GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 4161
TO BE ANSWERED ON 18.03.2026
RAIL CONNECTIVITY TO WAYANAD
4161. SMT. PRIYANKA GANDHI VADRA:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is considering proposals to improve inter and
intra State rail connectivity to Wayanad Lok Sabha Constituency and if
so, the details thereof;
(b) whether the Detailed Project Report (DPR) for the Nanjangud-Nilambur
railway line has been finalized and if so, the details thereof including
the timeline for submission;
(c) the details of railway overbridges and underpasses sanctioned to
replace level crossings in Wayanad Lok Sabha Constituency including
the current progress; and
(d) whether the Government proposes to introduce special tourist trains to
promote the unique heritage of Wayanad Lok Sabha Constituency and if
so, the details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (d): Wayanad district is already connected with railway network and
served by Nilambur Road Station which is catered by the following 16 train
services:
SN Train No. and Name
1 16325 Nilambur Road - Kottayam Express
...2/-
§-2-
2 16326 Kottayam - Nilambur Road Express
3 16349 Thiruvananthapuram North - Nilambur Road Express
4 16350 Nilambur Road - Thiruvananthapuram North Express
5 56322 Nilambur Road - Shoranur Passenger
6 56323 Shoranur - Nilambur Road Passenger
7 56607 Palakkad - Nilambur Road Passenger
8 56608 Nilambur Road - Palakkad Passenger
9 56609 Shoranur - Nilambur Road Passenger
10 56610 Nilambur Road - Shoranur Passenger
11 56611 Shoranur - Nilambur Road Passenger
12 56612 Nilambur Road - Shoranur Passenger
13 56613 Shoranur - Nilambur Road Passenger
14 56614 Nilambur Road - Shoranur Passenger
15 66325 Nilambur Road - Shoranur Passenger
16 66326 Shoranur - Nilambur Road Passenger
For providing connectivity of Nilambur road station with Karnataka, the
Survey of Nilambur-Nanjangud new line was carried out in 2007-08 but
project could not be taken forward due to low traffic projections.
However, on public demand, a fresh Final Location Survey (FLS) for
Nilambur-Nanjangud new line project (236 Km) has been sanctioned for
preparation of Detailed Project Report (DPR). The field survey has been
completed.
...3/--3-
After preparation of Detailed Project Report (DPR), sanctioning of project
requires consultation with various stake-holders including State
Governments and necessary approvals viz. appraisal of NITI Aayog,
Ministry of Finance etc. As sanctioning of projects is a continuous and
dynamic process, exact timelines cannot be fixed.
Keralam :-
Railway Budget:-
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling
fully/partly in the State of Keralam is as under:-
Period Outlay
2009-14 ₹ 372 crore/year
2025-26 ₹3,042 crore (more than 8 times)
Recently Completed Projects:-
Details of some of the recently completed projects falling fully/partly in
Keralam are as under :
S. Cost
Project
N (₹ in Crores)
1 Dindigul - Pollachi - Palghat & Pollachi - Coimbatore
1,360
gauge conversion (217 km)
2 Quilon – Tirunelveli - Tiruchendur gauge conversion
1,122
(357 km)
3 Mulanturutti-Kuruppantara doubling (24 km) 303
4 Chenganur-Chingavanam doubling (27 km) 436
5 Ambalapuzha-Haripad doubling (18 km) 346
6 Kurruppanthara-Chingavanam doubling (27 km) 749
...4/--4-
Ongoing Projects:-
Some of the projects falling fully/partly in Keralam which have been taken
up are as under:
Cost
S No. Project
(₹ in Crores)
1 Tirunnavaya –Guruvayur new line (35 Km) 138
2 Angamali-Sabarimala new line (111 km) 3,801
3 Ernakulam-Kumbalam doubling (8 km) 595
4 Kumbalam - Thuravur Patch doubling 8 0 3
(16 km)
5 Trivandrum- Kanyakumari doubling (87 km) 3,786
6 Shoranur - Vallathol doubling (10 km) 367
7 Palakkad Town to Parli Bypass Line 1 6 4
(2 Km)
8 Alappuzha-Ambalapuzha doubling (13 Km) 324
9 Turavur – Mararikulam doubling (21 Km) 451
Project sanctioned:-
As on 01.04.2025, 06 projects (02 new line and 04 doubling) of 266 km
length, costing ₹9,415 crore falling fully/partly in Keralam are sanctioned.
The summary is as under:-
Category No. of Total Length Balance Expenditure
projects Length Commissioned to upto March
complete 2025
(₹in Crore)
New line 02 146 km 0 km 146 km 309
Doubling 2,941
04 120 km 26 km 94 km
/multitracking
Total 06 266 km 26 km 240 km 3,250
...5/--5-
Zonal Railway wise details of Railway projects are made available in public
domain on Indian Railway’s website.
Execution of important infrastructure projects falling fully/partly in the
State of Keralam are held up due to delay in land acquisition. Status of land
acquisition in the State of Keralam is as under:
Total Land required for Projects in Keralam 476 ha
Land Acquired 65 ha (14%)
Balance Land to be acquired 411 ha (86%)
Railway had deposited ₹1,975 crore for land acquisition to Government of
Keralam. Support of the Government of Keralam is needed to expedite the
land acquisition. For instance, details of some major projects which are
delayed due to land acquisition are as under:-
SN Name of the project Total Land Balance
land acquired Land to be
required (in Ha) acquired
(in Ha) (in Ha)
1. Angamali - Sabarimala new line 416 24 392
(111 km)
2. Ernakulam – Kumbalam Patch 4 3 1
doubling (8 km)
3. Kumbalam – Turavur Patch doubling 10 9 1
(16 km)
4. Shoranur - Vallathol doubling 5 0 5
(10 km)
Government of India is geared up to execute projects, however success
depends upon the support of Government of Keralam.
...6/--6-
Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and remunerativeness of the
proposed route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives
Railway’s own operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
ROBs/ RUBs:-
Sanctioning of works of Road over Bridge (ROB)/Road under Bridge (RUB) in
lieu of Level crossings (LCs) is a continuous and dynamic process of Indian
...7/--7-
Railway. Such works are prioritised and taken up on the basis of its impact
on safety in train operations, mobility of trains & impact for road users and
feasibility etc.
No. of ROBs/ RUBs constructed on Indian Railways during the period 2004-
14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-25 (Upto 14,024 Nos. (including 121 Nos. in the State
Jan’26) of Keralam)
As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at cost of
₹ 1,14,196 Cr on Indian Railways including 138 Nos. Road Over Bridge
(ROB)/Road Under Bridge (RUB) are sanctioned at cost of ₹ 4,835 Cr in
Keralam which are at various stages of planning and execution.
01 No. Level Crossing (LC No. 10) exists in Wayanad Lok Sabha
Parliamentary and the work for construction of ROB has been sanctioned
at this location. General Arrangement Drawing (GAD) has been approved.
106 Nos. ROBs/RUBs are delayed on account of the State Govt. The details
are as under:
S.No. Reason ROBs/RUBs (in No.)
1. Delay in Land Acquisition by State Govt. 38
2. Finalization of Alignment by State Govt. 63
3. Law & order/ Public Protest/Court cases etc. 2
4. Agency yet to be fixed 3
...8/--8-
Completion of any ROB/RUB work depends on various factors like, fixing of
approach alignment, approval of General Arrangement Drawing (GAD), land
acquisition, removal of encroachment, shifting of infringing utilities,
statutory clearances from various authorities, law and order situation in
the area of project / work sites, number of working months in a year for
particular project / work sites due to climatic conditions etc. All these
factors affect the completion time of the projects / works.
Further, Railways have taken following measures to expedite the progress
of work:
i. Joint survey with concerned State Govt./Road Owning Authority is
done before finalizing the General Arrangement Drawing (GAD) to
ensure smooth execution.
ii. Periodic meetings of Railway & State Government officials are done
to resolve various issues related to ROB/RUB works.
iii. Standardization of superstructure drawings for various combinations
of span, skewness and width of road on Railway portion has been
done to avoid delays during the design approval. This has been issued
in the form of compendium, which can be directly adopted for Road
Over Bridge across Railway lines for expeditious planning.
Tourism:-
Indian Railways have issued ‘Bharat Gaurav Trains’ policy in November’
2021, under which theme based tourist circuit trains are being run with the
objective to showcase Indian’s rich cultural heritage and magnificent
historical places to the people of India and the world. As per this policy,
...9/--9-
service providers have full flexibility to decide the themes/itineraries for
operation of Bharat Gaurav tourist circuit trains, which may include tourist
circuits of any part of India including Wayanad, based on market demand,
commercial viability etc.
*****