GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO- 3773
ANSWERED ON-25/03/2026
PENDING ROAD PROJECTS IN TAMIL NADU
3773. SHRI P. WILSON:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:-
(a) the current progress, original cost, revised cost and expected date of completion of the Arakkonam–
Kancheepuram (Package-III) and Kancheepuram–Sriperumbudur (Package-IV) stretches of the
Bengaluru–Chennai Expressway, Mamallapuram–Mugaiyur (Package-I) and Mugaiyur–Marakkanam
(Package-II) on NH-332A, Sattanathapuram–Nagapattinam on NH-45A, Walajahpet/Ranipet–TN/AP
Border on NH-40 and Chennai Port–Maduravoyal Elevated Corridor;
(b) the reasons for delay, including land acquisition, environmental/statutory clearances, technical or
financial constraints of concessionaires; and
(c) whether project costs have been revised due to delays and the quantum of escalation and the steps
taken to resolve bottlenecks, fix accountability and ensure time-bound completion?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) The details in respect of projects mentioned in part (a) along with reasons for delay are
annexed. Various factors such as issues related to land acquisition, delays in pre-construction activities,
financial difficulties faced by contractors, force majeure events, and scarcity of construction materials
etc. have resulted in delays and cost overrun in certain projects.
The Government actively monitors National Highway (NH) projects in close coordination with all
stakeholders including project implementing agencies, State Governments, contractors/developers.
Periodic review meetings are held at various levels to resolve the issues and expedite progress. In
addition, many initiatives are being taken to avoid or reduce project delays, including streamlining land
acquisition & environment clearances, online approval of General Arrangement Drawing of Railway
Road Over Bridges/Road Under Bridges (ROBs/RUBs).ANNEXURE REFERRED TO IN REPLY TO PART (a) TO (c) OF RAJYA SABHA UNSTARRED
QUESTION NO. 3773 ANSWERED ON 25/03/2026 ASKED BY SHRI P. WILSON REGARDING
‘PENDING ROAD PROJECTS IN TAMIL NADU’
Cost as Length
Physical
per Revised Revised Complet
Lengt Scheduled Progress
Sl. Name Original Cost Appointed Scheduled ed Reason for
h completion as on
No. Project sanction (Rs.in Date date of as on Delay
(Km) date 28.02.202
(Rs.in Cr.) completion 28.02.20
6
Cr.) 26
1 4-lane 1155.5 1525.1 25.5 08.08.2022 29.07.2024 - 54% 11.0 Work has been
Bangalore - stopped since
Chennai May 2025 due
Expressway to financial
(Arakonam - constraints of
Kancheepura the
m section of Concessionaire.
of NE-7 Pkg- Subsequent to
3) Intention to
Terminate
Notice to the
Concessionaire
by NHAI dated
10.11.2025 and
Speaking Order
dated
08.01.2026 of
NHAI as per the
Court direction,
Senior Lenders
proposed to
exercise their
right to
substitute the
Concessionaire
vide letter dated
20.01.2026.
2 4-lane 2948.3 3605.7 31.7 11.07.2022 09.07.2024 31.07.202 86% 26.0 1) Delay in
Bangalore - 6 determination of
Chennai land/ crop
Expressway compensation
(Kanchepura for erection of
m - new EHT
Sriperumbud towers.
ur section of 2) Delay in
NE-7 Pkg-4) procurement of
Borrow Earth.
3) Unseasonal
rainfall.
4) Slow
Progress of
Concessionaire.3 4-laning of 1009.0 1360.5 31.0 12.05.2022 10.05.2024 31.08.202 64% 16.1 1) Delay due to
Mamallapura 6 Land
m - Mugaiyur Acquisition.
section of 2) Insufficient
NH-332A Resource
(Pkg-I) mobilisation and
Slow Progress
by
Concessionaire.
3) Delay in
Procurement of
Borrow Earth.
4) Additional
works under
COS.
4 4-laning of 825.9 1116.1 31.0 07.12.2023 05.12.2025 31.08.202 57% 20.4 1) Delay due to
Mugaiyur - 6 Land
Marakkanam Acquisition.
section of 2) Insufficient
NH-332A Resource
(Pkg-II) mobilisation and
Slow Progress
by
Concessionaire.
3) Delay in
Procurement of
Borrow Earth.
4) Ground
Improvement
requirements
near
Backwaters.
5 4-laning of 1872.7 2899.8 55.8 05.10.2020 04.10.2022 31.08.202 79% 44.5 1) Delay in
Sattanathapur 6 procurement of
am - earth/ flyash.
Nagapattina 2) Acquisition
m section of of additional
NH-45A land.
3) Public
demands for
additional
project facilities.
4) Slow
Progress of
Concessionaire.
6 4 lane Access 1338.1 1338.1 28.0 30.09.2025 29.09.2027 29.09.202 5% 0.0 Project on
controlled 7 schedule.
Highway
from
Walajapet/
Ranipet to
TN/AP
Border of
NH-40.7 Elevated 1388.0 1388.6 4.9 23.11.2023 20.05.2026 16.11.202 19% 0.0 1) Hon'ble NGT,
Corridor 7 Water
from Chennai Resources Dept.
Port to of GoTN
Maduravoyal directed not to
(Pkg-1) take up work
Elevated 1617.0 1617.0 5.1 23.11.2023 20.05.2026 16.11.202 15% 0.0 along Cooum
Corridor 7 river bank area
from Chennai during Monsoon
Port to season, resulting
Maduravoyal stoppage of
(Pkg-2) work during
Elevated 1299.4 1299.4 4.5 23.11.2023 20.05.2026 16.11.202 15% 0.0 Monsoon
Corridor 7 period.
from Chennai 2) Restrictions
Port to by Police for
Maduravoyal movement of
(Pkg-3) construction
Elevated 1205.4 1210.2 6.4 23.11.2023 20.05.2026 16.11.202 7% 0.0 vehicles through
Corridor 7 Chennai city
from Chennai roads.
Port to 3) Slow progress
Maduravoyal of Contractors
(Pkg-4)
Total 14659.3 17360.5 223.9 118.0
*****