See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5421
TO BE ANSWERED ON 25.03.2026
PENDING RAILWAY PROJECTS AND COST ESCALATION
5421. SHRI PUSHPENDRA SAROJ:
ADV PRIYA SAROJ:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the railway infrastructure projects sanctioned during the
last ten years that are yet to be completed in Northern Railway (NR),
North Central Railway (NCR) and North Eastern Railway (NER) along
with their original approved cost, revised cost and present physical and
financial progress, project-wise;
(b) the details of the number of such projects in NR, NCR and NER that
have experienced cost escalation or timeline overruns, the reasons
identified in Ministry reviews for such delays and the additional
financial burden arising therefrom;
(c) the details of the key findings of inspections, performance audits or
internal monitoring reports regarding land acquisition, statutory
clearances, contractor performance and fund availability affecting
project execution in these zones; and
(d) the details of the monitoring and accountability measures introduced to
ensure time-bound completion of railway infrastructure projects in NR,
NCR and NER?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d) : Capacity enhancement of railway network has been taken up by
Indian Railways in a big way during last 11 years. The details of
commissioning/laying of new track across Indian Railways is given below:-
§ Page 1 of 22New track
Period Average commissioning of new tracks
Commissioned
2009-14 7,599 Km 4.2 Km/day
2014-25 34,428 Km 8.6 Km/day (more than 2 times)
As on 01.04.2025, across Indian Railways, 431 Railway infrastructure
projects including port-connectivity (154 New Line, 33 Gauge Conversion
and 244 Doubling) of total length 35,966 Km, costing approx. Rs. 6.75 lakh
crore are sanctioned. The summary is as under:-
Total Length
Total Exp upto
No of Length Commissioned
Category Mar'25
Projects NL/GC/DL till Mar'25
(Rs. in Cr)
(km) (Km)
New Lines 154 16,142 3,036 1,45,318
Gauge
33 4,180 2,997 22,753
Conversion
Doubling /
244 15,644 6,736 1,22,858
Multitracking
Total 431 35,966 12,769 2,90,929
Zonal Railway-wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Projects Sanctioned in Northern Railway:
As on 01.04.2025, 29 projects (08 New Line and 21 Doubling) of 1,169 Km
length, costing ₹69,731 crore falling in Northern Railway (NR) are
sanctioned. The summary is as under:-
Page 2 of 22Category No of Total Length Exp
Projects Length Commissioned upto
(km) (km) Mar'25
(Rs. in Cr.)
New Line 08 499 80 28288
Doubling/Multitracking 21 670 264 3337
Total 29 1169 344 31625
Completed projects:
Details of some of the recently completed projects falling in Northern
Railway (NR) are as under:
SN. Project Cost
(Rs. in Cr.)
1 Udhampur-Srinagar-Baramula Rail Link (272 km) 42,278
2 Rajpura-Bhatinda Doubling (173 km) 2459
3 Barabanki-Akbarpur Doubling (161 km) 1700
4 Deoband (Muzzafar Nagar)-Roorkee New Line (27 1289
km )
5 Rewari-Rohtak New Line (85 km) 1001
6 Utretia-Zafrabad Doubling (148 km) 890
7 Rohtak-Mehem-Hansi New Line (64 km) 889
8 Jallandhar-Pathankot-Jammu Tawi Doubling (209 850
km)
9 Jind-Sonepat New Line (89 km) 800
10 Jaunpur- Akbarpur (Tanda) Doubling (77 km) 676
11 Raibareilly-Amethi Doubling (60 km) 668
12 Utretia-Raibareilly Doubling (66 km) 662
13 Muzaffarnagar – Tapri Doubling (52 km) 525
14 Meerut-Muzaffarnagar Doubling (55 km) 430
15 Janghai- Phaphamau Doubling (47 km) 414
16 Tughlakhabad-Palwal 4th line (34 km) 366
17 Alamnagar-Utretia Doubling (20 km) 358
Page 3 of 2218 Haridwar – Laksar Doubling (27 km) 347
19 Ambala-Dhapper-Chandigarh Doubling (45 km) 339
20 Kathua-Madhopur Punjab Doubling (3 km) 257
21 Mansa – Bhatinda Doubling (49 km) 216
22 Phaphamau-Prayagraj Doubling (14 km ) 212
23 Lahota-Bhadoi Doubling (39 km) 184
24 Bhadoi-Janghai Doubling (31 km) 168
25 Jakhal- Mansa Doubling (45 km) 163
26 New Delhi -Tilak Bridge Doubling (7 km) 137
27 Mirthal-Bhangala Doubling (3 km) 74
28 Jaunpur Jn. - Jaunpur city -Chord line (2 km) 72
29 Palwal -New Prithala Doubling (10 km) 66
30 Khukhrana- Panipat Doubling (8 km) 58
31 Amritsar - Chheharta Doubling (7 km) 31
32 Jalandhar City-Suchi Pind Doubling (4 km) 24
33 Chakki Bank-Bharoli Doubling (3 km) 15
Ongoing projects:
Some of the projects falling in Northern Railway (NR) which have been
taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Rishikesh-Karanprayag New Line (125 km) 38953
2 Bhanupalli-Bilaspur-Beri New Line (63 km) 13770
Varanasi-Pt. Deen Dayal Upadhyaya multritracking 2464
3 including Rail cum Road Bridge across Ganga (15
Km)
4 Nangal Dam-Talwara – Mukerian New Line (123 km)
2311
5 Chandigarh-Baddi New Line (28 km) 1540
Page 4 of 226 Janghai-Pratapgarh- Amethi Doubling (87 km) 1197
8 Phaphamau-Unchahar Doubling (72 km) 971
9 Mansa-Bhatinda Doubling (80 Km) 449
10 Anand Vihar-Tilak Bridge 3rd & 4th line (20 km) 419
11 Barabanki-Malhaur 3rd & 4th Line (33 km) 407
12 Ferozpur-Patti New Line (26 km) 300
13 Ludhiana-Mullanpur Doubling (21 km) 288
14 Ludhiana-Kila Raipur Doubling (19 Kms) 238
15 Jaunpur Jn.-Zafarabad Doubling (6 km) 177
16 Alal-Himmatana Chord line (13 km) 174
17 Dilkusha-Malhaur 3rd Line (8 km) 164
18 Didarganj - Shahganj - Bilwai Chord line (6 km) 137
19 Bypass line at Ayodhya Cantt. (6 km) 97
20 Bishanpura - Jind City Chord line (5 km) 77
21 Varanasi Shivpur 3rd line (6 km) 76
22 Byepass line at Ayodhya (1.5 km) 56
Projects Sanctioned in North Central Railway:
As on 01.04.2025, 18 projects (03 Gauge Conversion and 15 Doubling) of
1,874 Km length, costing ₹25,829 crore falling in North Central Railway
(NCR) are sanctioned. The summary is as under:-
Category No of Total Length Exp
Projects Length Commissioned upto
(km) (km) Mar'25
(Rs. in Cr.)
Gauge Conversion 03 440 97 2902
Doubling/Multitracking 15 1434 468 11155
Total 18 1874 565 14057
Page 5 of 22Completed projects:
Details of some of the recently completed projects falling in North Central
Railway (NCR) are as under:
SN. Project Cost
(Rs. in Cr.)
1 Bhimsen-Jhansi Doubling (206 km) 2620
2 Guna- Etawah New Line (348 Km) 683
3 Mathura – Palwal 4th Line (80 km) 669
4 Agra-Etawah New Line (110 km) 427
5 Etawah-Mainpuri New Line (58 km) 313
6 Ruma Chakeri- Chandari - 3rd line (13 km) 177
7 Yamuna Bridge-Agra Fort Doubling (3 km) 138
8 Chipiyana Buzurg - Dadri 4th line (12 km) 129
9 Mathura Yard Remodelling (4 km) 113
10 Bhaupur-Panki 4th line (11 km) 97
11 Dailwara-Birai chord line (8 km) 77
12 Baupur-Panki Doubling (11 km) 55
13 Kanpur-New Coaching Complex – Kanpur 35
Doubling (3 km)
14 Naini - Chheoki- 3rd Line (2 km ) 30
Ongoing projects:
Some of the projects falling in North Central Railway (NCR) which have
been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Mathura-Jhansi 3rd line (274 km) 5924
2 Jhansi-Khairar-Manikpur & Khairar-Bhimsen 4330
Page 6 of 22Doubling (431 km)
3 Gwalior-Sheopurkalan Gauge Conversion (284 km)
2913
4 Pt. Deen Dayal Upadhyaya -Prayagraj 3rd line (150 2649
km)
5 Jhansi-Bina 3rd line (153 km) 2002
6 Prayagraj (Iradatganj)-Manikpur 3rd Line (84 km) 1508
7 Doubling of Billi- Chunar (102 km) 1424
8 Agra Fort - Bandikui Doubling (150 km) 988
9 Dholpur-Sirmuttra Gauge Conversion (145 km) 747
10 Prayagraj - Bamrauli 4th line (10 Km) 494
11 Aligarh - Daud Khan 3rd line (18 km) 452
12 Lalitpur-Birari Doubling (16 km) 304
13 Kuberpur-Yamuna Bridge 3rd line(10 Km) 170
Projects Sanctioned in North Eastern Railway:
As on 01.04.2025, 17 projects (08 New Line, 01 Gauge Conversion and 08
Doubling) of 1,253 Km length, costing ₹20,466 crore falling in North
Eastern Railway (NER) are sanctioned. The summary is as under:-
Category No of Total Length Exp
Projects Length Commissioned upto
(km) (km) Mar'25
(Rs. in Cr.)
New Line 08 656 48 4042
Gauge Conversion 01 56 - 260
Doubling/Multitracking 08 541 306 6184
Total 17 1253 354 10486
Completed Projects:
Details of some of the recently completed projects falling in North Eastern
Railway (NER) are as under:
Page 7 of 22SN. Project Cost
(Rs. in Cr.)
1 Rosa-Sitapur Cantt - Burhwal Doubling (181 km) 2094
2 Varanasi-Madhosingh-Prayagraj Doubling (120 2018
km)
3 Kanpur-Kasganj-Mathura & Kasganj-Bareilly 1790
Gauge Conversion (545 km)
4 Phephna-Indara, Mau-Shahganj doubling (150 km) 1778
5 Ghazipur city-Tarighat New Line (17 km) 1766
6 Gonda-Gorakhpur Loop Gauge Conversion (260 863
km)
7 Kaptanganj-Thawe-Chhapra Gauge Conversion 819
(234 km)
8 Ballia-Gazipur city Doubling (65 km) 650
9 Pilibhit-Shahjahanpur Gauge Conversion (83 km) 589
10 Domingarh-Gorakhpur-Kusumhi - 3rd line and 508
Gorakhpur-Nakaha Jungle Doubling (21 km)
11 Maharajganj-Masrakh New Line (35 km) 412
12 Aunrihar-Jaunpur Doubling (60 km) 405
13 Ghazipur-Aunrihar Doubling (40 km) 371
14 Bahraich-Nanpara-Nepal Ganj Gauge Conversion 342
(56 km)
15 Gonda-Bahraich Gauge Conversion (60 km) 318
16 Bareilly-Pilibhit-Tanakpur Gauge Conversion (101 313
km)
17 Chhapra Gramin to Khairali New Line (11 km) 215
18 Indara-Dohrighat Gauge Conversion (34 km) 213
19 Aurnihar-Manduadih Doubling (39 km) 200
20 Malhaur-Daliganj Doubling (13 km) 183
21 Aishbagh-Manaknagar Doubling (4 km) 82
22 Chhapra Jn. - Chhapra kacheri 3rd Line (3 km) 33
Page 8 of 22Ongoing projects:
Some of the projects falling in North Eastern Railway (NER) which have
been taken up are as under:
SN. Project Cost
(Rs. in Cr.)
1 Bahraich - Khalilabad New Line (240 km) 4940
2 Bhatni-Aurnihar Doubling (117 km) 2529
3 Sahjanwa-Dohrighat New Line (81 km) 1320
4 Gorakhpur- Valmikinagar Doubling (96 km) 1121
5 Burhwal-Gonda 3rd line (62 km) 1118
6 Chhapra-Ballia Patch Doubling (65 km) 1046
7 Anandnagar-Ghugli New Line (53 km) 958
8 Barabanki-Burhwal 3rd line (27 km) 426
9 Etah-Kasganj New Line (29 km) 389
Indian Railways has established procedures of inspection as stipulated in
various Codes, Manuals etc. Inspections are carried out by various officials
regularly as per schedule. These projects are monitored at various levels
such as Division, Zone and Railway Board etc. Further, for effective
monitoring of projects, Indian Railways has also developed a dedicated
portal- Indian Railways Projects Sanctions & Management (IRPSM). Various
critical aspects of projects such as land acquisition, statutory clearances
and fund availability are monitored through IRPSM.
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Page 9 of 22 Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s
Railway Electrification :
Electrification of railway network on Indian Railways has been taken up in
mission mode. So far, about 99.4% of Broad Gauge (BG) network has been
electrified. The electrification in remaining network has been taken up.
Electrification carried out during 2014-25 and before 2014 is as under:
Period Route
Kilometer
Before 2014 (about 60 years) 21,801
2014-25 46,900
In, Northern Railway (7590 RKM), North Central Railway (4369 RKM) and
North Eastern Railway (32 RKM); 100% of BG network has been electrified.
Further, all new line / multitracking projects are being sanctioned and
constructed with electrification.
ROB/RUBs
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
Railway. Such works are prioritised and taken up on the basis of its impact
on safety in train operations, mobility of trains & impact for road users and
feasibility etc.
Page 10 of 22No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto Jan’26) 14,024 Nos.
As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at cost of ₹
1,14,196 Cr on Indian Railways which are at various stages of planning and
execution.
Details of ROBs/RUBs works sanctioned during last 10 years including
current financial year i.e. 2015-26 (Upto Jan’26) in Northern Railway, North
Central Railway and North Eastern Railway are as under:
RLY ROBs (in Nos.) RUBs (in Nos.)
NR 202 551
NCR 154 308
NER 91 508
Details of ROBs/RUBs works completed during last 10 years including
current financial year i.e. 2015-26 (Upto Jan’26) in Northern Railway, North
Central Railway and North Eastern Railway are as under:
RLY ROBs (in Nos.) RUBs (in Nos.)
NR 297 1125
NCR 139 684
NER 60 503
Page 11 of 22Details of Expenditure (upto Jan’26) Under PH-30 for ROBs/RUBs works
during last 10 years including current financial year i.e. 2015-26 (Upto
Jan’26) in Northern Railway, North Central Railway and North Eastern
Railway are as under:
(Rs. in Cr.)
RLY Expenditure (upto Jan’26)
NR 5607
NCR 4294
NER 2486
Completion of any ROB/RUB work depends on various factors like, fixing of
approach alignment, approval of General Arrangement Drawing (GAD), land
acquisition, removal of encroachment, shifting of infringing utilities,
statutory clearances from various authorities, law and order situation in
the area of project / work sites, number of working months in a year for
particular project / work sites due to climatic conditions etc. All these
factors affect the completion time of the projects / works.
Further, Railways have taken following measures to expedite the progress
of work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure drawings for various combinations
of span, skewness and width of road on Railway portion has been
done to avoid delays during the design approval. This has been issued
in the form of compendium, which can be directly adopted for Road
Over Bridge across Railway lines for expeditious planning.
Page 12 of 22Amrit Bharat Stations:
Development / redevelopment / upgradation / modernisation of stations
on Indian Railways is a continuous and ongoing process and works in
this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. Development / redevelopment /
upgradation / modernisation of a station is carried out based on
category of station/condition/traffic handled etc.
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planning
includes:
• Improvement of access to station and circulating areas
• Integration of station with both sides of city
• Improvement of station building
• Improvement of waiting halls, toilets, sitting arrangement, water
booths
• Provision of wider foot over bridge/air concourse commensurate
with passenger traffic
• Provision of lift/escalators/ramp
• Improvement /Provision of platform surface and cover over
platforms
• Provision of kiosks for local products through schemes like ‘One
Station One Product’
• Parking areas, Multimodal integration
• Amenities for Divyangjans
• Better passenger information systems
Page 13 of 22• Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station.
The scheme also envisages sustainable and environment friendly
solutions, provision of ballastless tracks etc. as per necessity, phasing
and feasibility and creation of city centre at the station in the long
term.
Completed stations:
So far, 1,338 stations have been identified for development under the
Amrit Bharat Station Scheme. Northern Railway, North Central Railway
and North Eastern Railway serve the following states and name of
Amrit Bhartar Stations in these states are as under:-
No. of
State Names of Stations
Stations
Bihar 98 Anugraha Narayan Road, Ara, Arariya Court,
Bakhtiyarpur, Banka, Banmankhi, Bapudham
Motihari, Barahiya, Barauni, Barh, Barsoi Jn,
Begusarai, Bettiah, Bhabua Road, Bhagalpur,
Bhagwanpur, Bihar Sharif, Bihiya, Bikramganj,
Buxar, Chakia, Chausa, Chhapra, Dalsingh Sarai,
Darbhanga, Dauram Madhepura, Dehri On Sone,
Dholi, Dighwara, Dumraon, Durgauti, Ekma,
Fatuha, Gaya, Ghorasahan, Guraru, Hajipur Jn,
Jamalpur Jn, Jamui, Janakpur Road, Jaynagar,
Jehanabad, Jhanjharpur, Kahalgaon, Karhagola
Road, Katihar Jn, Khagaria Jn, Kishanganj, Kudra,
Labha, Laheria Sarai, Lakhminia, Luckeesarai Jn,
Page 14 of 22Madhubani, Maheshkhunt, Mairwa, Mansi Jn,
Masrakh, Mokama, Motipur, Munger (Monghyr),
Muzaffarpur Jn, Nabinagar Road, Narkatiaganj Jn,
Naugachia, Nawadah, Paharpur, Patliputra, Patna
Jn, Piro, Pirpainti, Rafiganj, Raghunathpur.,
Rajendra Nagar Terminal (Patna), Rajgir, Ram
Dayalu Nagar, Raxaul, Sabaur, Sagauli, Saharsa,
Sahibpur Kamal, Sakri, Salauna, Salmari,
Samastipur, Sasaram, Shahpur Patoree,
Shivanarayanpur, Simri Bakhtiyarpur, Simultala,
Sitamarhi, Siwan, Sonpur Jn., Sultanganj, Supaul,
Taregna, Thakurganj, Thawe
Delhi 13 Adarshnagar Delhi, Anand Vihar, Bijwasan, Delhi,
Delhi Cantt., Delhi Safdarjung, Delhi Sarai Rohilla,
Delhi Shahadra, Hazrat Nizamuddin, Narela, New
Delhi, Sabzi Mandi, Tilak Bridge
Haryana 34 Ambala Cantt., Ambala City, Bahadurgarh,
Ballabhgarh, Bhattu, Bhiwani Jn, Charkhi Dadri,
Faridabad, Faridabad New Town, Gohana,
Gurugram, Hansi, Hisar, Hodal, Jind Jn,
Kalanwali, Kalka, Karnal, Kosli, Kurukshetra Jn,
Loharu, Mahendragarh, Mandi Adampur, Mandi
Dabwali, Narnaul, Narwana Jn, Palwal, Panipat
Jn, Pataudi Road, Rewari, Rohtak, Sirsa, Sonipat,
Yamunanagar Jagadhari
Himachal 4 Amb Andaura, Baijnath Paprola, Palampur
Pradesh Himachal, Shimla
Madhya 80 Akodia, Amla, Anuppur, Ashoknagar, Balaghat,
Pradesh Banapura, Bargawan, Beohari, Berchha, Betul,
Bhind, Bhopal, Bijuri, Bina, Biyavra Rajgarh,
Page 15 of 22Chhindwara, Dabra, Damoh, Datia, Dewas,
Gadarwara, Ganjbasoda, Ghoradongri, Guna,
Gwalior, Harda, Harpalpur, Indore Jn, Itarsi Jn,
Jabalpur, Junnor Deo, Kareli, Katni Jn, Katni
Murwara, Katni South, Khachrod, Khajuraho Jn,
Khandwa, Khirkiya, Laxmi Bai Nagar, Maihar,
Maksi Jn, Mandla Fort, Mandsor, MCS Chhatarpur,
Meghnagar, Morena, Multai, Nagda Jn, Nainpur
Jn, Narmadapuram (Hoshangabad), Narsinghpur,
Nepanagar, Nimuch, Orchha, Pandhurna,
Pipariya, Ratlam, Rewa, Ruthiyai, Sanchi, Sant
Hirdaram Nagar, Satna, Saugor, Sehore, Seoni,
Shahdol, Shajapur, Shamgarh, Sheopur Kalan,
Shivpuri, Shridham, Shujalpur, Sihora Road,
Singrauli, Tikamgarh, Ujjain, Umaria, Vidisha,
Vikramgarh Alot
Punjab 30 Abohar, Amritsar, Anandpur Sahib, Beas,
Bhatinda Jn, Dhandari Kalan, Dhuri, Fazilka,
Firozpur Cantt, Gurdaspur, Hoshiarpur, Jalandhar
Cantt. Jn, Jalandhar City Jn, Kapurthala, Kot
Kapura Jn, Ludhiana Jn, Malerkotla, Mansa,
Moga, Muktsar, Nangal Dam, Pathankot Cantt.,
Pathankot City, Patiala, Phagwara Jn, Phillaur Jn,
Rup Nagar, Sahibzada Ajit Singh Nagar Mohali,
Sangrur, Sirhind
Rajasthan 85 Abu Road, Ajmer, Alwar, Anupgarh, Asalpur
Jobner, Balotra, Bandikui, Baran, Barmer,
Bayana, Beawar, Bharatpur, Bhawani Mandi,
Bhilwara, Bijainagar, Bikaner, Bundi, Chanderiya,
Chhabra Gugor, Chittorgarh Jn., Churu, Dakaniya
Page 16 of 22Talav, Dausa, Deeg, Degana, Deshnoke, Dholpur,
Didwana, Dungarpur, Falna, Fatehnagar, Fatehpur
Shekhawati, Gandhinagar Jaipur, Gangapur City,
Gogameri, Gotan, Govind Garh, Hanumangarh,
Hindaun City, Jaipur Jn, Jaisalmer, Jalor, Jawai
Bandh, Jhalawar City, Jhunjhunu, Jodhpur,
Kapasan, Khairthal, Kherli, Kota Jn, Lalgarh Jn,
Mandal Garh, Mandawar Mahwa Road, Marwar
Bhinmal, Marwar Jn, Mavli Jn, Merta Road Jn,
Nagaur, Naraina, Nim ka Thana, Nokha, Pali
Marwar, Phalodi Jn, Phulera Jn, Pindwara, Rai
singh nagar, Rajgarh, Ramdevra, Ramganj Mandi
Jn, Ranapratapnagar, Rani, Ratangarh Jn, Ren,
Ringas, Sadulpur, Sanganer, Sawai Madhopur,
Shri Mahaveerji, Sikar, Sojat Road, Somesar, Sri
ganganagar, Sujangarh, Suratgarh, Udaipur City
UT of 1 Chandigarh
Chandigarh
UT of 4 Budgam, Jammu Tawi, Martyr Captain Tushar
Jammu Mahajan, Shri Mata Vaishno Devi Katra
&Kashmir
Uttar 157 Achnera, Agra Cantt., Agra Fort, Aishbagh Jn,
Pradesh Akbarpur Jn, Aligarh, Amethi, Amroha, Anand
Nagar Jn., Aonla, Ayodhya Dham Junction,
Azamgarh, Babatpur, Bachhrawan, Badaun,
Badshahnagar, Badshahpur, Baheri, Bahraich,
Balamau Jn., Ballia, Balrampur, Banaras, Banda,
Barabanki Jn, Bareilly, Bareilly City, Barhni,
Basti, Belthara Road, Bhadohi, Bharatkund,
Page 17 of 22Bhatni, Bhuteshwar, Bijnor, Bulandsahar,
Chandauli Majhwar, Chandausi, Chilbila,
Chitrakutdhamkarwi, Chopan, Chunar Jn.,
Daliganj, Darshannagar, Deoria Sadar, Dhampur,
Dildarnagar, Etawah Jn., Farrukhabad,
Fatehabad, Fatehpur, Fatehpur Sikri, Firozabad,
Gajraula, Garhmuktesar, Gauriganj, Ghatampur,
Ghaziabad, Ghazipur City, Gola Gokarnath,
Gomtinagar, Gonda, Gorakhpur, Govardhan,
Govindpuri, Gursahaiganj, Haidergarh, Hapur,
Hardoi, Hathras City, Idgah Agra Jn, Izzatnagar,
Janghai Jn, Jaunpur City, Jaunpur Jn, Kannauj,
Kanpur Anwarganj, Kanpur Bridge Left Bank,
Kanpur Central, Kaptanganj Jn, Kasganj Jn,
Kashi, Khalilabad, Khorason road, Khurja Jn.,
Kosi Kalan, Kunda Harnamganj, Lakhimpur,
Lalganj, Lalitpur Jn, Lambhua, Lohta, Lucknow
(Charbagh) NR, Lucknow city, Lucknow Jn. (NER),
Maa Belha Devi Pratapgarh Junction, Maghar,
Maharaja Bijli Pasi, Mahoba Jn, Mailani Jn,
Mainpuri Jn, Malhaur, Manak Nagar, Manikpur Jn,
Mariahu, Mathura Jn, Mau Jn, Meerut City Jn,
Mirzapur, Modinagar, Mohanlalganj, Moradabad
Jn, Muzaffarnagar, Nagina, Najibabad Jn, Orai,
Panki Dham, Phaphamau Jn, Phulpur, Pilibhit Jn,
Pokhrayan, Prayag Jn, Prayagraj Jn, Pt. Deen
Dayal Upadhyay Jn , Rae Bareli Jn, Raja Ki
Mandi, Ramghat Halt, Rampur Jn, Renukoot,
Saharanpur Jn., Salempur, Seohara, Shahganj Jn,
Shahjahanpur, Shamli, Shikohabad Jn., Shivpur,
Page 18 of 22Siddharth nagar, Sitapur Jn., Sonbhadra, Sri
Krishna Nagar, Sultanpur Jn, Suraimanpur,
Swaminarayan Chappia, Takia, Tulsipur, Tundla
Jn., Ujhani, Unchahar, Unnao Jn, Utraitia Jn,
Varanasi Cantt., Varanasi City, Vindhyachal,
Virangana Lakshmibai, Vyasnagar, Zafarabad
Uttarakhand 11 Dehradun, Haridwar Jn., Harrawala, Kashipur Jn,
Kathgodam, Kichha, Kotdwar, Lal Kuan Jn,
Ramnagar, Roorkee, Tanakpur
Development works at railway stations under Amrit Bharat Station
Scheme have been taken up at a good pace. Till now, works have been
completed at 180 stations. Names of stations completed so far are as
following:
Alnavar, Amb Andaura, Ambikapur, Amgaon, Anandpur Sahib, Anara,
Angamali For Kaladi, Ayodhya Dham, Badami, Bagalkot, Baijnath
Paprola, Balrampur, Bantawala, Barabhum, Baramati, Bareilly City,
Baripada, Barmer, Barpali, Begumpet, Beohari, Bhanupratappur, Bhilai,
Bhind, Bijnor, Bimalgarh, Bommidi, Bundi, Chanda Fort, Chalakudi,
Changanassery, Chennai Park, Chhindwara, Chidambaram, Chinchpokli,
Chinna Salem, Chirayinkeezh, Cuttack, Dakor, Derol, Deshnoke, Devlali,
Dharwad, Dhule, Dongargarh, Fatehabad, Fatehpur, Fatehpur
Shekhawati, Ferok, Gadag, Gangapur City, Godda, Godhra Jn.,
Gogameri, Gokak Road, Gola Gokarnath, Gomti Nagar, Govardhan,
Govind Garh, Govindpuri, Govindpur Road, Hafizpeta, Haibargaon,
Haldia, Hapa, Harpalpur, Hathras City, Hodal, Idgah Agra Jn., Izzatnagar,
Jaisalmer, Jam Jodhpur, Jam Wanthali, Joychandin Pahar, Junnor Deo,
Kakinada Town, Kalyani Ghoshpara, Kamakhyaguri, Kanalus Jn.,
Karaikkudi Jn., Karamsad, Karimnagar, Katni South, Kedgaon,
Page 19 of 22Khairthal, Khambhaliya, Khalilabad, Koppal, Kosamba Jn., Kulitturai,
Kuttipuram, Lasalgaon, Limbdi, Lohardaga, Lonand Jn., Mahe, Mahuva,
Mailani, Mandal Garh, Mandawar Mahwa Road, Madhupur, Mambalam,
Manaparai, Mandi Dabwali, Mangalagiri, Mannargudi, Matunga, M.C.S.
Chhatarpur, Mithapur, Morappur, Morbi, Muktsar, Munirabad, Muri Jn.,
Murtizapur Jn., Nainpur Jn., Nandura, Narmadapuram, Netaji Subhash
Chandra Bose Itwari Junction, Nidadavolu Jn., Nilambur Road, Okha,
Orchha, Palitana, Panagarh, Panki Dham, Parel, Parlakhemundi,
Pirpainti, Piska, Pokhrayan, Pollachi Jn., Polur, Porbandar, Rajgarh,
Rajmahal, Rajula Jn., Ramagundam, Ramghat Halt, Rayanpadu,
Saharanpur Jn., Sahibzada Ajit Singh Mohali, Sahebgunj, Samakhiyali,
Samalpatti, Sanchi, Sankarpur, Savda, Seoni, Shahad, Shajapur,
Sholavandan, Shoranur Jn., Shridham, Siddharth Nagar, Sihor Jn., Siuri,
Sri Bala Brahmeswara Jogulamba, Srirangam, Srivilliputtur, St.Thomas
Mount, Sullurpeta, Suraimanpur, Swaminarayan Chappia, Talcher,
Tamluk, Thawe, Thiruvarur Jn., Tiruvannamalai, Tripunithura, Tuni,
Ujhani, Urkura, Utran, Vadakara, Vadala Road, Vidisha, Vriddhachalam
Jn., Wadakancheri, Warangal.
The activities for development at other stations have also been taken
up at good pace and progress of some of the above stations is as given
below:
Ghaziabad station: The structural works of station building at main
entry side and second entry side, foundation work of new Foot Over
Bridge-B at Tundla end, roof plaza, extension work of existing Foot Over
Bridge-A, finishing work of electrical substation at main entry side and
second entry side, Magistrate building, Government Railway Police and
Railway Protection Force buildings have been taken up.
Page 20 of 22 Rampur Junction station: The works of new station building, platform
shelter, platform surfacing, booking office, waiting hall and toilet have
been completed. The works of circulating area and Foot Over Bridge
have been taken up.
Shikohabad Junction station: The works of new station building,
platform surfacing of platform no. 1/2, improvement of circulating area,
parking and Divyangjan facilities have been completed. The work of 12
m Foot Over Bridge has been taken up.
Budaun station: The works of parking area, toilet, platform shelter,
platform surfacing and waiting hall have been completed. The work of
improvement to station building has been taken up.
Tulsipur station: The works of improvement of station building,
entrance porch, circulating area, parking area, improvement to waiting
room, toilet, platform shelter and signages have been completed. The
finishing works have been taken up.
Indian Railways has a well established mechanism to monitor
implementation of projects including their reviews, inspection, check for
quality of works and audits. Works are carried out adhering to the
standards and specifications laid down in various codes and manuals.
Inspections/audits/checks are carried out from time to time by various
agencies/officials/multi-disciplinary teams as per laid down instructions
and actions for correction including damages are taken immediately. This
is a continuous and ongoing process.
Development / Upgradation of railway stations is complex in nature
involving safety of passengers & trains and requires various statutory
clearances such as fire clearance, heritage, tree cutting, airport clearance
etc. The progress also gets affected due to brownfield related challenges
Page 21 of 22such as shifting of utilities (involving water/sewage lines, optical fibre
cables, gas pipe lines, power/signal cables, etc.), infringements, operation
of trains without hindering passenger movement, speed restrictions due to
works carried out in close proximity of tracks and high voltage power lines,
etc. and these factors affect the completion time.
Further, development / upgradation / modernization of stations including
Amrit Bharat Station Scheme is generally funded under Plan Head–53
‘Customer Amenities’. The details of allocation and expenditure under
Plan Head–53 are maintained Zonal Railway-wise and not work-wise or
station-wise or state-wise.
For Northern railway, an allocation (Revised Estimate) of ₹ 5,867 crore has
been made for the last four years and current year, out of which an
expenditure of ₹ 5,130 crore (up to February, 2026) has been incurred so
far.
North Central Railway, an allocation (Revised Estimate) of ₹ 2,933 crore
has been made for the last four years and current year, out of which an
expenditure of ₹ 2,523 (up to February, 2026) crore has been incurred so
far.
North Eastern Railway, an allocation (Revised Estimate) of ₹ 1,366 crore
has been made the last four years and current year, out of which an
expenditure of ₹ 1,359 (up to February, 2026) crore has been incurred so
far.
*****
Page 22 of 22