See Full Document Text
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 3086
TO BE ANSWERED ON 11.03.2026
RAILWAY INFRASTRUCTURE PROJECTS IN FATEHGARH SAHIB LOK SABHA
CONSTITUENCY
3086. DR. AMAR SINGH:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware of delays in execution of sanctioned
railway infrastructure projects in Fatehgarh Sahib Lok Sabha
Constituency including the Doraha Railway overbridge approved in
March, 2024 and if so, the details thereof;
(b) the reasons for non-commencement of work on the said overbridge
despite approval and the timeline by which construction is proposed to
begin and be completed;
(c) whether the Government has assessed the inconvenience and safety
risks being faced by the general public due to delays in completion of
such projects and if so, the details thereof;
(d) the details of funds sanctioned, released and utilised for railway
infrastructure and passenger amenities in the said Constituency during
the last five years; and
(e) the steps taken/being taken by the Government to expedite pending
railway projects and improve passenger safety and connectivity in the
region?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (e): Sanctioning of proposals for construction of ROBs/RUBs in lieu of
Level Crossings is a continuous and dynamic process of Indian Railways.
Such works are prioritised and taken up on the basis of its impact on safety
§in train operations, mobility of trains & impact for road users and feasibility
etc.
Nos. of ROBs/ RUBs constructed on Indian Railways during the period
2004-14 vis a vis 2014-26 (Upto Jan’26) is as under:
Period ROBs/ RUBs constructed
2004-14 4,148 Nos.
2014-26 (Upto 14,024 Nos. (including 434 Nos. in the State of
Jan’26) Punjab)
As on 01.02.2026, 4,802 Nos. ROBs/ RUBs are sanctioned at the cost
of ₹1,14,196 Cr on Indian Railways including 120 Nos. Road Over Bridge
(ROB)/Road Under Bridge (RUB) at a cost of ₹ 1,848 crore in Punjab, which
are at various stages of planning and execution. Out of these, 04 Nos.
ROB/RUB works at a cost of ₹ 56 Cr are sanctioned in Fatehgarh Sahib Lok
Sabha Constituency.
The work of Road Over Bridge in lieu of LC No. 164 A-B at Km 353/990
was initially sanctioned in 2013 on cost sharing basis with Government of
Punjab. The work was to be executed by the state Govt. However, because
of inability of the State Govt. to execute the work, the work was dropped in
2021.
Keeping in view the public demand, the work was again sanctioned in
Feb’2024 at Railway’s cost. General Arrangement Drawings (GAD) for the
work has been approved and contract has been awarded by the Railways.
The work of construction has been taken up.
Railways have taken following measures to expedite the progress of
ROB/RUB works:(i) Joint survey with concerned State Govt./Road Owning Authority is done
before finalizing the General Arrangement Drawing (GAD) to ensure
smooth execution.
(ii) Periodic meetings of Railway & State Government officials are done to
resolve various issues related to ROB/RUB works.
(iii) Standardization of superstructure drawings for various combinations of
span, skewness and width of road on Railway portion has been done to
avoid delays during the design approval. This has been issued in the
form of compendium, which can be directly adopted for Road Over
Bridge across Railway lines for expeditious planning.
(iv) ROB/RUB works are planned to be executed on a single entity basis by
Railway wherever possible. In case any Road Owning authority/State
Govt. wants, then Railway may permit them to execute the work on a
single entity basis.
PUNJAB
Budget allocation for Infrastructure projects and safety works, falling
fully/partly in the Punjab is as under:
Period Outlay
2009-14 ₹225 crore/year
2025-26 ₹ 5,421 Cr. (More than 24 times)
As on 01.04.2025, 09 projects (04 new line and 05 doubling) of total length
714 Km, costing ₹ 21,926 crore, falling fully/partly in the Punjab are in
different stages of planning/sanctioning/execution, out of which 115 Km
length has been commissioned and an expenditure of ₹ 8,079 crore has
been incurred upto March’ 2025. The summary is as under:-Category No. of Total Length Expenditure upto
projects Length Commissio March 2025
ned (₹ in Crore)
New line 04 252 Km 64 Km 7,359
Doubling
/multitrack 05 462 Km 51 Km 720
ing
Total 09 714 Km 115 Km 8,079
Details of some of the recently completed projects falling fully/partly in the
Punjab are as under:
Cost
S. No. Project
(₹ in Cr.)
1 Chakki Bank-Bharoli Doubling (3 Km) 15
2 Jakhal- Mansa Doubling (45 Km) 163
3 Mirthal-Bhangala Beas River Doubling (2.5 Km) 74
4 Ambala-Dhapper-Chandigarh Doubling (45 Km) 339
5 Mansa – Bhatinda Doubling (49 Km) 216
6 Amritsar - Chheharta Doubling (7 Km) 31
Jallandhar-Pathankot-Jammu Tawi Doubling (209 850
7
km)
Kathua-Madhopur Punjab - doubling including 257
8
Bridge on Ravi (2.5 Km)
9 Rajpura-Bhatinda Doubling (173 Km) 2,459
Some of the projects falling fully/partly in the Punjab which have been taken
up are as under:
SN. Project Cost
(₹ in Cr.)
1 Nangal Dam-Talwara - Mukerian New line (123 Km) 2,018
2 Bhanupalli-Bilaspur-Beri New Line(63 Km) 6,753
3 Qadian-Beas New Line(40 km) 8424 Ferozpur-Patti New Line (26 Km) 300
5 Rama Mandi (Raman)-Maur Mandi (Maur) via 154
Talwandi Sabo ( 29 km) New Line
6 Ludhiana-Kila Raipur doubling (19 Km) 238
7 Ludhiana-Mullanpur doubling (21 Km) 235
8 Rajpura-Mohali New Line (18 km) 443
9 Rajpura Bypass line (14 km) 412
Government of India is geared up to execute projects, however success
depends upon the support of Government of Punjab. For instance,
details of some major projects which are delayed due to land acquisition are
as under: -
SN Name of the project Total land Land Balance Land
required acquired to be acquired
(in Ha) (in Ha) (in Ha)
1 Firozpur-Patti new line 166 0 166
2 Alal-Himmatana Chord 20 0 20
line
3 Qadian-Beas New Line 151 0 151
4 Rama Mandi( Raman)- 85 0 85
Talwandi Sabo New Line
Firozpur-Patti New line (26 km) situated fully in Punjab is an important
project near the international border. Land for project was to be handed over
free of cost for this project by State Govt. of Punjab. Total 166 Ha land is to
be acquired in the districts of Firozpur and Tarn Taran. Award for entire land
has been published in Mar’23. However, disbursement of award has not been
done by state govt. Considering delay in execution of this important border
area project, Ministry of Railways has decided to take up Firozpur-Patti New
line (26 km) through its own funding.Qadian-Beas (39.6 Km) New Rail Line Project was sanctioned in 2011-12 at a
cost of ₹ 205 crore. However, the project could not be taken forward due to
law and order issues. The project was then kept in abeyance. However,
considering importance of this project, it has been decided to take up the
work again.
Rajpura – Mohali new line project (18 Km) passing through Fatehgarh Sahib
Constituency has been sanctioned recently at a cost of ₹ 443 crore. The
project has been declared as special Railway Project. Competent Authority
for land Acquisition (CALA) has been nominated in November 2025 and land
acquisition has been taken up. This project will directly connect Southern
Punjab (Bathinda area), between Sirhind – Gobindgarh and Rajpura area to
Chandigarh avoiding Ambala.
Completion of Railway project/s including ROBs/RUBs depends on various
factors which include the following:
Land acquisition by State Government
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
Station redevelopment:
Ministry of Railways has launched Amrit Bharat Station Scheme for
redevelopment of stations with a long-term approach.
The scheme involves preparation of master plans and their
implementation in phases to improve the stations. The master planningincludes:
Improvement of access to station and circulating areas
Integration of station with both sides of city
Improvement of station building
Improvement of waiting halls, toilets, sitting arrangement, water
booths
Provision of wider foot over bridge/air concourse commensurate with
passenger traffic
Provision of lift/escalators/ramp
Improvement /Provision of platform surface and cover over platforms
Provision of kiosks for local products through schemes like ‘One
Station One Product’
Parking areas, Multimodal integration
Amenities for Divyangjans
Better passenger information systems
Provision of executive lounges, nominated spaces for business
meetings, landscaping, etc. keeping in view the necessity at each
station
The scheme also envisages sustainable and environment friendly solutions,
provision of ballastless tracks etc. as per necessity, phasing and feasibility
and creation of city centre at the station in the long term.
So far, 1,337 stations have been identified for development under this
scheme, out of which 30 stations including Sirhind station of Fatehgarh
Sahib Lok Sabha constituency, are located in Punjab. The names of
stations identified for development under Amrit Bharat Station Scheme in
Punjab are as following:State No. of Name of Stations
Stations
Punjab 30 Abohar, Amritsar, Anandpur Sahib, Beas,
Bhatinda Jn, Dhandari Kalan, Dhuri, Fazilka,
Firozpur Cantt, Gurdaspur, Hoshiarpur, Jalandhar
Cantt Jn, Jalandhar City Jn, Kapurthala, Kot
Kapura Jn, Ludhiana Jn, Malerkotla, Mansa,
Moga, Muktsar, Nangal Dam, Pathankot Cantt.,
Pathankot Jn, Patiala, Phagwara Jn, Phillaur Jn,
Rup Nagar, Sahibzada Ajit Singh Nagar Mohali,
Sangrur, Sirhind
Development works at railway stations under Amrit Bharat Station Scheme
in Punjab have been taken up at a good pace. Till now, works of 03 stations
(Anandpur Sahib, Muktsar and Sahibzada Ajit Singh Nagar Mohali) in Punjab
have been completed under this scheme.
The activities for development at other stations have also been taken up at
good pace and progress of some of the stations is as given below:
Sirhind station: The work of improvement of station building, entrance
porch, AC waiting room with toilet, improvement of second class
waiting room, toilet block, circulating area, parking, entry/exit gate,
lighting and signage have been completed. The works of lift and 12 m
Foot Over Bridge have been taken up.
Gurdaspur station: The works of station building, platform shelter,
improvement of platform surface, waiting room, toilet, circulating area,
porch and lighting have been completed. The works of new platform no.
2, booking cum waiting hall, circulating area, parking, entry/exit gate onmain entry and second side and 12 m Foot Over Bridge have been taken
up.
Patiala station: The works of improvement of station building, entrance
porch, platform shelter, improvement of waiting hall, retiring room,
toilet, circulating area, parking, entry/exit gate and signage have been
completed. The works of platform surfacing, development of second
entry, lift and 12 m Foot Over Bridge have been taken up.
Sangrur station: The works of improvement of station building, entrance
porch, platform shelter, improvement of waiting room, toilet block,
circulating area, parking, entry/exit gate and signage have been
completed. The works of platform surfacing at platform no. 1, lift and
4.8 m Foot Over Bridge have been taken up.
Further development / redevelopment / upgradation / modernisation of
stations on Indian Railways is a continuous and ongoing process and works
in this regard are undertaken as per requirement, subject to inter-se
priority and availability of funds. The priority for development /
redevelopment / upgradation / modernisation of stations is accorded to
higher category of station over lower category of station while sanctioning
and executing the works.
Development / upgradation / modernisation of stations including under
Amrit Bharat Station Scheme is generally funded under Plan Head-53
‘Customer Amenities’. The details of allocation and expenditure under Plan
Head-53 are maintained Zonal Railway-wise and not work-wise, or station-
wise, or state-wise. Punjab is covered under the jurisdiction of two railway
zones, namely Northern Railway and North Western Railway. These zones
have been allocated ₹ 8,501 crore under Plan Head-53 for the last four
years and the current year. The expenditure incurred under Plan Head-53by these zones for the last four years and current year (up to January,
2026) is ₹ 7,310 crore.
Trains:
At present, Fatehgarh Sahib station is served by the following 08 train
services :
SN Train Number and Name
1 14053 Delhi-Daulatpur Chowk Himachal Express
2 14054 Daulatpur-Delhi Chowk Himachal Express
3 64514 Nangal Dam - Ambala Cantt MEMU
4 64515 Ambala Cantt - Nangal Dam MEMU
5 64511 Haridwar - Amb Andaura MEMU
6 64517 Ambala Cantt - Nangal Dam MEMU
7 64518 Nangal Dam - Ambala Cantt MEMU
8 64513 Saharanpur - Nangal Dam MEMU
Besides, introduction of train services on any route/section, which is an on-
going process, depends on various factors which include:
● Capacity of that section.
● Availability of path.
● Availability of required rolling stock.
● Availability of matching infrastructure for rolling stock.
● Maintenance requirement of railway tracks and other assets.
*****