and 2014-25 is as under: Period New Track Average Commissioning of new Commissioned tracks 2009-14 87 Km 17.4 km/per year 2014-25 774 Km 70.4 km /per year (more than 4 times) Details of some of the completed projects falling fully/partly in the State of Telangana are as under: Cost S. No. Project (Rs. in Cr.) 1 Peddapalli- Nizamabad new line (178 Km) 926 2 Jaggayyapeta- Janpahad new line (48 Km) 737 3 Akkanapet – Medak new line (17 Km) 205 4 Bhadrachalam Road-Sattupalli new line (56 Km) 990 5 Raghavapuram-Mandamari Doubling (24 Km) 165 6 Raichur-Guntakal Doubling (81 Km) 388 7 Secunderabad- Mehboobnagar Doubling (85 Km) 1,266 8 Multi- Modal Transport System (MMTS) Phase-II, 1,156 Hyderabad (103 Km) 9 Byepass line at Peddapalli (2 Km) 37 As on 01.04.2025, 20 Railway projects (6 New Lines and 14 Doubling), of a total length of 2,166 Km, costing ₹35,045 crore falling fully/partly in the Contd…3-3- State of Telangana have been sanctioned, out of which, 548 Km length has been commissioned and an expenditure of ₹11,550 crore has been incurred upto March, 2025. The summary is as under:- Category No. of Total Length Total Exp. projects Length Commissioned upto (in Km) till March, March, 2025 2025 (Rs. (in Km) in Cr.) New Line 6 840 245 4,611 Doubling/Multi- 14 1,326 303 6,939 tracking Total 20 2,166 548 11,550 Details of some of the projects falling fully/partly in the State of Telangana which have been sanctioned are as under: S.N Name of Project Cost (Cr) 1 Manoharabad-Kothapalli new line (151 Km) 2,781 2 Malkangiri-Pandurangapuram new line (174 Km) 3,592 3 Kazipet -Vijaywada - 3rd line (220 Km) 3,315 4 Kazipet -Ballarshah - 3rd line (202 Km) 3,183 5 Guntur- Bibinagar Doubling(239 Km) 2,853 6 Mudkhed - Medchal - Dhone Doubling (417 Km) 4,686 7 Bhadrachalam Road – Dornakal Doubling(55 Km) 770 8 Motumari-Vishnupuram doubling and RoR at 1,596 Motumari (100 Km) 9 Nashkal (Pindial)-Hasanparthi Road bypass (25 Km) 465 10 Secunderabad (Sanathnagar)- Wadi 3rd and 4th line 5,012 (173 Km) 11 Dornakal Rail over Rail (RoR) Flyover (11 Km) 327 Pandurangapuram-Bhadrachalam Road are already connected through existing railway network. Contd…4-4- In last 3 years i.e. (2022-23, 2023-24, 2024-25) and current Financial Year i.e.2025-26, 57 surveys (18 New Line and 39 Doubling) covering a total length of 5,665 Km have been sanctioned falling fully/partly in the State of Telangana . Surveys of following works have been sanctioned for preparation of Detailed Project Report: S. No. Name of project 1 Vikarabad–Krishna new line (122 Km) 2 Gadwal–Dornakal via Kalwakurthy new line (316 Km) 3 Kacheguda–Jaggayyapeta new line (250 Km) 4 Patancheru–Adilabad new line (320 Km) 5 Bodhan–Latur Road new line (128 Km) 6 Akkanapet Bypass new line (128 Km) After preparation of DPR, sanctioning of project requires consultation with various stake-holders including State Governments and necessary approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As sanctioning of projects is a continuous and dynamic process, exact timelines cannot be fixed. Sanction of any railway project depends upon many parameters/factors which include the following:  Anticipated traffic projections and remunerativeness of the proposed route  First and last mile connectivity provided by the project  Connection of missing links and providing additional route  Augmentation of congested/saturated lines  Demands raised by State Governments/Central Ministries/Public representatives,  Railway’s operational requirements Contd…5-5-  Socio-economic considerations  Overall availability of funds Execution of important infrastructure projects falling fully/partly in the State of Telangana is held up due to delay in land acquisition. Status of land acquisition in Telangana is as under: Total Land required 2,343 Ha Land Acquired 1,580 Ha (67%) Balance Land to be acquired 764 Ha (33%) Details of some major projects which are delayed due to land acquisition are as under:- SN Name of the project Total Land Balance Amount land acquired Land to Paid to required (Ha) be State (Ha) acquired (Cr.) (Ha) 1. Guntur- Bibinagar 31 0 31 40 Doubling 2. Mudkhed – Medchal 70 0 70 30 & Mahbubnagar – Dhone Doubling 3. Kazipet-Vijaywada 135 118 17 159 3rd Line 4. Manoharabad – 1146 1050 96 - Kothapalli New Line Completion of Railway project/s depends on various factors which include the following:  Land acquisition by State Government  Forest clearance  Shifting of infringing utilities Contd…6-6-  Statutory clearances from various authorities  Geological and topographical conditions of area  Law and order situation in the area of project site  Number of working months in a year for particular project site etc. All these factors affect the completion time and cost of the project/s. *****