GOVERNMENT OF INDIA
MINISTRY OF COAL
LOK SABHA
UNSTARRED QUESTION NO. 2813
ANSWERED ON 05.08.2026
OUTSOURCED COMPANIES ENGAGED BY BCCL AND CCL
2813. Shri Chandra Prakash Choudhary:
Will the Minister of Coal be pleased to state:
(a) the names of outsourcing companies presently engaged by Bharat Coking Coal Limited
(BCCL) and Central Coalfields Limited (CCL) along with the value and duration of each
contract;
(b) the criteria adopted for selection of outsourcing companies along with the details of tenders
awarded during the last three years and the measures taken to assess the impact of
outsourcing on coal production, cost of production, employment generation and safety
standards in BCCL and CCL;
(c) whether any outsourcing companies have been penalised, blacklisted or had their contracts
by BCCL and CCL terminated during the last five years due to non-performance, safety
violations or contractual breaches and if so, the details thereof;
(d) the quantity and quality of coal produced by BCCL and CCL through outsourced operations
vis-à-vis departmental production during the last five years, year-wise; and
(e) the measures taken by the Government to improve efficiency and reduce dependence on
outsourcing while ensuring sustainable coal production?
ANSWER
MINISTER OF STATE FOR COAL AND MINES
(SHRI SATISH CHANDRA DUBEY)
(a): The list of outsourcing contracts engaged in Bharat Coking Coal Limited (BCCL) and
Central Coalfields Limited (CCL) for Coal production along with the value and duration of
each contract is enclosed as Annexure-I & Annexure-II respectively.
(b): Outsourcing agencies in BCCL and CCL are selected through a transparent open
competitive bidding process. The eligibility and qualification criteria prescribed in the Notice
Inviting Tender/ Tender Document are based on the Contract Management Manual and other
guidelines issued by Coal India Limited. Details of tenders awarded during the last three years
are enclosed as Annexure-III and Annexure-IV in respect of BCCL and CCL respectively.
The performance and impact of outsourcing are assessed through periodic contract-wise
monitoring of targeted production vis-à-vis actual achievement, scrutiny of contractual
payments in accordance with tender conditions and monitoring of deployment of manpower.
1Compliance with prescribed employment provisions, including engagement of Project
Affected Persons and local persons, wherever applicable, and payment of High Power
Committee-approved wages to contractual workers is also ensured.
Safety performance is monitored by strict enforcement of the statutory provisions, DGMS
guidelines, mine-specific Safety Management Plans, Principal Hazard Management Plans,
Standard Operating Procedures and Codes of Practice. Regular inspections and safety audits
are conducted by mine management, area and headquarters officials, Internal Safety
Organisation and statutory authorities. Safety training, workshops, awareness drives,
counselling programmes, Pit Safety Committee meetings and monitoring of prescribed safety
features in Heavy Earth Moving Machinery deployed by outsourcing agencies are also
undertaken regularly.
(c): Yes, the detailed list of outsourcing companies that have been penalized, blacklisted,
or had their contracts terminated by BCCL and CCL during the last five years due to non-
performance or contractual breaches is enclosed as Annexure V and Annexure
VI, respectively.
(d): The details of grade-wise coal produced along with production through outsourced
operations vis-à-vis departmental production during the last five years of BCCL and CCL
are enclosed as Annexure VII.
(e): The Government follows a balanced and need-based approach for improving
efficiency and ensuring sustainable coal production. Coal projects are implemented through
departmental operations, outsourcing mode or through the Mine Developer-cum-Operator
model, depending on technical feasibility, geological conditions, financial viability and
resource availability.
Outsourcing is used to supplement the capabilities of coal companies and provide access to
specialized technology and expertise. However, ownership, mine planning, safety, statutory
compliance, environmental management and overall operational control remain with the
concerned coal company.
Efficiency is being improved through digital monitoring, Integrated Command and Control
Centres, GPS- and drone-based systems, First Mile Connectivity projects, high-capacity
equipment, surface miners and mass production technologies. These measures strengthen in-
house capabilities, improve productivity and safety, reduce costs and support sustainable coal
production.
****
2Annexure-I
Contra
ct
Name of Award Value as per Name of Period
Name of Patch Details of LOA Remarks
the Area Award (INR) Contractor as per
award
(days)
Leftout OC
BCCL/GM/CMC/F-LOA/Patch-B Dhansar
Patch-B of
PHULARITAND/2015/1464 DATE Engineering Co. 2190
Phularitand 4,559,230,715.00
11/12/2015 Pvt.Ltd.
Colliery
Muraidih
Section (Patch
4th A),
BCCL/CMC/H-HEMM-55/Patch-4th A-
Amalgamated M/s SUPL JV 1460
Barora/2021/180 Date: 21.05.2021 2,238,316,230.83
Muraidih
Barora
Phularitand
Colliery
Patch -7,
Phularitand
Section of
BCCL/CMC/78/Patch-7/LOA/Barora/2023/ M/s Sanjay Udyog
Amalgated 1460
181 Date: 20.04.2023 3,653,662,472.77 Pvt. Ltd
Muraidih
Phularatand
Colliery
New Benedih
BCCL/CMC/H-HEMM-44/LOA/New
Patch of Ambey Mining
Block -II Benidih/Block-II/2020/352 Dtd. 2190
Amalgamated 8,022,693,883.82 Pvt. Ltd.
20/10/2020
Block-II OCP
3“NEW
NUDKHURK
BCCL/CMC/71/New Nudkhurkee
EE PATCH” M/s Khemka
Patch/LOA/Block II/2022/483 Date: 1460
at 2,563,918,149.04 Carriers
18.10.2022
Amalgamated
Block II OCP
mining charge for
delivery of coal in
dump=Rs.
BCCL/CMC/Highwall/ABOCP/LOA/BLO
BlocK-II 1422.99/te, Mining M/s DECO-GCPL
CK-II/2022/490 2555
Highwall charge for delivery (JV)
Dated-26.10.2022
of coal to
NMCW=Rs.1467.9
9/te
Patch H, New BCCL/CMC/68/Patch-
M/s STG DECO
Akashkinaree H/LOA/Govindpur/2022/577 Date: 1825
4,963,881,963.26 JV
Colliery 29.12.2022
BCCL/CMC/77/Patch-
Patch-D of M/s Sagar
D/LOA/Govindpur/2023/64 Date: 1095
ABG Colliery 1,059,659,586.35 Infrastructure
14.02.2023
Patch-A of बीसीसीएल/सी.एम.सी./87/Patch-
M/s GAIPL-CRN
Govindp Jogidih A/Jogidih/Govindpur/LOA/2024/1618-38 150,53,78,379 1825
(JV)
ur Colliery दिन ांक: 15.07.2024
M/s
बीसीसीएल/सी.एम.सी./88/Patch-
Patch-C of VISHNUSHIVA
C/Govindpur/LOA/2024/2902-2919 2555
ABG Colliery 3,146,358,685.91 INFRASTRUCTU
दिन ांक:03.12.2024
RE
Patch-M1 of
बीसीसीएल/सी.एम.सी./90/Patch
M/s SIRI INFRA -
Maheshpur M1/Govindpur/LOA/2024/2920-2937 2190
5,137,877,446.00 ARETPL (JV)
Colliery दिन ांक:03.12.2024
412.02 %
KHARKHAR
BCCL/CMC/MDO- Revenue
EE COAL M/s HILLTOP
RS/LOA/KHARKHAREE/GOVINDPUR Not Applicable Sharing
MINE HIRISE PVT.LTD
AREA/2023/189 Date: 25.04.2023 Basis, 25
(MDO)
Years
Kantapahari
Patch-II of BCCL/GM/CMC/F-LOA/HEMM
DECO-AMPL-
AKWMC Kantapahari Patch-II/2014/3283 Date: 2920
8,058,718,182.00 BKB(JV)
Colliery and 05.11.2014
AARC
Tetulmari
BCCL/CMC/H-
patch BSMCPL-BEPL
HEMM/AAK/LOA/AKWMC/Tetulmari 2190
AKWMC 2,650,389,024.00 JV
Patch/Katras/2020/253 Date: 31.07.2020
Colliery
Patch B of
Katras-
Katras Choitodih
Section of BCCL/CMC/H-HEMM/AAK/LOA/Patch Dhansar
Amalgamated B Choitodih/AGKCC Katras/2020/254 Engineering Co. 1825
3,999,923,063.00
Gaslitand Date: 31.07.2020 Pvt.Ltd.
Katras
Choitodih
Colliery
M/s R K
9% Revenue
SALANPUR- BCCL/CMC/MDO-RS/LOA/SALANPUR- TRANSPORT CO
Sharing
AGKC AGKC/KATRAS AREA/2023/130 Date: Not Applicable (SPV: R.K
Basis, 25
(MDO) 21.03.2023 Transport Coal
Years
Mine Pvt. Ltd)
BCCL/GM (CMC)/F-LOA/HEMM
S. Bansjora
Sijua SENDRA BANSJORA PATCH- Saakar-Mass JV 2190
Patch-X 3,877,836,109.00
X/2014/1909 dated 27.01.2014
5Tetulmuri
BCCL/CMC/F-LOA/Tetulmuri Patch
(Patch-A) of M/S Hilltop Hirise
A_Mudidih_Sijua/2018/269Date: 1825
Mudidih 3,928,631,762.50 Pvt. Ltd
04.05.2018
Colliery,
Patch D, BCCL/CMC/H-HEMM-56/LOA/Patch-D
M/s RAM AVTAR
Kankanee Kankanee/Sijua/2021/ 129 Date: 2555
9,570,110,082.37 - EIPL (JV)
Colliery 19.03.2021
PAHARI M/s Chennai
BCCL/CMC/79/Pahari
Patch of Radha Engineering
Patch/LOA/Sijua/2023/190 1825
Tetulmari 3,137,964,924.48 works Private
Date: 27.04.2023
Colliery Limited
बीसीसीएल/सी.एम.सी./84/Beldari
Beldari Patch
Patch/Sijua/LOA/2024/97-116 दिन ांक: M/s SNR-
of Tetulmari 1095
819,790,164.50 CRN(JV),
15.01.2024
Colliery
Patch "C" of
amalgamated
Sendra
बीसीसीएल/सी.एम.सी./HEMM-102/Patch-C M/S BLA
Bansjora
/SIJUA/LOA/2026/581-614 दिन ांक: 126,83,17,582.17 INFRASTRUCTU 540
Nichitpur
30.03.2026 RE PVT LTD
Colliery,
(ASBNC) of
Sijua Area
R. K Earth
BCCL/GM(CMC)/F-LOA/H-
Ena Patch Resource Limited
Kusunda HEMM/Patch-DE_Mega 2555
DE(Mega) 20,435,393,000.00 (Previously Known
Project_Kusunda/2015/743 dtd. 30.05.2015
as R.K. Transport)
6Patch-R, of
Gondudih- BCCL/CMC/HEMM/LOA/ Gondudih- Hilltop Hirise Pvt.
2190
Khas-Kusunda Khas-Kusunda/2019/443 dated. 24.10.2019 4,908,341,803.78 Ltd.
Colliery
E.Bassuriya,
BCCL/CMC/62/Patch-C East
OC Patch-C M/s Khemka
Basuria/LOA/Kusunda/2022/454 Date: 790
(Quantity 935,346,469.00 Carriers
01.10.2022.
exhausted)
Patch-P of
Amalgamated BCCL/CMC/73/Patch
M/s SNR-SI-VSA
Dhansar P/LOA/Kusunda/2023/115 Date: 1185
1,979,157,294.44 (JV),
Industry 15.03.2023
Colliery
Patch “E”
under New M/s RA MINING
बीसीसीएल/सी.एम.सी./94/Patch
Godhur 141,80,17,468.86 PRIVATE 1095
E/Kusunda/LOA/2025/41 दिन ांक: 12.02.2025
Kusunda LIMITED
Colliery
Patch-E of
बीसीसीएल/सी.एम.सी./HEMM-98/Patch-E
East Bassuria M/s SATYAM
EBC/Kusunda/LOA/2025/1689-1710 91,04,86,437.19 1095
Colliery, INFRA
दिन ांक:07.10.2025
Kusunda Area
Fire Patch of
BCCL/CMC/72/Fire Patch /LOA/PB M/s SNR-SI-VSA
Gopalichuk 1095
/2022/581 Date: 30.12.2022 2,119,916,810.27 (JV),
Colliery
Patch B
BCCL/CMC/70/Patch-B/PB/LOA/2023/56 M/s STG
PB Gopalichulk 730
Date: 06.02.2023 710,271,570.80 ASSOCIATES
Colliery
Hired HEMM
बीसीसीएल/सी.एम.सी./95/Phase-IV /PB M/s TBEPL-
Patch Phase- 849,25,20,187.22 2190
/LOA/2025/144 दिन ांक:12.06.2025 NSIPL (JV)
IV of
7Kendwadih
Colliery
South Jharia BCCL/GM(CMC)/FLOA/S.Jharia
AMR-Devprabha
OC Patch of OCPatch_ROCP_Bastacolla/2018/117 1825
8,034,277,602.00 Consortium
ROCP Date:12.03.2018
The Mining
Rajapur
charge is Rs.
OCP/SJ BCCL/CMC/Highwall/Rajapur-
Devprabha-GCPL 1905.57 /- per
Colliery SJ/Bastacolla/LOA/2023/325 Not Applicable 2555
JV Tonne
Date:23.08.2023
(excluding
HighWall
GST)
बीसीसीएल/सी.एम.सी./89/BOCP-
Bastacol Bastacolla M/s VMIPL-C5
II/Bastacolla/LOA/2024/2515-36 S 2190
la OCP-II 18,658,834,936.65 Engineering (JV)
दिन ांक:15.10.2024
NC Patch-III M/s SINGH
(Left out of बीसीसीएल/सी.एम.सी./93/NC Patch NATURAL
NC Patch II) III/Bastacolla/LOA/2025/18-37 RESOURCE 730
913,256,824.00
of ABDKC/ दिन ांक:02.01.2025 PRIVATE
KOCP LIMITED
Ghanoodih
बीसीसीएल/सी.एम.सी./HEMM-97/ Patch-
OC Patch- A, M/S MNSR-GSCO
A/Bastacolla/LOA/2025/388 दिन ांक: 2190
Bastacolla 17,545,224,462.92 (JV)
24.11.2025
Area
Mega Patch
BCCL/GM/CMC/F-LOA/Mega Patch-
‘D’ of Sushee Infra Pvt.
Lodna D_Joyrampur_LodnaArea/2015/818 Date: 2920
Joyrampur 41,946,080,377.00 Ltd.
13.06.2015
Colliery
8BCCL/CMC/H-HEMM-45/LOA/Kujama M/s Devprabha
Kujama OC
Patch G/Lodna/2020/420 Date: Construction Pvt. 2555
Hired Patch-G 5,603,303,086.06
04.12.2020 Ltd.
Rs.
M/S DCPL-GCL
1898.55per
ConsortiumDevpra
NT-ST Tonne
BCCL/CMC/MDO/NTST/LODNA/LOA/2 bha Mining &
Kujama OCP Not Applicable 9125 Mining
023/341 Dated- 18.09.2023 Infra Private
MDO Charge
Limited (Mine
Basis(Excludi
Operator)
ng GST)
Eastward
Extension of BCCL/CMC/80/Fire Patch-
M/s STG
Fire Patch-A A/EJ/LOA/2023/248 1825
1,886,082,082.36 ASSOCIATES
of A.S.P Date: 02.06.2023
EJ Colliery,
Mega C-2
BCCL/CMC/82/Mega C-2
Patch of Devprabha Const.
Patch/EJ/LOA/2023/2479-2500 2920
Bhowra (N & 24,140,406,818.74 Pvt Ltd.
Dated: 23.08.2023
S) Colliery
Sabanpur
बीसीसीएल/सी.एम.सी./85/Sabanpur
Patch, M/s RA Mining
Patch/CV/LOA/2024/1219 दिन ांक: 1095
Damagoria 1,511,981,773.48 Private Limited
05.06.2024
Colliery
CV
Borira Patch-
बीसीसीएल/सी.एम.सी./86/Borira Patch-
A (Extension) M/s RA Mining
A/CV/LOA/2024/1218 दिन ांक: 05.06.2024 1278
of Damagoria 3,056,370,027.07 Private Limited
Colliery
9Annexure-II
Details of Running CCL Contracts
Value of
Name of
Contract/Award Period of
SN Mine / Name of Contractor
Value (incl. 18% Contract
Project
GST in Rs.)
(2915 days) from
Amrapali M/s NCC limited 80,58,14,85,777.00 21.12.2025 to
13.12.33
17.02.26 to upto
25 yr ( 3 MT
Chandragupta target for
M/s Sushee Infra 95,08,61,53,216.86
MDO FY2026-27) coal
1 started from
21.03.26
10-04-26 to 09-
Amrapali M/S VCPL 1,01,06,30,391.50
04-27 (1 year)
1095 days
Amrapali M/s JTPL SIPL JV 2,50,09,54,948.24 (08.06.26 to
07.06.29)
Total AC Area 1,79,17,92,24,333.60
M/S VPR BGR PLR 06.11.19 to
40,53,60,50,000.00
Con. 05.11.27
23.02.23 to
M/s Jai Ambey
3,03,17,93,711.68 22.02.26 extn to
Roadlines
22.02.27
M/s United Coal 07.11.25 to
4,96,51,40,826.58
Magadh Carriers 06.11.28
M/s KS MAHADEV 95,07,55,895.63 16.8.24 to 15.8.27
2 04.06.23 to
M/s R K Transport Pvt.
47,40,86,995.20 03.06.26 extnded
Ltd.
till 29.11.27
M/s Ravindra 01.05.25 to
14,26,33,575.22
Enterprises 30.04.27
TOTAL MS AREA 50,10,04,61,004.31
M/s PLR Projects P Ltd 4,47,93,87,500.00 15.6.19 - 22.10.26
03.09.23 to
Kaartik Mining JV 2,80,04,89,726.07 02.09.25 Extn.
Upto 06.11.26
Ashoka OCP,
14.06.24 to
3 Piparwar M/s Jai Ambey
81,09,90,126.24 13.06.26 extn to
Area Roadlines
10.12.26
M/s Jai Maa Ashtabhuji
22.01.26 to
Construction (Stock to 1,35,00,394.75
24.08.26
CHP)
10M/s Shree Enterprises 18.08.22 to
17,34,41,606.51
(Wagon Loading) 06.01.27
TOTAL PIPARWAR AREA 8,27,78,09,353.57
18.07.21 to
AKK OCP M/s KSML JV 7,79,63,75,196.32
17.07.27
BKB Transport Pvt. 03.07.20 to
Karo OCP 4,28,94,77,000.00
Ltd. 01.07.27
20.12.25 TO
Karo OCP DCCPL-RKTCL(JV) 3,79,90,85,839.34
18.12.29
14.12.22-12.12.25
Bokaro OCP M/s RKT Pvt. Ltd. 7,68,36,762.00
extn till 14.01.27
19.11.23 to
AKK OCP M/s Dadan Singh 82,89,20,504.72
16.11.28
M/S RK Transport Pvt. 24.02.2025 to
AKK OCP 8,89,32,975.04
Ltd. 23.02.2027
05.07.20 to
Karo OCP M/S BKB Tpt P Ltd 18,65,79,240.00 03.07.25 Extn.
Till 12.09.28
09.12.25 to
Karo OCP M/s DSAT JV 10,43,55,189.18 22.07.26 extn till
21.10.26
26.06.26 to
Karo OCP M/s Shyam Transport 6,57,80,952.60
25.06.27
M/s Variant 06.05.26 to
AKK OCP 6,14,20,873.84
Commercial Pvt Ltd. 02.11.26
M/s Variant 13.06.26 to
AKK OCP 2,43,53,784.00
Commercial Pvt Ltd. 09.09.26
08.12.25 TO
Karo OCP M/s DSAT JV 6,73,56,465.00
07.12.27
4 Jarangdih M/s Radhika
11-02-2025 to 10-
Railway Infrastructure (Wagon 6,00,03,332.76
02-2028
Siding Loading)
Jarangdih 09.05.19 to
M/s NKAS Services
Railway 17,43,04,290.00 08.05.24 extns.
(Wagon Loading)
Siding Till 09.07.27
Konar M/s RKTPL-RLCTPL 09.12.21 to
Railway JV (Wagon 6,99,28,452.00 07.12.24 extn.
Siding Loading) Till 23.11.26
TOTAL
17,69,37,10,856.80
B&K AREA
M/s RA Mining Pvt. 02.09.23 to
Sayal D 4,89,42,88,481.49
Ltd. 01.09.31
5
Bhurkunda M/s BLA Infrastructure 05.06.26 to
2,63,97,68,796.00
OCP Pvt. Ltd. 04.06.30
11M/s ASHIRBAD REAL
ESTATE & 26.08.24 to
Urimari OCP 1,96,26,51,324.18
TRANSPORT PVT. 25.08.27
LTD.
North
M/s Kaartik Mining 17.10.24 to
Urimari 15,70,05,43,911.32
(JV) 11.10.34
(Birsa) OCP
Birsa Dept. M/s Jai Mahalaxmi 07.06.24 to
2,99,56,989.46
stock Transport Company 06.06.27
Urimari OS M/s Jai Maa Kali 20.06.26 to
69,18,768.58
stock Transport Co. 17.09.26
Urimari Dept. M/s Jai Maa Kali 15.11.2024 to
8,56,25,130.67
Stock Transport Co. 14.11.27
M/s ASHIRBAD REAL
ESTATE &
Biirsa OS 17.05.26 to
TRANSPORT PVT 2,58,93,512.20
stock 16.11.26
LTD
(Nomination Basis)
Birsa Dept. M/s Jai Mahalaxmi 07.10.25 to
1,02,14,708.94
Stock Transport Company 06.10.26
Crusher
M/s Jai Maa Kali 30.12.23 to
Saunda-B 18,26,91,300.48
Transport Co. 29.04.27
Siding
North
M/s Jai Mahalaxmi
Urimari 20.05.25 to
Transport Company 5,90,20,955.06
Railway 19.09.28
(Wagon Loading)
Siding
North
M/s Jai Maa Kali 04.11.23 to
Urimari
Transport Co.(Wagon 5,52,92,588.21 03.11.25 extn.
Railway
Loading) Till 03.11.26
Siding
Saunda-B M/s Shri Shyam
07.08.23 to
Railway Transport Co. (Wagon 8,22,90,432.19
06.08.26
Siding Loading)
TOTAL BS
25,73,51,56,898.78
AREA
Dhori Khas M/s Ravindra 05.02.2024 to
8,99,42,975.80
UG Enterprises 03.02.2027
M/s Bhagwati Raj Rani 12.12.2021 to
2,41,31,89,125.40
Ventures JV 10.12.2026
M/s JAI MA TARA
25.03.26 to
PROJECTS 15,92,77,883.68
21.06.28
(Wagon loading)
M/s JAI MA TARA 11.06.26 to
1,88,19,171.00
PROJECTS 08.10.26
M/s Ravindra 20.01.2023 to
29,99,26,000.00
Enterprises 18.01.2028
6 AADOCM
19.08.2023 to
Jai Balajee 9,22,52,000.00
17.08.2026
12M/s R.K.Transport 03.10.2024 to
38,34,45,258.13
Pvt.Ltd 04.10.2027
M/s RA Petrochemicals 18.10.25 to
6,48,89,407.80
Pvt Ltd 17.10.26
14.11.2024 to
M/s Uber Mining
69,49,48,053.92 14.05.2026 ext
Pvt.Ltd
06.07.2027
18.09.2023 to
M/s Variant
16.09.2026 extn.
Commercial Pvt Ltd 16,46,28,011.52
Upto
(Wagon Loading)
05.05.2027
M/s Pramod Kumar 17.01.2024 to
3,14,23,000.00
Singh 15.01.2027
SDOCM 28.11.2024 to
M/s R.K.Transport
8,54,39,098.00 29.05.2026 ext
Pvt.Ltd
25.04.2027
M/s BKB Transport Pvt (16.08.25-
69,34,94,000.00
Ltd 15.08.26)
M/s Maa Kamakhya 25.03.2026 to
15,95,00,310.19
Traders 21.08.2026
TOTAL DHORI AREA
5,35,11,74,295.44
M/s Krishna 28.06.26 -
Giridih 81,57,75,956.55
Infrastructure 27.06.30
19.10.23-
Kabribad M/s Amba Lal Patel 1,02,10,34,878.18
18.10.29
7
M/s Sonmati 24.10.25 to
Kabribad 2,45,21,403.00
Constructiuon 23.10.30
Pramod Kumar Singh 06.02.24 to
Kabribad 2,00,65,377.02
(Wagon Loading) 04.02.27
TOTAL GIRIDIH AREA
1,88,13,97,614.75
26.03.2025 to
Tapin South 25.03.2026
M/s NEPL-CRN JV 24,89,15,223.12
OCP (extended till
07.09.2026)
Tapin North 06.04.2026 to
M/s JARLPL-AT 3,79,19,78,502.58
OCP 05.04.2031
10.01.2025 to
Kedla OCP M/s Vishnushiva Infra. 2,03,40,89,333.29
09.01.2030
Jharkhand 13.02.2026 to
M/s Shiv Enterprises 31,41,01,686.51
OCP 12.02.2027
Tapin North M/s Rajeev Transport 01.06.2025 to
44,82,12,262.00
OCP Coal Agency (RTCA) 30.05.2028
Tapin North M/s Jai Maa Tara 10.03.2026 to
92,97,708.23
OCP Projects (JMTP) 09.03.2027
8
Jharkhand M/s KMAG 20.05.2025 to
3,77,01,977.04
OCP INTERNATIONAL 19.05.2027
13M/s Jai Balajee
Jharkhand 06.05.2026 to
Transport Company 11,83,81,007.25
OCP 15.05.2028
(JBTC)
M/s Jai Balajee
Parej East 24.09.2025 to
Transport Company 23,74,17,433.11
OCP 23.09.2028
(JBTC)
M/s Ravindra
Tapin South 01.05.2024 to
Enterprises (Wagon 6,85,37,316.96
OCP 30.04.2027
loading)
Kedla 22.01.2026 to
M/s Shai Transporter 76,45,68,315.00
Washery 20.01.2031
Kedla M/s Vikhyat Raj 26.10.2025 to
8,60,06,654.10
Washery Logistic (crushing) 24.10.2030
Kedla M/s Rajeev Transport 23.01.2026 to
39,18,00,828.00
Washery Coal Agency (RTCA) 22.01.2028
Kedla M/s Rajeev Transport 08.06.26 to
13,32,54,450.00
Washery Coal Agency (RTCA) 05.09.26
TOTAL HAZARIBAGH AREA 8,68,42,62,697.19
18.02.21 to
18.02.26
Tetariakhar M/S PRANABNAMAN
1,10,10,89,865.48 (Extn. Upto
OCP MINERALS PVT. Ltd.
30.06.26 further
extn till 31.12.26)
9
Tetariakhar 17.06.26 to
M/S PNM and KNS 2,99,99,72,342.34
OCP 13.06.36
(3 Yr Contract)
M/s RA Petrochemicals
Rajhara OCP 31,25,39,018.90 01.12.25 to
Pvt. Ltd.
29.11.28
TOTAL RAJHARA AREA 4,41,36,01,226.72
07.03.2026 -
M/s BKT-PMIW JV 86,92,86,854.89
04.09.2027
M/s Jai Balajee 04.06.2026 -
Kathara OCP 2,96,00,723.86
Transport Company 28.02.2027
M/s Pramod Kumar 13.06.2025 -
2,92,50,282.62
Singh 04.12.2026
M/s Krishna 03.07.2024 -
1,69,62,96,353.94
Infrastructure 01.07.2030
M/s Jai Ma Tara 01.09.2023 -
41,16,87,351.48
Projects 27.12.2028
10
04.11.2023 - to
Jarangdih M/s Maa Kalka Coal & 07.11.2026,
6,66,68,153.46
OCP Minerals(JV) extended upto
07.02.2028
M/s Jai Mahalaxmi 19.07.2025 to
2,36,65,225.68
Transport Company 18.07.2027
M/s Aakar Engineers & 02.07.2026 to
1,65,08,500.88
Contractors 28.12.2026
GVP Ph-II 15.02.2026 to
M/s BKT-PMIW JV 84,86,17,968.15
OCP 13.08.2027
14M/s Pandaveswar
24.05.2026 to
Mining & Industrial 83,31,49,864.29
19.09.2029
Works
Sawang 24.02.2026 to
M/s Ravinder Kumar 1,20,00,600.00
Washery 23.02.2028
TOTAL KATHARA AREA 4,83,67,31,879.25
28.03.24 to
M/s Krishna 27.06.29 (5
Chainpur OC 40,23,79,526.25
Infrastructure YEARS 3
MONTHS)
M/s Nilkanth Infra
Pundi 30,06,37,24,892.80 4740 DAYS
Mining Limited
1640 days
Karma oc Ms JARLPL-AT 1,27,42,09,772.12 (03.04.26 to
28.09.30)
1 year
TOPA OC M/s Shiv Enterprises 14,80,96,022.80 (21.01.2026 to
20.01.2027)
M/s Jai Mahalaxmi 14.09.25 to
Topa OC 6,72,79,785.65
11 Transport 13.09.27
31.05.26 to
Topa OC M/s DDG Associates 16,21,42,478.40
09.06.29
04.03.23 to
M/s RSSG Cons. Pvt
Karma oc 39,63,27,570.43 30.06.26 extn
Ltd
23.01.27
21.05.26 to
Karma oc MS Shai Transporter 19,85,09,110.80
27.08.29
Chainpur M/s Fairdeal Project 25.07.25 to
14,18,84,332.80
OCP Pvt. Ltd. 24.07.29
15.04.2025 to
M/s Jai Maa Kali
Topa OC 10,88,18,196.23 14.04.2029
Transport Co.
(04Years)
TOTAL KUJU AREA 32,96,33,71,688.28
M/s JMS Mining 24.03.19 to
Churi UG 5,68,04,00,000.00
Services Pvt. Ltd. 23.03.28
3 Yr [24-02-2025
Rohini OC M/s Shila Enterprises 13,19,94,992.34
to 08-02-2028]
M/s Srimanth Mining 14.08.2024 to
Dakra Stock 46,08,684.11
LLP 13.08.2027
M/s Variant 01.01.24 to
Churi UG 27,59,19,580.78
Commercials Pvt. Ltd. 29.12.28
12
21.01.25 to
Dakra OCP M/s Jai Maa Kali 3,62,16,222.72
08.08.27
M/s Variant
17.02.26 to
KDH Commercials Pvt. Ltd. 69,63,746.40
15.08.26
(Wagon loading)
M/s Jai Maa Ashthbhuji
05.03.26 to
Dakra Siding Construction (Wagon 2,66,57,681.88
03.03.28
loading)
15M/s Sainik Mining & 9 yr (LoA issued
Purnadih 4,18,32,85,419.31
Allied Services Ltd. 05.10.24)
TOTAL NK AREA 10,34,60,46,327.54
M/s Jai Mahalaxmi 25.08.2025 to
3,98,90,000.00
Transport Co. 24.08.2027
M/s Jai Ma Tara 23.04.2024 to
Giddi- A 15,55,96,500.00
Projects 22.04.2027
24.12.2021 to
M/s RKT-BKB JV 5,23,20,700.00
23.12.2026
13 M/s Classic
28.01.2026 to
Religara OCP Secureshield Private 12,59,80,000.00
27.01.2028
Limited
07.09.2024 to
M/s Deoraj Singh 38,13,76,000.00
06.01.2028
Sirka OC
M/s Krishna 14.02.2025 to
60,90,36,570.00
Infrastructure 13.02.2028
M/s Shri Shyam 06.10.24 to
Giddi-C 22,40,04,990.00
Transport Co. 05.10.28
TOTAL ARGADA AREA 1,58,82,04,760.00
13-12-2023 to
Rajrappa OC M/S MKT-SIPL JV 1,42,22,78,659.68 12-12-26 Extn.
Till 06.05.27
M/s Fairdeal Projects P 07.07.25 to
Rajrappa OC 36,70,30,308.00
14 Ltd. 03.11.27
M/s Fairdeal Projects P 15.05.24 to
Rajrappa OC Ltd.(Wagon 2,11,95,820.80 14.05.26 Extn.
loading) Till 14.11.26
TOTAL RAJRAPPA AREA 1,81,05,04,788.48
Total Award value of running contracts in
3,52,86,16,57,724.71
CCL (in Rs.)
16Annexure-III
Contract awarded to Outsourcing Agencies since FY 23-24 to till date
Sl. Name of Awarded value
Name of Work LOA No. Duration
No. Contractor (in Rs)
Hiring of equipment for
removal of OB and
extraction and M/s Chennai
transportation of coal from Radha
BCCL/CMC/79/Pahari
1 VII, V/VI, IV, III, II Top, Engineering 313,79,64,924.48 1825 days
Patch/LOA/Sijua/2023/190 27/04/2023
II Middle seams of works private
PAHARI Patch of limited
Tetulmari Colliery, Sijua
Area BCCL.
"Re-open, salvage,
rehabilitate, develop,
construct and operate for
25
excavation/ extraction of M/s Hilltop BCCL/CMC/MDO- FY:2023
@ 12.02 % (Twenty
2 coal from Kharkharee Hirise Pvt. RS/LOA/KHARKHAREE/GOVINDPUR -24
Revenue share Five)
Coal Mine and delivery Ltd. AREA/2023/189 25/04/2023
years
thereof to the Authority”
at Govindpur Area of
BCCL.
"Hiring of equipment for
removal of OB, extraction
and transportation of Coal
M/s Sanjay
from seamn XI/XIL, BCCL/CMC/78/Patch-
3 Udyog Pvt. 365,36,62,472.77 1460 days
IX/X, VIIIC, VIIIB, VIIIA 7/LOA/Barora/2023/181 20/04/2023
Ltd.
& V/VI/VII (Combined)
at Patch-7, Phularitand
section of Amalgamated
17Muraidih Phularitand
Colliery, Barora Area of
BCCL."
"Setting up of
Sand/aggregate (Agreed
Segregation Plant (OB to Facilitation
M/s
sand/aggregate) of OB Charge) offered by
END2END
throughput capacity 1.10 bidder which is Rs BCCL/CMC/OB_TO_SAND/LOA/2023/
4 URJA 2555 days
Mtpa at Damoda OCP, 72.57/t of OB 182 21/04/2023
SOLUTIONS
Barora Area, BCCL on provided by
PVT LTD
Build-Operate (BO) BCCL, exclusive
concept" for a period of of GST
2555 days.
"Hiring of equipment for
removal of OB and
extraction and
transportation of coal with
M/s STG
FireFighting from VIIIA, BCCL/CMC/80/Fire Patch-
5 ASSOCIATE 188,60,82,082.36 1825 days
IX/X & XI/XII seams in A/EJ/LOA/2023/248 02/06/2023
S
the Eastward Extension of
Fire Patch-A of A.S.P
Colliery, E.J. Area,
BCCL"
18Contractual Unloading
(Mechanical cum manual)
of coal from the rake of
BOXN wagons within
railway free time, loading
of coal (unloaded from M/s BCCL/CMC/TPTN
6 BOXN wagons) into AGARWAL 8,44,61,004.00 58/WASHERY/LOA/2023/283 300 days"
tippers and transporting & CO 12/07/2023
the same to Patherdih
NLW Washery Raw Coal
Tube stacker or raw coal
hopper for a period of 300
days".
Introduction of Highwall
Mining technology at
Rajapur OCP/SJ Colliery
of Bastacolla Area of
Mining charge @
BCCL" (the Project) M/s 7 (seven)
Rs. 1905.57 per BCCL/CMC/Highwall/Rajapur-
7 through a Mine Operator Devprabha - accounting
Tonne (excluding SJ/Bastacolla/LOA/2023/325 23/08/2023
for extraction of Coal and GCPL JV years
GST).
delivery Operator for
extraction of Coal and
delivery
thereof to the Authority
Hiring of Equipment for
removal of overburden
and Extraction and M/s
BCCL/CMC/82/Mega C-2
Transportation of coal Devprabha
8 2414,04,06,818.74 Patch/EJ/LOA/2023/2479-2500 2920 days
with firefighting from Construction
23/08/2023
XIV, XIII, XI/XII, X, IX, Pvt. Ltd.
VIII and VII seams of
proposed Mega C-2 Patch
19of Bhowra (N & S)
Colliery, E J Area."
Transportation of coal
from different sources to
different destination
including crushing and M/s
BCCL/CMC/TPTN59/Barora/LOA/2023/
9 allied jobs under KHEMKA 151,03,25,881.50/- 1827 Days
342 19/09/2023
Amalgamated Muraidih CARRIERS
Phularitand Colliery of
Barora Area, BCCL for a
period of 1827 Days".
"Re-open, salvage,
rehabilitate, develoр,
construct and operate for
BCCL/CMC/MDO- 25(Twenty
excavation/ extraction of M/s IMA @5.40 % Revenue
10 RS/LOA/MADHUBAND/BARORA/202 Five)
coal from Madhuband Consortium share
3/343 19/09/2023 years
Coal Mino and doliveny
thareof to the Authority" at
Barora Area of BCCL.
20OPERATION AND
MAINTENANCE FOR
THE EXISTING
LONGWALL PACKAGE
AT MOONIDIH XVI
SEAM FOR
EXTRACTION OF
COAL FROM XVT
SFAM AT MOONIDTH
UNDERGROUND
PROJECT ON COST M/s INDU AC @ Mining charge BCCL/CMC/Moonidih XVI Seam/W J 06(Six)
11
PER TONNE BASIS Consortium of Rs 1980/tonne AREA/LOA/2023/344 19/09/2023 APPS
INCLUDING SUPPLY
OF
SPARES,REFURBISHM
ENT, OVERHAUL &
REPAIR OF THE
LONGWALL
EQUIPMENT DURING
THE CONTRACT
PERIOD" AT W J AREA
OF BCCL.
21Development and
operation of Amalgamated
NTST Kujama OCP (the
"Project") and extraction
25
of coal from IX/X,VIIIA,
(Twenty
V/VI/VII/VIII group
Five)
(V/VI,VII.V/VI/VII,VIII.
accounting
V/VI/VII/VIII). IVT, M/s DCPL-
BCCL/CMC/MDO/NTST/LODNA/LOA/ years as
12 IVB,IIIT,IIIB,III,IIT,II,II GCL Mining charge
2023/341 18/09/2023 per the
B,I seams and removal of Consortium
Annual
overburden by Shovel -
Production
Dumper combination,
Programm
construction and
e
Operation of Coal
Handling Plant and
Railway
Siding as per Agreement"
RE-OPEN, SALVAGE,
REHABILITАTЕ,
DEVELOP,
CONSTRUCT AND
OPERATE FOR
M/s 25
EXCAVATION/ BCCL/CMC/MDO-
MANGALAM @ 4.10 % (Twenty
13 EXTRACTION OF RS/LOA/AMLABAD/EJ/2023/367
CONSORTIU Revenue share Five)
COAL FROM 10/11/2023
M years
AMLABAD COAL
MINE AND DELIVERY
THEREOF TO THE
AUTHORITY" at EJ Area
of BCCL.
22Hiring of Equipment for
removal of overburden
and Extraction and
Transportation of coal BCCL/CMC/84/Beldari
M/s SNR-
14 from VIIIA, VIII, VII, 81,97,90,164.50 Patch/Sijua/LOA/2024/97-116 1095 days
CRN(JV)
V/VI & IV seams by 15/01/2024
opencast method from
Beldari Patch of Tetulmari
Colliery, Sijua Area."
"Re-open, salvage,
rehabilitate, develop,
construct and operate for
excavation/ extraction of M/s 25
BCCL/CMC/MDO-
coal from Amalgamated Devprabha 15.30 % of (Twenty
15 RS/LOA/AEBS/Bastacolla/2024/126
East Bhuggatdih Construction Revenue share Five)
10/06/2024
Simlabahal Coal Mine and Pvt Ltd. years
delivery thereof to the
Authority" at Bastacolla
Area of BCCL.
Transportation of coal
FY
from different Sources to
2024-25
different destinations and
allied jobs at BCCL/CMC/TPTN 61/BLOCK-
16 M/s DMPT JV 38,02,01,258.36 1186 Days
Amalgamated Block II II/LOA/2024/122 05/06/2024
0CP Mine, Block II Area
of BCCL for a period of
1186 Days".
Hiring of HEMM for
removal of OB and M/s RA
BCCL/CMC/86/Borira Patch-
17 extraction & Mining Private 305,63,70,027.07 1278 days
A/CV/LOA/2024/1218 05/06/2024
transportation of Coal Limited
from Laikdih (Top),
23Laikdih (Middle), Laikdih
(Bottom), L-11, L-10,
Salanpur C, Salanpur D
seams of Borira Patch-A
(Extension) of Damagoria
Colliery under
Kalyaneshwari OC, CV
Area.
Extraction and
Transportation of coal and
Removal of Overburden
by Hiring of HEMM and M/s RA
BCCL/CMC/85/Sabanpur
18 by Ripper Mining at Mining Private 151,19,81,773.48 1095 days
Patch/CV/LOA/2024/1219 05/06/2024
Proposed Sabanpur Patch, Limited
Damagoria Colliery under
Kalyaneshwari OC under
CV Area.
Hiring of HEMM for
removal of OB and
extraction &
transportation of Coal BCCL/CMC/87/Patch-
M/s GAIPL-
19 from VIIIB, VIIIА, 150,53,78,379 A/Jogidih/Govindpur/LOA/2024/1618-38 1825 days
CRN (JV)
V/VI/VII seams of Hired 15/07/2024
HEMM Patch-A of
Jogidih Colliery,
Govindpur Area-III."
Transportation of coal
from different sources to M/s
BCCL/CMC/TPTN
20 different destinations KHEMKA 137,57,07,443.88 1826 days
62/Sijua/LOA/2024/177 26/08/2024
including crushing of coal CARRIERS
and allied jobs under Sijua
24Area of BCCL for a period
of 1826 days".
"Hiring of equipment for
removal of OB, extraction
and transportation of coal M/s VMIPL-
BCCL/CMC/89/BOCP-
from IV(T), IV(B), III(T), C5
21 1865,88,34,936.65 II/BASTACOLLA/LOA/2024/2515-36 2190 days
III(B) and II(B), I(Bot) Engineering
15/10/2024
seams of Bastacolla OCP- (JV)
II of Bastacolla Area
BCCL.
Contractual Unloading
(Mechanical cum manual)
of coal from the rake of
BOXN Wagons within
railway free time, loading
of coal (unloaded from M/s
BCCL/CMC/TPTN
22 BOXN wagons) into AGARWAL 9,40,96,840.32 270 days
64/Washery/LOA/2024/216 25/10/2024
tippers and transporting & CO.
the same to Patherdih
NLW Washery Raw Coal
Tube stacker or raw coal
hopper for a period of 270
days".
25"Removal of Hard/ Soft
OB with fire-fighting by
vertical/xcentric or
M/s VMIPL-
equivalent ripper and
C5 BCCL/CMC/91/ChatkariJore/Lodna/LOA
23 transportation of OB 50,83,44,397.43 365 days
Engineering /2024/2818-35 25/11/2024
through Hiring of HEMM
(JV)
for diversion of chatkari
Jore at Lodna Area of
BCCL."
"Hiring of equipment for
removal of OB, extraction
and transportation of coal
from XI/XII, IX/X, VIIIB,
M/s
VIIIA, V/VI/VII seams of
VISHNUSHI BCCL/CMC/88/Patch-
Hired HEMM Patch-C of
24 VA 314,63,58,685.91 C/Govindpur/LOA/2024/2902-2919 2555 days
ABG Colliery, Govindpur
INFRASTRU 03/12/2024
Area BcCL (including
CTURE
partial extraction of OB
and Coal by blast-free
method using Vertical or
equivalent ripper)."
"Hiring of HEMM for
removal of OB and
extraction &
transportation of Coal
from IX/X, VIIIC, VIIIB, M/s SIRI BCCL/CMC/90/Patch
25 VIIIA, V/VI/VII seams of INFRA- 513,78,77,446 M1/Govindpur/LOA/2024/2920-2937 2190 days
Hired HEMM Patch-M1 ARETPL(JV) 03/12/2024
of Maheshpur Colliery,
Govindpur Area, BCCL
(including partial
extraction of OB and Coal
26by blast free method using
vertical or equivalent
ripper)."
"Hiring of HEMM for
removal and
transportation of OB and
M/s SINGH
Extraction and
NATURAL BCCL/CMC/93/NC Patch
Transportation of Coal
26 RESOURCE 91,32,56,824 III/Bastacolla/LOA/2025/18-37 730 days
from IV(T), IV(B), III(T)
PRIVATE 02/01/2025
& III(B) of NC Patch-III
LIMITED
(Left out of NC Patch II)
of ABDKC/ KOCP,
Bastacolla, Area, BCCL.
"Hiring of equipment for
Extraction and
Transportation of
Overburden and Coal with
M/s RA
fire fighting from IX/X, BCCL/CMC/94/Patch
27 Mining Private 141,80,17,468.86 1095 days
VII/VIII and V/VI seams E/Kusunda/LOA/2025/41 12/02/2025
Limited
of proposed patch "E"
under New Godhur
Kusunda Colliery,
Kusunda Area, BCCL."
M/s DEV
"Hiring of HEMM for Re BCCL/CMC/96/KD
MULTICOM
28 handling of Loose OB for 96,70,18,238.14 Barrier/Bastacolla/LOA/2025/718-739 730 days 2025-26
PRIVATE
KD Barrier Patch of 08/04/2025
LIMITED
27Bastacolla Area of
BCCL."
"Transportation of coal
from different sources to M/s Hindustan
different destination Trade
BCCL/CMC/TPTN63/Katras/LOA/2025/
29 including crushing of coal Overseas 185,90,86,204.58 972 days
129 28/05/2025
and allied jobs under Private
Katras Area of BCCL for a Limited
period of 972 days".
Hiring of HEMM for
removal of OB &
extraction &
transportation of coal and
Jhama from XV, XIV,
M/s TBEPL- BCCL/CMC/95/Phase-
30 XIII, XII and XI seams 849,25,20, 187.22 2190 days
NSIPL (JV) IV/PB/LOA/2025/144 12/06/2025
with fire-fighting in
dumped loose OB of Hired
HEMM Patch Phase-IV of
Kendwadih Colliery, PB
Area, BCCL.
Transportation of coal
from different sources to
different destinations with
M/s Pragati
Hiring of Mobile Crushers BCCL/CMC/TPTN
31 Indian Road 96,52,19,173.09 1095 days
at Different Locations 65/Kusunda/LOA/2025/274 26/08/2025
Lines
including allied jobs at
Kusunda Area of BCCL
for a period of 1095 days".
28Hiring of HEMM for
removal of OB and
extraction and
transportation of Coal
from II Seam and III Seam BCCL/CMC/HEMM-98/Patch-E
M/s SATYAM
32 by Hired HEMM along 91,04,86,437.19 EBC/Kusunda/LOA/2025/1689-1710 1095 days
INFRA
with crushing of coal by 07/10/2025
Mechanical Crusher from
proposed Patch-E of East
Bassuria Colliery,
Kusunda Area, BCCL"
Hiring of HEMM for
removal of 08 and
extraction and
transportation of Coal
M/s MNSR- BCCL/CMC/HEMM-97/Patch-
33 from IV(T), IV(B), III(T) , 1754,52,24,462.92 2190 days
GSCO(JV) A/Bastacolla/LOA/2025/388 24/11/2025
Ill(B), II(MB) and I(MB)
seams of Ghanoodih OC
Patch -A, Bastacolla Area,
BCCL.
Contractual Unloading
{Mechanical Gum
mantia[) of coal from the
rake of BOXN wagons
within railway free time,
M/s Agarwal BCCL/CMC/TPTN-
34 loading of coal (unloaded 13,08,21,075.04 365 days
and Company 68/Patherdih/LOA/2025/426 25/12/2025
from BOXN wagons) into
tippers and transporting
the same to Patherdih
NLW Washery Raw Coal
Tube stacker or raw coal
29hopper for a period of 365
days".
"Transportation of coal
from Mudidih Colliery to
New Madhuban Washery
with Hiring of Mobile M/s Rawani BCCL/CMC/TPTN
35 8,23,33,377.42 730 days
Crusher including allied Roadways 69/Sijua/LOA/2025/430 26/12/2025
jobs at Sijua Area of
BCCL for a period of 730
days".
Transportation of
27,74,000 tonne of
Washery products Such as
Washed Coal, Washed
Coal (Power) / Rejects on
daily basis. Washed Coal,
M/s Singh
Washed Coal (Power)
Natural BCCL/CMC/TPTN-
from Tube Stackers (1 &
36 Resource 9,18,86,102.22 67/Patherdih/LOA/2026/06 Date: 365 days
2) respectively from 5.0
Private 10.01.2026 10/01/2026
MTPA Patherdih NLW
Limited
Washery and Rejects from
Reject heap near PNWP
Loading Siding of
Patherdih Washery (lead
distance 0-1 KM) to
loading platform of 5.0
30MTPA Patherdih NLW
Washery along with the
loading of the 27,74,000
Tonne quantity into the
supplied rakes (as per
availability) for a period of
365 days”
Hiring of HEMM for
removal of In-situ OB and
extraction and
transportation of coal from
M/S BLA
VIII, VII, V/VI, IVT, IVB,
INFRASTRU BCCL/CMC/HEMM-102/Patch-
37 III, IIT and IIM seams by 126,83,17,582.17 540 days
CTURE PVT C/SIJUA/LOA/2026/581-614 30/03/2026
opencast method from
LTD
Patch 'C' of amalgamated
Sendra Bansjora Nichitpur
Colliery (ASBNC) of
Sijua Area
31Hiring of HEMM for
removal of OB, Extraction
and Transportation of
Coal from IX/X, VIIIВ,
VIIIA, VIII, VII, V/VI,
IV(T) and IV(B) seams
with fire-fighting of M/s STG BCCL/CMC/HEMM-101/Patch-
38 596,40,90,095.52 1825 days 2026-27
proposed Patch-S along Associates S/Kusunda/LOA/2026/77 04/05/2026
with crushing of Coal by
Mechanical Crusher at
Bassuriya Gondudih Khas
Kusunda Colliery
Kusunda Area" (BGKKC)
of
32Annexure- IV
Mining Service Tenders details for FY 2025-26
Awarded
Period of
Value in
Sl. Subsidiary GeM Bid No. / NIC Contracts
Rs. (Incl. Name of Contractor Type of Contract
No. Name Tender ID in
of GST)
Months
(Cr.)
1 CCL GEM/2025/B/5829853 48 14.18 M/s Fairdeal Projects Private Limited Loading and Transporting
2 CCL GEM/2025/B/5835527 48 10.88 M/s Jai Maa Kali Transport Co. Loading and Transporting
3 CCL GEM/2025/B/5794652 40 44.82 M/s Rajeev Transport Coal Agency Loading and Transporting
4 CCL GEM/2025/B/6016813 24 3.77 M/s KMAG INTERNATIONAL Loading and Transporting
5 CCL GEM/2025/B/6031601 24 36.7 M/s Fairdeal Projects Private Limited Loading and Transporting
6 CCL GEM/2025/B/9093792 64 8.6 VIKHYAT RAJ LOGISTICS(V.R.L) Loading and Transporting
7 CCL GEM/2025/B/6097214 40 23.74 M/s Jai Balajee Transport Company Loading and Transporting
69.34 Removal of OB &
8 CCL GEM/2025/B/6099624 12 M/s BKB Transport Pvt.Ltd.
Extraction of Coal
123.12 M/s BLA INFRASTRUCTURE
9 CCL GEM/2025/B/6209502 6 Extraction of Coal
PRIVATE LIMITED
10 CCL GEM/2025/B/6204983 24 3.98 M/s Jai Mahalaxmi Transport Co. Loading and Transporting
11 CCL GEM/2025/B/6359579 24 6.72 M/s Jai Mahalaxmi Transport Co. Loading and Transporting
379.19 M/s JARPL-AT(Consortium of Jai
Removal of OB &
12 CCL GEM/2025/B/6553471 60 Ambey Roadlines Pvt. Ltd. And Avinash
Extraction of Coal
Transport)
263.97 Removal of OB &
13 CCL GEM/2025/B/6581450 48 M/s BLA Infrastructure Pvt. Ltd.
Extraction of Coal
15.95 Removal of OB &
14 CCL GEM/2025/B/6767486 5 M/s Maa Kamakhya Traders
Extraction of Coal
15 CCL GEM/2025/B/6795497 12 14.81 M/s Shiv Enterprises Removal of OB
3384.86 M/s BKT-PMIW JV(Through the lead
16 CCL GEM/2025/B/6808871 6 Removal of OB
partner Birendra Kumar Tripathi)
86.93 M/s BKT-PMIW JV(Through the lead Removal of OB &
17 CCL GEM/2025/B/6837036 18
partner Birendra Kumar Tripathi) Extraction of Coal
76.46
18 CCL GEM/2025/B/6658121 60 M/s Shai Transporter Loading and Transporting
12.59 M/s CLASSIC SECURESHIELD
19 CCL GEM/2025/B/6795402 24 Loading and Transporting
PRIVATE LIMITED
20 CCL GEM/2025/B/6799953 24 39.18 M/s Rajeev Transport Coal Agency Loading and Transporting
21 CCL GEM/2025/B/6519395 36 496.51 M/s UNITED COAL CARRIERS Loading and Transporting
22 CCL GEM/2025/B/6574796 84 10.43 M/s DSAT JV Loading and Transporting
31.23 Removal of OB &
23 CCL GEM/2025/B/6399631 36 M/s RA Petrochemicals Private Limited
Extraction of Coal
80.58 Removal of OB &
24 CCL GEM/2025/B/6613905 96 M/s NCC Limited
Extraction of Coal
25 CCL GEM/2025/B/6459196 24 6.73 M/s DSAT JV Loading and Transporting
26 CCL GEM/2025/B/6442759 12 6.49 M/s RA Petrochemicals Private Limited Loading and Transporting
127.42 M/s JARPL-AT(Consortium of Jai
Removal of OB &
27 CCL GEM/2025/B/6515660 54 Ambey Roadlines Pvt. Ltd. And Avinash
Extraction of Coal
Transport)
28 CCL GEM/2025/B/6959729 28 15.92 M/s Jai Ma Tara Projects Loading and Transporting
29 CCL GEM/2025/B/6973833 40 19.85 M/s Shai Transporter Loading and Transporting
83.31 M/s Pandaveswar Mining & Industrial
30 CCL GEM/2025/B/6995758 40 Loading and Transporting
Works
31 CCL GEM/2025/B/6996994 36 250.09 M/s JTPL SIPL JV Loading and Transporting
81.57 Removal of OB &
32 CCL GEM/2025/B/7009749 48 M/s Krishna Infrastructure
Extraction of Coal
299.99 M/s PNM and
KNS(Consortium)(Through the Lead Removal of OB &
33 CCL GEM/2025/B/7014329 120
partner PRANABNAMAN MINERALS Extraction of Coal
PRIVATE LIMITED)
3431.41 Removal of OB &
34 CCL GEM/2025/B/7016521 12 M/s SHIV ENTERPRISES
Extraction of Coal
35 CCL GEM/2026/B/7079681 36 19.4 M/s Deo Trading Company Loading and Transporting
11.83
36 CCL GEM/2026/B/7187674 24 M/s Jai Balajee Transport Company Loading and Transporting
6.14
37 CCL GEM/2026/B/7187172 6 M/s Variant Commercial Private Limited Loading and Transporting
16.21
38 CCL GEM/2026/B/7231047 36 M/s DDG Associates Loading and Transporting
101.06
39 CCL GEM/2026/B/7256215 12 M/s Variant Commercial private Limited Loading and Transporting
35Annexure- V
List of black listing outsourcing Company by CMC Department during last 5 years:
Sl. Name & Address of the company Period of Order No.
No. blacklisting
1 Libra Business Private Limited 06.10.2025 to BCCL/CMC/H-
1st FLOOR, UPPER RAJBARI ROAD, 05.10.2026 HEMM/DEBAR/LI
NEAR NILKANTH WASNI MANDIR, BRA/2025/316
JHARIA, DHANBAD, Jharkhand-828111 Date 06.10.2025
e-mail: info.lbpl89@gmail.com
Phone No.- 9204651700
2 BMPL- GKR (JV) 06.10.2025 to BCCL/CMC/H
Hirak Road, Tapoban Colony, 05.10.2026 HEMM/DEBAR
Saraidhella, Dhanbad, Jharkhand-828109 /BMPL-
e-mail: GKR(JV)/2025/315
bhagwatiminingpvtltd@gmail.com, gkrinfrac Date: 06.10.2025
on@gmail.com
Phone No.- 9931454071
3 GKR INFRACON (INDIA) PRIVATE 06.10.2025 to BCCL/CMC/H-
LIMITED 05.10.2026 HEMM/DEBAR/G
8-2-293/82/J 111/43/N, KR
OPP. JUBILEE HILLS PUBLIC SCHOOL, INFRACON/2025/
ROAD NO 71, JUBILEE HILLS, 314 Date
Hyderabad, Telangana, 500033 06.10.2025
e-mail: gkrinfracon@gmail.com
4 Bhagwati Mining Private Limited 06.10.2025 to BCCL/CMC/H-
Hirak Road, Tapoban Colony. 05.10.2026 HEMM/DEBAR/B
Saraidhella, Dhanbad, Jharkhand-828109 MPL/2025/313
e-mail: Date 06.10.2025
bhagwatiminingpvtltd@gmail.com
Phone No.-9931454071
5 LIBRA-GKR (JV) 06.10.2025 to BCCL/CMC/H-
UPPER RAJBARI ROAD, 05.10.2026 HEMM/Debar/LIB
NEAR NILKANTH WASNI MANDIR, RA-
JHARIA, DHANBAD, Jharkhand-828111 GKR(JV)/2025/312
e-mail: Date 06.10.2025
info.lbpl89@gmail.com
Phone No.- 9431120282, 9263186505
6 M/s NNT DEVELOPERS PRIVATE BCCL/CMC/TPT
LIMITED, N 46/Debar/NNT
(Shri Suyash Kumar, Director) Developers Pvt.
104 SRIRAM TOWER, Ltd./2022/406
KANKARBAGH MAIN ROAD PATNA dated 05.09.2022
NEAR JALAN SHOP
Patna, Bihar, PIN-800020
However, balance
period of Banning
was removed vide
36letter ref. No.
BCCL/CMC/TPT
N 46/Debar/NNT
Developers Pvt
Ltd/2024/137
Date: 14.06.2024
7 S.G.Projects Ltd 03.02.2021 to BCCL/CMC/F-
613, Jasmine tower,31 02.02.2026 HEMM-
Shakeshpearesarani OS/Sh.Ca/SGPL/20
Kolkata-17, 21/58 dated
West Bengal 02.02.2021
8 Balaji project's 03.02.2021 to BCCL/CMC/F-
3A.3rd floor,75 C 02.02.2026 HEMM-
Park Street, OS/Sh.Ca/BP/2021/
Kolkatta-700016 59 dated
West Bengal 02.02.2021
List of terminated Contract during last 5 years:
Sl. Name of NIT No. LOA No. Name of Contractor Period Award Value
N Patch with address of (INR)
o. Contr
act
1. Basantim BCCL/CM BCCL/CM M/s Hanumant 2190 530,14,34,84
ata C/H- C/H- Construction Private Days 7.65
Dahibari HEMM/e- HEMM- Limited, At: Ground
Patch-B, Tender/202 53/Patch-B- Floor, Parwani
CV Area 1/01 BMDBC- Complex,
Date: CV/2021/1 Opp. Dist Judges
01.01.2021 52 Date: Bungalow, Civil
17.04.2021 Lines, Raipur,
Chhattisgarh, PIN-
492001 Phone No.:
0771-4041893
Mobile No.:
08349593731 Email
ID:
hanumant009@yaho
o.co.in
37Annexure- VI
Sl No. Bidder/Contractor Place at CCL Date of Banning Period Reason
Not Commenced the work after submission
1 RAMLAL AGARWALLA RAJHARA 11.09.2020 3 years of performance security.
2 DHORI 21.09.2022 3 years Not Commenced the work after submission
BGR LOGISTICS JV of performance security.
M/s Bhart kumar thaker,
M/s Galaxeos infra tech
M/s.R.N.Singh
M/s Paradise transporters private
3 limited KATHARA 01.04.2023 1 Year Due to modification and withdralwal of bid.
M/s Paradise transporters private Due to furnishing of wrong information in the
4 limited ARGADA 18.09.2024 2 Years Bid.
5 M/s Jai Maa Tara Projects Kuju 28.11.2024 1 Year Due to modification and withdralwal of bid.
Not Commenced the work after submission
6 M/s KS Mahadeo Constech pvt. Ltd Rajrappa 16.02.2025 1 Year of performance security.
7 M/s Sheela Enterprises B&K 08.08.2025 1 Year Due to poor performance .
8 M/s Babulal Gupta Argada 10.09.2025 1 Year Due to poor performance.
9 M/s Modi Transport company Kathara 01.12.2025 1 Year Due to poor performance .
38M/s Hanumant Construction Private Due to non submission of Performance
10 Limited Hazaribagh 27.12.2025 1 Year Security.
M/s Shashi Structurtal Engineers
11 Privert Limited Kuju 13.01.2026 1 Year Due to poor performance .
M/s S Group Construction & Power Due to submission of false / incorrect
12 Transmission Kuju 22.01.2026 2 Years document of work experience
M/s TCIL-AT (JV) Due to participation of M/s Avinash Transport
M/s Tejas Cargo India Limited Magadh- twice with other two bidders as a JV in same
13 M/s Avinash Transport Sanghamitra 05.05.2026 1 Year tender.
Due to furnishing of wrong information in the
14 M/s Menakshi Con. Hazaribagh 29.05.2026 2 Years Bid
39Annexure-VII
Grade wise coal produced by BCCL during the last five years is as below:
BCCL GRADEWISE COAL PRODUCTION [fig in '000 Tonnes]
GRADE 2025-26 2024-25 2023-24 2022-23 2021-22
ST-II 0.00 0.00 63.34 0.00 0.00
W-I 65.10 399.60 706.57 171.54 234.24
W-II 4,056.62 3,436.06 2,205.25 2,255.98 1,377.08
W-III 1,109.16 1,282.55 1,869.66 1,618.63 967.15
W-IV 17,727.31 18,232.52 18,115.10 11,231.40 14,150.64
W-V 10,324.21 15,537.43 15,954.10 18,273.50 11,019.92
W-VI 419.50 0.00 195.01 164.79 1,292.20
TOTAL
COKING 33,701.90 38,888.16 39,109.03 33,715.83 29,041.23
COAL
G-5 0.00 0.20 15.00 491.31 8.62
G-6 232.30 9.90 89.42 0.00 61.19
G-7 971.21 686.16 444.34 936.09 615.40
G-8 0.00 499.24 638.03 1,000.98 692.64
G-9 615.68 418.51 700.20 0.00 0.00
G-10 0.00 0.00 100.40 34.70 92.20
TOTAL NON-
COKING 1,819.18 1,614.01 1,987.40 2,463.08 1,470.04
COAL
G/TOTAL 35,521.08 40,502.16 41,096.43 36,178.91 30,511.27
Coal produced by BCCL through outsourced operations vis-à-vis departmental
production during the last five years is as below:
BCCL COAL PRODUCTION [fig in Mill. Tonnes]
Departmental Coal Hired Coal
Year Total Coal Production
Production Production
2025-26 6.38 29.14 35.52
2024-25 8.72 31.78 40.50
2023-24 10.46 30.64 41.10
2022-23 10.11 26.07 36.18
2021-22 9.18 21.33 30.51
40Grade wise coal produced by CCL during the last five years is as below:
CCL GRADEWISE COAL PRODUCTION [fig in '000 Tonnes]
GRADE 2025-26 2024-25 2023-24 2022-23 2021-22
ST-II 0.00 150.00 40.00 60.00 0.00
W-I 1410.00 1290.00 530.00 0.00 0.00
W-II 300.00 810.00 740.00 1150.00 530.00
W-III 2850.00 3550.00 2480.00 590.00 630.00
W-IV 13710.00 10910.00 12070.00 14850.00 7120.00
W-V 3680.00 3720.00 4920.00 3910.00 8880.00
W-VI 0.00 110.00 280.00 0.00 0.00
TOTAL COKING COAL 21950.00 20540.00 21060.00 20560.00 17160.00
G-5 810.00 450.00 790.00 220.00 0.00
G-6 2450.00 2820.00 880.00 110.00 830.00
G-7 8340.00 810.00 1660.00 2560.00 1680.00
G-8 9580.00 6520.00 5130.00 5250.00 4380.00
G-9 1190.00 5050.00 6320.00 3340.00 5740.00
G-10 25580.00 2170.00 5330.00 3270.00 4050.00
G-11 12030.00 33410.00 28380.00 27660.00 20020.00
G-12 170.00 14700.00 15190.00 7930.00 6680.00
G-13 150.00 1050.00 1310.00 5190.00 8290.00
TOTAL NON-COKING COAL 60300.00 66980.00 64990.00 55530.00 51670.00
G/TOTAL 82250.00 87520.00 86050.00 76090.00 68830.00
41Coal produced by CCL through outsourced operations vis-à-vis departmental production
during the last five years is as below:
CCL COAL PRODUCTION [fig in Mill. Tonnes]
Year Departmental Hired Coal Total Coal
Coal Production Production
Production
2025-26 15.36 66.89 82.25
2024-25 16.99 70.53 87.52
2023-24 15.68 70.37 86.05
2022-23 15.46 60.63 76.09
2021-22 13.78 55.05 68.83
****
42