GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 5504
TO BE ANSWERED ON 25.03.2026
RAIL CONNECTIVITY FOR NAGARKURNOOL
5504. DR. MALLU RAVI:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware that large parts of southern
Telangana, particularly Nagarkurnool Lok Sabha Constituency still lack
direct railway connectivity despite decades of proposals and if so, the
details thereof;
(b) whether the Government has received representations seeking
construction of new railway lines such as Dornakal–Nalgonda–
Kalwakurthy–Nagarkurnool, Wanaparthy–Gadwal and Jadcherla–
Nandyal via Nagarkurnool and Kollapur to improve connectivity in the
region and if so, the details thereof;
(c) whether the Government has conducted any feasibility study or Final
Location Survey for new railway corridors connecting unserved
districts of southern Telangana including Nagarkurnool and if so, the
details thereof;
(d) whether it is a fact that railway infrastructure projects in Telangana
have faced delays due to land acquisition issues and funding gaps and
if so, the details thereof;
(e) the details of railway projects sanctioned, under survey or pending
approval in Telangana during the last five years particularly those
affecting backward districts such as Nagarkurnool; and
(f) the timeline proposed by the Government for improving rail connectivity
and initiating new railway line projects in the region?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (f): Dornakal, Nalgonda, Gadwal, Jadcherla, Nandyal are existing
railway stations. For improving the connectivity in Southern Part of Telangana,
§ Page 1 of 5survey for Dornakal-Gadwal new line (296 Km) has been sanctioned for
preparation of Detailed Project Report (DPR). The survey has been completed.
The line passes through Suryapet, Nalgonda, Kalwakurthy, Nagarkurnool and
Wanaparthy.
After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary approvals
viz. appraisal of NITI Aayog, Ministry of Finance etc. As sanctioning of projects
is a continuous and dynamic process, exact timelines depend upon appraisals
and approvals by various stakeholders.
Survey for Jadcherla-Nandyal new line (182 Km) was carried out. The project
has low traffic projections.
TELANGANA:
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Telangana is as under:
Period Outlay
2009-14 ₹886 Cr./Yr.(including Andhra Pradesh)
2025-26 ₹5,337 Cr.
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Telangana during 2009-14 and 2014-25 is as under:
Period New Track Average Commissioning of new
Commissioned tracks
2009-14 87 Km 17.4 Km/per year
2014-25 774 Km 70.4 Km /per year (more than 4 times)
Projects sanctioned:
As on 01.04.2025, 20 Railway projects (6 New Lines and 14 Doubling), of a
total length of 2,166 Km, costing ₹35,045 crore falling fully/partly in the
Page 2 of 5State of Telangana have been sanctioned. The summary is as under:-
Category No. of Total Length Total Exp. upto
projects Length Commissioned March, 2025
(in Km) till March, 2025 (₹ in Cr.)
(in Km)
New Line 6 840 245 4,611
Doubling/Mult 14 1,326 303 6,939
i-tracking
Total 20 2,166 548 11,550
Recently completed projects:
Details of some of the completed projects falling fully/partly in the State of
Telangana are as under:
Cost
S. No. Project
(₹ in Cr.)
1 Peddapalli - Nizamabad new line (178 Km) 926
2 Jaggayyapeta - Janpahad new line (48 Km) 737
3 Akkanapet - Medak new line (17 Km) 205
4 Bhadrachalam Road - Sattupalli new line (56 Km) 990
5 Raghavapuram - Mandamari Doubling (24 Km) 165
6 Raichur - Guntakal Doubling (81 Km) 388
7 Secunderabad- Mehboobnagar Doubling (85 Km) 1,266
8 Multi- Modal Transport System (MMTS) Phase-II,
1,156
Hyderabad (103 Km)
9 Byepass line at Peddapalli (2 Km) 37
Ongoing Projects:
Details of some of the projects falling fully/partly in the State of Telangana
which have been taken up are as under:
S.N Name of Project Cost (Cr)
1 Manoharabad - Kothapalli new line (151 Km) 2,781
2 Malkangiri - Pandurangapuram new line (174 Km) 3,592
3 Kazipet – Vijaywada 3rd line (220 Km) 3,315
4 Kazipet -Ballarshah 3rd line (202 Km) 3,183
5 Guntur - Bibinagar Doubling (239 Km) 2,853
6 Mudkhed - Medchal - Dhone Doubling (417 Km) 4,686
7 Bhadrachalam Road – Dornakal Doubling (55 Km) 770
8 Motumari - Vishnupuram doubling and RoR at 1,596
Motumari (100 Km)
Page 3 of 5S.N Name of Project Cost (Cr)
9 Nashkal (Pindial) - Hasanparthi Road bypass (25 Km) 465
10 Secunderabad (Sanathnagar) - Wadi 3rd and 4th line
5,012
(173 Km)
11 Dornakal Rail over Rail (RoR) Flyover (11 Km) 327
In last 3 years i.e. (2022-23, 2023-24, 2024-25) and current Financial Year
i.e.2025-26, 57 surveys (18 New Line and 39 Doubling) covering a total length
of 5,665 Km have been sanctioned falling fully/partly in the State of Telangana.
Sanction of any railway project depends upon many parameters/factors which
include the following:
Anticipated traffic projections and remunerativeness of the proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Execution of important infrastructure projects falling fully/partly in the State of
Telangana is held up due to delay in land acquisition. Status of land acquisition
in Telangana is as under:
Total Land required 2,343 Ha
Land Acquired 1,580 Ha (67%)
Balance Land to be acquired 764 Ha (33%)
Details of some major projects which are delayed due to land acquisition are
as under:-
SN Name of the project Total Land Balance Amount
land acquired Land to be Paid to
required (Ha) acquired State (Cr.)
(Ha) (Ha)
1. Guntur - Bibinagar 31 0 31 40
Doubling
Page 4 of 52. Mudkhed – Medchal & 70 0 70 30
Mahbubnagar – Dhone
Doubling
3. Kazipet - Vijaywada 3rd 135 118 17 159
Line
4. Manoharabad – 1146 1050 96 -
Kothapalli New Line
Completion of Railway project/s depends on various factors which include the
following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****