GOVERNMENT OF INDIA
MINISTRY OF CIVIL AVIATION
RAJYA SABHA
UNSTARRED QUESTION NO. : 178
TO BE ANSWERED ON THE 2nd February 2026
PROGRESS OF BELAGAVI AIRPORT
178. SHRI IRANNA KADADI
Will the Minister of CIVIL AVIATION be pleased to state:-
(a) the physical and financial progress of the new integrated terminal building construction at
Belagavi airport (IXG) as on January, 2026;
(b) the status of the runway extension work to facilitate the operation of wide-body aircraft like
Airbus A321 and Boeing 737 for international operations;
(c) the details of the new routes awarded under UDAN 5.0 connecting Belagavi with major economic
hubs like Pune, Chennai and Mangaluru; and
(d) the timeline for operationalization of the new terminal and the projected increase in passenger
handling capacity?
ANSWER
Minister of State in the Ministry of CIVIL AVIATION (Shri Murlidhar Mohol)
(a): The Airports Authority of India (AAI) has undertaken the construction of a new terminal
building and allied works at Belagavi Airport. As on date, the physical progress of the project is
71.5%, and the financial progress is Rs.158.27 crore. The extension of Runway is contingent upon
assessment of traffic demand and availability of land.
(b): Belagavi Airport is a domestic airport and is currently operating A320-type aircraft.
Commencement of international operations from any airport depends on factors such as traffic
potential, demand from the State Government or airlines for international flight operations.
Accordingly, the decision to extend the runway to accommodate wide body aircraft for international
operations is undertaken. Presently there is no such proposal under consideration.
(c): During the UDAN 5.0 bidding round, the routes connecting Belagavi with major economic hubs
such as Pune, Chennai, and Mangaluru were not eligible for bidding, as Belagavi and all the airports
involved in these routes are served airports and therefore, do not fall under the purview of the
Regional Connectivity Scheme.
(d): The new terminal building, with a capacity to handle 3.5 million passengers per annum (MPPA),
is projected to be completed by the end of April, 2026, with an additional period of approximately one
month required for operationalization. However, the timeline for completion of the airport projects
depends upon many factors such as land acquisition, availability of mandatory clearances, financial
closure etc.
******