GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
RAJYA SABHA
UNSTARRED QUESTION NO. 1385
ANSWERED ON – 11/02/2026
PROGRESS OF NATIONAL HIGHWAY PROJECTS IN PUNJAB
1385. DR. SANDEEP KUMAR PATHAK:
Will the Minister of ROAD TRANSPORT AND HIGHWAYS be pleased to state:
(a) the total number of National Highway projects currently under construction in the State of
Punjab and the number of these projects that are delayed beyond the stipulated timelines, project-
wise details thereof;
(b) whether any official data is available with Government regarding the causes of delays in
National Highway projects in Punjab, such as cost escalation, land acquisition, environmental
clearances and negligence of contractors, the details thereof; and
(c) the concrete and time-bound steps taken by Government so far to ensure timely completion of
the delayed projects, the details thereof?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) District-wise and Project-wise status of 37 numbers of ongoing National Highways
(NHs) projects in the State of Punjab, their scheduled and expected completion date is enclosed
at Annexure I.
District-wise and Project-wise status of remaining 15 numbers of Sanctioned/ Awarded NH
projects in the State of Punjab is enclosed at Annexure II.
Development and maintenance of NHs is a continuous process. Works on NHs are
accordingly taken up based on the traffic density, condition of road and synergy with PM Gati
Shakti National Master Plan to keep the NHs in traffic worthy condition.
At present, 4 National Highway Projects are stalled in the State of Punjab mainly due to
delay in land acquisition, issue of non-reimbursement of transportation cost of pond ash by the
Thermal Power Plants of the State in accordance with the notification dated 25.01.2016 of theGovernment in the Ministry of Environment, Forests and Climate Change and non-availability of
earth. The project-wise details are at Annexure III.
Due to non-supply of pond ash free of cost and non-reimbursement of transportation costs
for pond ash for projects taken up between 25.01.2016 and 31.12.2021, Contractors and
Concessionaires are unwilling to continue with project implementation and are staking claims for
compensation, including resorting to arbitration.
Wherever there are defaults attributable to Contractors/Concessionaires, actions against
defaulting agencies are taken up as per the provisions of the Contract/ Concession agreement in
cases of delays, deficiencies/ damages, such as termination of contract agreement, levying of
penalties/ liquidated damages, debarment/ blacklisting, declaring as non-performers etc.
Government actively monitors NH projects in close coordination with project implementing
agencies, State Governments, contractors/developers. Periodic review meetings are held at
various levels, and steps are taken to improve liquidity of funds available with
contractors/developers, to expedite progress. In addition, various initiatives have been taken to
avoid or reduce project delays, including streamlining land acquisition & environment
clearances, online approval of General Arrangement Drawing (GAD) of Railway ROBs/RUBs,
revamping dispute resolution mechanism, premium re-scheduling, one- time fund infusion, etc.
Cooperation and support of the State Government has been sought from time to time, to remove
impediments to project implementation.ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (c) OF RAJYA SABHA
UNSTARRED QUESTION NO. 1385 ANSWERED ON 11.02.2026 ASKED BY DR.
SANDEEP KUMAR PATHAK REGARDING PROGRESS OF NATIONAL HIGHWAY
PROJECTS IN PUNJAB
District wise and Project wise status of Ongoing National Highways (NHs) projects in the
State of Punjab:
Sl Name of the Leng TP Districts Physi Sched Expected Reasons for Penalties Remarks
no Project th (in C from cal uled Completion delay imposed
Km) (Rs which Progr Comp Date on
in Project is ess letion Contractor
Cr) passing (%) date /Concessio
naire for
delays (if
any)
1 4L of Amritsar- 35.13 128 Amritsar 58.20 17.09. 30.06.2026 LA issues, Local Nil -
Ghoman - 0.37 2023 farmers
Tanda - Una demand, COS
Section from
Km 8.270 to Km
54.000 of NH-
503A (Package-
I)
2 Amritsar(airport 38.98 524. Amritsar 78.00 26.10. 31.03.2026 LA issues, Local Nil -
Junction) - 88 2024 farmers
Ramdas from demand, COS
km. 100.835 to
km. 139.813
(Pkg - IV)
3 DAK 28.07 195 Amritsar 29.33 30.08. 30.11.2026 LA issues, non- Nil -
Expressway 1.7 2024 reimbursement
(Phase-I Spur- of pond ash
III) transportation
cost by State
TPPs, Local
farmers
demand, COS,
4 Amritsar 49.94 147 Amritsar 79.33 16.04. 05.05.2026 LA issues, non - Nil -
Bypass (Pkg III) 4.77 2026 reimbursement
from km. 71.496 of pond ash
to km. 105.158 transportation
cost by State
TPPs, Local
farmers
demand, COS,
5 DAK 16.9 216 Kapurthala 27.48 21.06. 31.12.2027 LA issues, non - Nil -
Expressway 5.23 & Taran 2025 reimbursement
(Amritsar Taran of pond ash
Connectivity) transportation
(Spur-1) cost by State
TPPs, Local
farmers
demand, COS
-1-6 Beas-Baba- 31.3 937. Amritsar & 63.65 21.06. 31.12.2026 LA issues, Local Nil -
Bakala-Batala- 82 Gurdaspur 2025 farmers
Dera Baba demand, COS
Nanak (PKG-I)
7 Beas-Baba- 37.8 100 Gurdaspur 77.20 29.12. 31.05.2026 LA issues, Local Nil -
Bakala-Batala- 3.38 2024 farmers
Dera Baba demand, COS
Nanak (PKG-II)
8 Greenfield 43.32 103 Moga & 75.00 29.12. 31.05.2026 LA issues, Local Nil -
Moga to 2.59 Faridkot 2024 farmers
Bajakhana demand, COS
section of NH-
105B
9 4-lane 24.93 646. Bathinda, 98.60 31.07. 30.01.2026 LA issues, Local Nil -
Greenfield 4 Sri Muktsar 2024 farmers
Malout & Sahib & demand, COS
Dabwali Sirsa
Bypasses
10 6 lane Amritsar- 61.87 202 Bathinda 65.00 15.06. 16.08.2026 LA issues, non- Nil -
Bathinda from 9.17 2026 reimbursement
Km 89 to 155 of of pond ash
NH-754A (Pkg- transportation
III) HAM cost by State
TPPs, Local
farmers
demand, COS
11 4 Laning of 44.96 140 Fazilka 55.00 12.04. 30.11.2026 LA issues, Local Nil -
Abohar to 9.88 2026 farmers
Fazilka section demand, COS
of NH-07
12 4/6 lane 43.26 110 SAS Nagar 76.34 15.02. 31.05.2026 Flood in 2023, Nil -
Ludhiana 7 & 2025 Restriction on
Roopnagar Roopnagar mining by
Greenfield NH Hon'ble
205K (Pkg-III) Supreme Court,
Land
Acquisition &
Farmers Protest
13 Sirhind-Mohali 27.37 679 SAS Nagar 76.00 07.05. 30.06.2026 Delay in Nil -
NH-205 AG & 2025 approval from
Fatehgarh railway and
Sahib Irrigation (Syl
Canal), COS,
Local Demands
Land
Acquisition, and
farmer protest
14 Ambala 30.83 164 SAS Nagar 80.01 11.10. 30.06.2026 Farmer Protest, Nil -
Chandigarh 2 & Patiala 2025 Land
greenfield Acquisition ,
(HAM) COS
-2-15 6 lane Amritsar- 39 122 Jalandhar, 64.31 13.11. 30.06.2027 LA issues, Local -
Bathinda Km 9.38 Kapurthala 2024 farmers
0.00 to 39.00 and Moga demand, COS
(Pkg-I)
16 4/6 lane 46.5 216 Jalandhar 41.64 14.01. 30.06.2027 LA issues, Local Nil -
Jalandhar 7.09 and 2025 farmers
Bypass Kapurthala demand, COS
17 6 lane Amritsar- 54 180 Moga and 63.06 26.06. 31.12.2026 NA Nil -
Bathinda Km 1.37 Bathinda 2026
39.00 to 93.00
(pkg-II)
18 Hoshiarpur-Una 27.92 571. Hoshiarpur 10.27 20.05. 20.05.2027 NA Nil -
(2L+PS) length 34 2027
(incl
Hoshiyarpur
bypass) NH-
503A
19 4/6 lane 37.7 136 Ludhiana 2.00 10.12. 11.10.2027 Contractor has Nil -
Ludhiana 8.91 2024 stopped the
Roopnager work due to
(Pkg-I) non-availability
of land. With the
land issues
being
addressed, the
Concessionaire
has demanded
transportation
charges for
pond ash by
NHAI and
intervention by
NHAI for
according
permission from
State
Government for
desilting of
Satluj river.
20 Ludhiana 30.3 906. Bathinda, 78.50 13.09. 07.03.2026 LA issues Nil -
Bathinda from 51 Barnala 2025
Km. 0.00 to Km.
30.300 (Pkg-I)
21 4-lane 48.62 119 Hoshiarpur 9.33 30.03. 31.03.2027 Nil Nil -
Phagwara 6.38 , 2027
Hoshiarpur NH- Kapurthala
344B ,
Jalandhar,
SBS Nagar
-3-22 Ludhiana 45.24 155 Ludhiana, 10.09 29.09. 29.09.2027 Nil Nil -
Bathinda from 5.13 Barnala 2027
Km. 30.300 to
Km. 75.543
(pkg-II)
23 DAKExpresswa 36.94 175 Malerkotla 95.02 09.07. 25.03.2026 LA issues, non- Nil EOT
y (Phase-I Pkg- 9.82 & Sangrur 2024 reimbursement approved
VII) of pond ash upto
transportation 25.03.2026
cost by State
TPPs,
Local farmers
demand, COS
24 DAK 35.09 189 Malerkotla 31.08 13.03. Project is LA issues, non- Nil -
Expressway 5.74 & Ludhiana 2025 under reimbursement
(Phase-I Pkg- Foreclosure/ of pond ash
VIII) Termination transportation
cost by State
TPPs
25 DAK 43.04 185 Ludhiana & 69.07 16.07. 30.06.2026 LA issues, Non- Nil EOT
Expressway 1.47 Jalandhar 2024 reimbursement approved
(Phase-I Pkg- of pond ash upto
IX) transportation 30.06.2026
cost by State
TPPs
26 DAK 39.5 217 Jalandhar 62.99 09.07. Project is LA issues, non- Nil -
Expressway 7.54 2024 under reimbursement
(Phase-I Pkg-X) Foreclosure/ of pond ash
Termination transportation
cost by State
TPPs
27 DAK 43.02 217 Jalandhar, 43.45 14.11. Project is LA issues, non- Nil -
Expressway 5.35 Kapurthala 2024 under reimbursement
(Phase-I Pkg- & Foreclosure/ of pond ash
XI) Gurdaspur Termination transportation
cost by State
TPPs
28 DAK 35.28 173 Gurdaspur 25.62 20.02. 20.02.2027 NA Nil -
Expressway 4.18 2027
(Phase-I Pkg-
XII)
29 Delhi Katra 12.35 666. Pathankot 14.92 15.07. 15.07.2027 NA Nil -
Expressway- 81 2027
Pathankot link
road
-4-30 Up-gradation to 63.27 263. Ferozepur, 78 15.04. 15.04.2026 • A Delay has NIL
two lane with 19 Faridkot, 2025 occurred in the
paved shoulder Muktsar handover of toll
configuration of plaza land by
NH-354 Section the office of
Arifkes- CALA-Cum
Ferozepur- SDM, Sri
Muktsar-Malaut Muktsar Sahib
from Km .(Resolved)
201.500 to Km • Delay in
212.500 & Km obtaining the
229.690 to Km NOC and GAD
269.960 and approval for
strengthening of MNBs and
existing Culverts from
pavement from the Water
Km 212.500 to Resources
Km 229.690 Department.(Re
(excluding Km solved)
218.500 to • Delay in
223.690) of NH- Receiving utility
354 on EPC shifting
Mode in the Estimates from
State of Punjab. concerned utility
(Job No. NH- owning
354-PB-2020- Departments.(R
21-532) esolved)
31 Work sanction 0.01 38.0 Fazilka 05- 31.08. 28.02.2026 • Delay in NIL
for Construction 2 Apr-00 2024 approval of
of 2 lane ROB launching
at Railway scheme by
Crossing No. C- Railway
28A on Abohar- Authority.(Resol
Fazlika Rail ved)
section at Km • Delay in
39/3-4 & on NH- getting
07 at Km encroached
12.560 on land from 52nd
Fazlika Border Battalion BSF,
in the State of Fazilka
Punjab on EPC (Resolved)
mode.(Job No.
NH-07-PB-
2021-22-549)
-5-32 Work of 27.66 152. Sri Muktsar 96 15.04. 28.02.2026 All works except NIL
Widening/upgra 58 Sahib 2025 Toll Plaza has
dation of 2-Lane been
with paved completed. The
shoulder of Sri construction of
Muktsar Sahib Toll Plaza
to Malout road delayed due to
from Km non availability
279.400 to Km of encumbrance
307.060 section free site to the
of NH-354 in agency by
the State of SDM-cum-
Punjab on EPC CALA, Malout.
mode. (Job No. Now, all issues
NH-354-PB- have been
2021-22-555) resolved and
work of Toll
Plaza is under
progress.
33 Construction of 0.01 87.5 Jalandhar 38 20.12. 31.12.2026 • Demand of NIL
2 lanes ROB 1 2025 local public to
over L.C.NO. S- convert RC wall
53/T-2 atCH. into viaduct.
50+665 of NH- • Revision of
703A GAD by
(Jalandhar - railways to
Kapurthala - incorporate SV
Sultanpur Lodhi loading and
- Makhu) in the cogestion
State of Punjab factor.
on EPC mode.
(Job No. NH-
703A-PB-2021-
22-556)
34 Construction of 0.01 43.4 Ferozepur 44 07.01. 31.12.2026 Revision of NIL
Rail Over 4 2026 GAD by
Bridge in lieu of railways to
Railway incorporate SV
Crossing no.E/2 loading and
on Ferozepur- cogestion
Fazlika Rail factor.
section at Km
2/4-5 & on NH-
95(New NH-05)
section
Ferozepur to
Indo Pak Border
at km 205.320
(near Ferozepur
city & village
Madhre) in the
State of Punjab
on EPC mode.
(Job No. NH-95
(New NH-05)-
PB-2021-22-
550)
-6-35 Four Laning 7.25 52.9 Jalandhar 30- 07.06. 30.04.2026 Majority of the NIL
with paved 9 Mar- 2025 work has been
shoulders from 00 completed
Km 29.00 to Km except BC in
36.25 section of 0.85 Km reach
Jalandhar (Four lane
Kapurthala portion). BC
Sultanpur Lodhi work is stopped
Lohian Makhu due to winter
Road, NH- season. BC
703A, (7.25 work will
Km) in the State resume in
of Punjab March 2026
36 Rehabilitation 13.2 94.6 Moga 45 20.02. 31.12.2026 Due to land NIL
and Up- 2026 hindrance.
gradation to 2
Lane with
paved
shoulders of
Patto Jawahar
Singh Wala to
Dina village
Kangar road
section of NH-
254 Design
Chainage from
Km 38+000 to
Km 51+200 in
the State of
Punjab
(Package– III).
37 Development to 21 546. Bathinda 30 05.11. 05.11.2026 No delay NIL
4-lane with 67 2026
paved shoulder
for the road
section
Talwandi Sabo-
Raman road to
refinery Road
junction with
Bathinda
Dabwali Road
of NH-254 from
existing Km
131.600 to Km
155.650
(Design Km
131+600 to km
155+600) in the
State of Punjab.
(Job No: NH-
254-PB-2022-
23-565
-7-ANNEXURE-II
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (c) OF RAJYA SABHA
UNSTARRED QUESTION NO. 1385 ANSWERED ON 11.02.2026 ASKED BY DR.
SANDEEP KUMAR PATHAK REGARDING PROGRESS OF NATIONAL HIGHWAY
PROJECTS IN PUNJAB
District wise and Project wise status of remaining Sanctioned/Awarded NH projects in the
State of Punjab:
Sl Name of the Project Length TPC (Rs Districts from Expected Remarks
no (in Km) in Cr) which Project is Completion from
passing Appointed date
(in months)
1 Zirakpur Bypass 19.5 1878.67 SAS Nagar 24 At tender stage
Panchkula
2 Construction of 4L+PS Sri Muktsar 19.306 440.97 Ferozepur 24 At tender stage
Sahib bypass from existing Km.
269.960 of NH-354 to existing km
39.280 of NH-754 in the State of
Punjab.
3 Widening and upgradation of road 1.22 7.28 Sangrur 3 At tender stage
from 2 lane with paved shoulder to 4
lane with paved shoulder for
rectification of blackspot ID PB 03
189 of series 2017 19 at Km 159 550
Pakho Kalan on NH 703 in the State
of Punjab
4 "Construction of VUP for rectification 1.3 28.64 Sangrur 18 At tender stage
of blackspot (ID:PB-03-164 of series
2017-19) at km 287.710 (Grain
Market Bhikhi) on NH 148B in the
State of Punjab
5 Widening and upgardation of road 1 6.49 Sangrur 3 At tender stage
from 2Lane with PS to 4-lane PS for
rectification of blackspot ID No. PB-
(03)-186 at location Km 154/310
(Rure ka kalan) on Nh-703 in the
State of Punjab on EPC mode
6 "Construction of VUP for rectification 1.6 25.74 Bathinda 18 At tender stage
of blackspot (ID: PB-03-256 of series
2017-19) atlocation Km 4+100 near
village Deon on NH-754 in the State
of Punjab
7 Construction of VUP for rectification 1.67 42.57 Bathinda 18 At tender stage
of blackspots (ID: PB-03-261 of
series 2017-19) at location at Km
317+880 (Ramnagar Chowk) on NH-
148B in the State of Punjab
8 Widening and strengthening of NH 8.06 35.62 Sangrur 9 At tender stage
148B from Km 226.370 to Km
234.900 i.e. from Tohana (Haryana
Border) to Moonak Jakhal excluding
stretch from Km 233.830 to Km
234.300 On EPC mode in the State
of Punjab
-8-9 Widening and Upgradation from 2 3.75 29.97 Abohar 12 At tender stage
lanes with paved shoulder to four
lane in Km 17.600 to 21.350 of NH
07 Section Sulemanki Border-Fazilka
on EPC mode in the State of Punjab
10 Development of 6-lane Greenfield 25.24 1424.55 Ludhiana 24 Terminated and re-
Southern Ludhiana Bypass from awarded again on
intersection with NH-44 near Village 13.03.2025.
Rajgarh to intersection with Delhi
Katra Expressway (NE-5) near
Village Ballowal, km 0+000 to km
25+240
11 Development of 4L Northern Patiala 28.9 934.85 Patiala 24 -
Bypass
12 Construction of VUP for rectification 3.66 78.38 Bathinda 18 LOA has been issued
of blackspots at location Km on 11.11.2025.
299+520 (Mansa Kenchian Chowk) Agreement has been
(ID: PB-03-170 of series 2017-19) signed on 20.12.2025.
and Km 304+520 (Bhaini Bagha
Chowk) (ID:PB-03-173 of series
2017-19) on NH-148B in the State of
Punjab
13 Construction of VUP for rectification 1.685 27.48 Bathinda 18 LOA has been issued
of blackspots (ID: PB-03-258 of on 11.11.2025.
series 2017-19) at location at Km Agreement has been
340+260 (Kotshamir village) on NH- signed on 20.12.2025.
148B in the State of Punjab
14 Construction of VUP for rectification 1.475 27.51 Bathinda 18 LOA has been issued
of blackspots (ID: PB-03-162 of on 11.11.2025.
series 2017-19) at location at Km Agreement has been
190.050 (Ramditta Chowk) on NH- signed on 20.12.2025.
703 in the State of Punjab
15 Strengthening of stretches of NH- 65.45 89 Bathinda 9 LOA has been issued
148B (Km 234.900 to Km 244.750 on 01.01.2026.
and Km 287.710 to Km 349.640) and
NH-703 (Km 182.750 to Km 189.240)
in the State of Punjab
-9-ANNEXURE-III
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (c) OF RAJYA SABHA
UNSTARRED QUESTION NO. 1385 ANSWERED ON 11.02.2026 ASKED BY DR.
SANDEEP KUMAR PATHAK REGARDING PROGRESS OF NATIONAL HIGHWAY
PROJECTS IN PUNJAB
Details of stalled projects in the State of Punjab:
Sl Name of the Date of Scheduled Target Date from Reasons for Stalling of Project
no Project Commence Completio Completio when the
ment n date n Date project is
stalled
1 4/6 lane 12.12.2022 10.12.2024 11.10.2027 18.04.2024 Contractor has stopped the work due to non-
Ludhiana availability of land. With the land issues being
Roopnager (Pkg- addressed, the Concessionaire has demanded
I) transportation charges for pond ash and
intervention by NHAI for according permission
from State Government for desilting of Sutlej
river.
2 DAK 15.03.2023 13.03.2025 Project is 19.08.2024 LA issues, non-reimbursement of pond ash
Expressway under transportation cost by State TPPs
(Phase-I Pkg- Foreclosur
VIII) e/Terminati
on
3 DAK 11.07.2022 09.07.2024 Project is 01.04.2025 LA issues, non-reimbursement of pond ash
Expressway under transportation cost by State TPPs
(Phase-I Pkg-X) Foreclosur
e/Terminati
on
4 DAK 15.11.2022 14.11.2024 Project is 19.08.2024 LA issues, non-reimbursement of pond ash
Expressway under transportation cost by State TPPs
(Phase-I Pkg-XI) Foreclosur
e/Terminati
on
*****
-10-