**Executive Summary**
This document addresses Lok Sabha Unstarred Question No. 2940 regarding rail connectivity in Tripura, to be answered on December 17, 2025. The document details measures taken to improve rail infrastructure, resilience, and alternative connectivity options. It outlines completed and ongoing projects, budget allocations, and challenges affecting project completion.
**Key Points / Main Content**
* **Rail Connectivity Status:**
* Tripura is already connected to the rail network of Indian Railways.
* **Completed Projects in Tripura:**
* Agartala – Sabroom New Line (112 Km): ₹3170 crore
* Lumding – Badarpur – Kumarghat Gauge Conversion (244 Km): ₹6500 crore
* Kumarghat – Agartala New Line (107 Km): ₹1242 crore
* **Planned Projects:**
* Final Location Surveys (FLS) sanctioned for Chandranathpur – Agartala doubling (244 Km) and Jirania-Bodhjung Nagar (14 Km) new line, to prepare Detailed Project Reports (DPR).
* **Agartala-Kolkata Connectivity:**
* Kolkata and Agartala are connected through existing railway network.
* Agartala-Akhaura (12 km) new line project sanctioned for improved connectivity via Bangladesh.
* Alignment for Indian side from Agartala Railway Station to Nischintpur (5.46 km) commissioned.
* **North Eastern Region Budget Allocation:**
* Budget allocation has increased significantly over the last five years.
* ₹10,440 crore allocated for 2025-26, about 5 times the 2009-14 outlay.
* **New Track Commissioning (2009-2025):**
* 2009-14: 333 Km commissioned (66.6 Km/year).
* 2014-25: 1,840 Km commissioned (167.27 Km/year).
* **Sanctioned Railway Projects as of April 1, 2025 (NER):**
* 12 projects (8 New Lines, 4 Doubling) sanctioned, totaling 777 Km and costing ₹69,342 crore.
* New Lines: 8 projects, 448 Km sanctioned, 113 Km commissioned, ₹38,078 crore expended.
* Doubling/Multitracking: 4 projects, 329 Km sanctioned, 165 Km commissioned, ₹3,598 crore expended.
* **Commissioned Projects (since 2014):**
* Agartala - Sabroom new line (112 Km): ₹3,170
* Agartala - Akhaura new line (5 Km): ₹865
* Rangiya - Murkongselek gauge conversion (510 Km): ₹3,019
* Kumarghat - Agartala gauge conversion (109 Km): ₹1,242
* Lumding - Badarpur - Silchar & Badarpur - Kumarghat gauge conversion (412 Km): ₹6,500
* Lumding - Hojai doubling (45 Km): ₹410
* Digaru - Hojai doubling (102 Km): ₹1,873
* New Bongaigaon - Agthori doubling (143 Km): ₹2,048
* Bogibeel Bridge (92 Km): ₹5,820
* **Main Projects in the North East Region:**
* Jiribam - Imphal new line (111 Km): ₹21,886
* Dimapur - Kohima new line (82 Km): ₹15,230
* Murkongselek - Pasighat new line (27 Km): ₹1,249
* New Bongaigaon - Goalpara - Guwahati (Kamakhaya) doubling (176 Km): ₹4,962
* Saraighat Bridge doubling (7 Km): ₹1,474
* Kamkhya Guwahati 3rd line (6 Km): ₹395
* Lumding – Furkating doubling (140 Km): ₹2,124
* Furkating – Tinsukia doubling (194 Km): ₹3,634
* **Sanctioned Surveys (2022-2026):**
* 18 surveys (14 New Line, 4 Doubling) of total length 1,804 Km in NER, including Tripura, have been sanctioned.
* **Project Sanctioning Process:**
* Requires consultation with stakeholders, including State Governments, and approvals from NITI Aayog, Ministry of Finance.
* **Factors Affecting Project Completion:**
* Land acquisition, forest clearance, shifting utilities, statutory clearances, geological conditions, law and order, and available working months.
* **Government Steps for Speedy Implementation:**
* Increased fund allocation, delegation of powers, close monitoring, and regular follow-up with State Governments.
**Impact Analysis**
**Stakeholder: Tripura Residents and Businesses**
* **Impact**: Improved rail connectivity facilitates passenger and goods transport, boosting the economy and accessibility.
* **Action Required**: No immediate action required, but benefit from improved transportation infrastructure.
**Stakeholder: Ministry of Railways**
* **Impact**: Responsible for planning, funding, and executing railway projects to improve connectivity and infrastructure in Tripura and the North Eastern Region.
* **Action Required**: Continue monitoring project progress, securing necessary approvals, and addressing factors affecting project completion.
**Stakeholder: North Eastern Region (NER) including State Governments**
* **Impact**: Benefit from enhanced railway infrastructure and economic development opportunities.
* **Action Required**: State Governments should facilitate land acquisition, forest clearances, and other necessary approvals for projects.
**Stakeholder: NITI Aayog and Ministry of Finance**
* **Impact**: Play a role in appraising and approving railway projects.
* **Action Required**: Expedite project appraisals and approvals to ensure timely implementation.
Key Entities Referenced
Tripura: Focus of the policy is to improve rail connectivity in the state of Tripura.
Ministry of Railways: The government ministry responsible for railway infrastructure projects in Tripura.
Agartala-Akhaura Rail Line project: A project to improve rail connectivity between Agartala and Kolkata through Bangladesh.
North Eastern Region (NER): The region in India which includes the state of Tripura.
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 2940
TO BE ANSWERED ON 17.12.2025
RAIL CONNECTIVITY IN TRIPURA
2940. SMT. KRITI DEVI DEBBARMAN:
Will the Minister of RAILWAYS be pleased to state:
(a) the details of the measures being taken to improve rail connectivity
in Tripura a landlocked State which heavily depends on railways for
goods and passenger transport;
(b) the details of the step being taken to ensure more resilient and
uninterrupted connectivity in light of frequent disruptions due to
floods and landslides; and
(c) whether the Government considers actively pursuing the alternate
arrangement to improve rail connectivity between Agartala and
Kolkata through Bangladesh particularly the Agartala-Akhaura Rail
Line project and if so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Tripura is already connected to Rail network of Indian Railways.
To improve rail connectivity to Tripura following projects falling fully/partly
in the State of Tripura have been completed:-
Contd….2/--:2:-
S.N. Name of the Project Cost
(₹ in crore)
1. Agartala – Sabroom New Line (112 Km) 3170
2. Lumding – Badarpur – Kumarghat Gauge Conversion 6500
(244 Km)
3. Kumarghat – Agartala New Line (107 Km) 1242
To provide additional railway infrastructure in the State of Tripura, Final
Location Surveys (FLS) for Chandranathpur – Agartala doubling (244 Km)
and Jirania-Bodhjung Nagar (14 Km) new line have also been sanctioned for
preparation of Detailed Project Report (DPR).
Kolkata and Agartala are already connected through existing railway
network via New Farakka, New Jalpaiguri, Guwahati and Lumding.
To provide additional connectivity between Agartala and Kolkata through
Bangladesh and encourage trade between the two nations, Agartala-
Akhaura (12 km) new line project has been sanctioned. The alignment for
Indian side of the project runs from Agartala Railway Station to Nischintpur
(5.46 km), which has been commissioned. Further connectivity to Tripura
via Bangladesh can improve after upgradation of track in Bangladesh.
North Eastern Region
Budget allocation during the last five years has increased significantly.
Budget allocation for infrastructure projects and safety works, falling
fully/partly in North Eastern Region (NER) including the state of Tripura is as
under:-
Contd….3/--:3:-
Period Outlay
2009-14 ₹2,122 crore/year
2025-26 ₹10,440 crore (about 5 times)
The details of commissioning/laying of new track falling fully/partly in North
Eastern Region (NER) including the state of Tripura during 2009-14 and 2014-
2025 is as under:-
Period New track
Average commissioning of new tracks
Commissioned
2009-14 333 Km 66.6 Km/year
2014-25 1,840 Km 167.27 Km/year (about 2.5 times)
As on 01.04.2025, 12 Railway projects (08 New Lines, 04 Doubling), of a total
length of 777 Km, costing ₹69,342 crore falling fully/partly in North Eastern
Region (NER) including the state of Tripura have been sanctioned. The
summary is as under:-
Category No. of Total Length Exp. upto
sanctioned Length Commissioned Mar’25
projects (in Km) upto (₹ in Cr.)
Mar’25 (in Km)
New Lines 08 448 113 38,078
Doubling/Multitracking 04 329 165 3,598
Total 12 777 278 41,676
Contd….4/--:4:-
Projects commissioned falling fully/partly in North East Region including the
state of Tripura since 2014, are as under:
S.No. Project Cost
(₹ in crore)
1 Agartala - Sabroom new line (112 Km) 3,170
2 865
Agartala - Akhaura new line (5 Km)
3 3,019
Rangiya - Murkongselek gauge conversion (510 Km)
4 1,242
Kumarghat - Agartala gauge conversion (109 Km)
5 Lumding - Badarpur - Silchar & Badarpur - Kumarghat 6,500
gauge conversion (412 Km)
6 410
Lumding - Hojai doubling (45 Km)
7 Digaru - Hojai doubling (102 Km)
1,873
8 New Bongaigaon - Agthori doubling (143 Km)
2,048
9 Bogibeel Bridge (92 Km) 5,820
Some of the main projects falling fully/partly in the North East Region
including the state of Tripura which have been taken up are as under:-
S.No. Name of the project Cost
(₹ In crore)
1 Jiribam - Imphal new line (111 Km) 21,886
Contd….5/--:5:-
2 Dimapur - Kohima new line (82 Km) 15,230
3 Murkongselek - Pasighat new line (27 Km) 1,249
4 New Bongaigaon - Goalpara - Guwahati 4,962
(Kamakhaya) doubling (176 Km)
5 Saraighat Bridge doubling (7 Km) 1,474
6 Kamkhya Guwahati 3rd line (6 Km) 395
7 Lumding – Furkating doubling (140 Km) 2,124
8 Furkating – Tinsukia doubling (194 Km) 3,634
Further, during the last three years i.e. 2022-23, 2023-24, 2024-25 and the
current financial year 2025-26, 18 surveys (14 New Line, and 4 Doubling) of
total length 1,804 Km falling fully/ partly in North East Region including the
projects in the State of Tripura have been sanctioned.
After preparation of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog, Ministry
of Finance etc. As sanctioning of projects is a continuous and dynamic
process, exact timelines depend upon appraisals and approvals by various
stakeholders
Completion of Railway project/s depends on various factors which include
the following:
Contd….6/--:6:-
• Land acquisition by State Government
• Forest clearance
• Shifting of infringing utilities
• Statutory clearances from various authorities
• Geological and topographical conditions of area
• Law and order situation in the area of project site
• Number of working months in a year for particular project site
etc.
Various steps taken by the Government for effective and speedy
implementation of rail projects include:
Substantial increase in allocation of funds.
Delegation of powers at field level.
Close monitoring of progress of project at various levels.
Regular follow up with State Governments and concerned
authorities for expeditious land acquisition, forestry and Wildlife
clearances and for resolving other issues pertaining to projects.
*****