GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6098
TO BE ANSWERED ON 01.04.2026
RAILWAY PROJECT BETWEEN TALCHER-GOPALPUR
†6098. SHRI RUDRA NARAYAN PANY:
Will the Minister of RAILWAYS be pleased to state:
(a) whether the Government is aware that a railway project from Talcher
(coal-city) to Gopalpur (port-city) in the Gulf of Bengal is pending for a
long time and if so, the details thereof;
(b) the effective steps are likely to be taken by the Government for its
completion; and
(c) whether the proposal from Talcher (coal-city) to Gopalpur (port-city) via
Hindol is likely to be reconsidered by the Government and if so, the
details thereof?
ANSWER
MINISTER OF RAILWAYS, INFORMATION & BROADCASTING AND
ELECTRONICS & INFORMATION TECHNOLOGY
(SHRI ASHWINI VAISHNAW)
(a) to (c): Talcher is already connected to Jagannathpur (Gopalpur) via
Hindol Road, Rajathgarh, Bhubaneswar, Khurda Road on the existing
Railway network. However, to further augment the connectivity following
works/surveys have been taken up:-
S. Name of Project Status
No.
1 Budhapank - Salegaon via Rajatgarh 3rd 57 KM commissioned.
and 4th Line (85 KM) Works have been taken up
in balance sections
2 Nergundi - Vizianagaram 3rd Line Works have been taken up.
(385 KM)
3 Rajathgarh - Kaipadar Road New Line DPR prepared
(93 KM) by passing Bhubaneshwar and
Khurda Road
§ Page 1 of 5S. Name of Project Status
No.
4 Haridaspur Jn. to Nergundi Jn. & DPR prepared
Cuttack Jn. to Vizianagaram Jn. 4th line
(440 KM)
5 Angul – Hindol - Nayagarh New Railway FLS sanctioned
Line (120 KM)
6 Talcher - Gopalpur New Line (282 KM) FLS sanctioned
After preparation of DPR, sanctioning of project requires consultation with
various stake-holders including State Governments and necessary
approvals viz. appraisal of NITI Aayog, Ministry of Finance etc. As
sanctioning of projects is a continuous and dynamic process, exact
timelines cannot be fixed.
ODISHA
Railway Budget:
Budget allocation in the recent years has increased significantly. Budget
allocation for infrastructure projects and safety works, falling fully/partly in
the State of Odisha is as under:
Period Outlay
2009-14 ₹ 838 Cr./year
2025-26 ₹ 10,599 Cr. (Nearly 13 times)
Track Construction:
The details of commissioning/laying of new track falling fully/partly in the
State of Odisha during 2009-14 and 2014-25 is as under:
Period New Track Average Commissioning of new tracks
Commissioned per year
2009-14 267 Km 53 Km
2014-25 2,150 Km 195 Km
(More than 3.5 times)
Page 2 of 5Project Sanctioned:
As on 01.04.2025, 49 projects (19 New Lines and 30 Doubling), of a total
length of 4,010 Km, costing ₹ 67,496 crore, falling fully/partly in Odisha, are
sanctioned, out of which 1,429 Km length has been commissioned and an
expenditure of ₹28,043 crore has been incurred upto March’ 2025. The
summary is as under:-
Total Length
No of Total Exp
Length Commissioned
Category sanctioned upto Mar'25
NL/GC/DL till Mar'25
Projects (₹ in Cr)
(in Km) (in Km)
New Lines 19 1,544 256 6,270
Doubling/Multi-
30 2,466 1,173 21,773
tracking
Total 49 4,010 1,429 28,043
Recently Completed Projects:
Details of some of the recently completed projects falling fully/partly in
Odisha are as under:
S. No. Name of Project Cost
(In Crores of ₹)
Daitari-Banspani New Line and Jakhapura-
1 1,317
Haridaspur 3rd Line (179 Km)
MCL siding from Jharsuguda - Sardega New
2 1,598
Line (53 Km)
3 Haridaspur-Paradeep New Line (82 Km) 2,397
4 Angul-Sukinda New Line (104 Km) 2,834
5 Champa-Jharsuguda 3rd Line (152 Km) 1,227
6 Sambalpur-Titlagarh Doubling (182 Km) 2,262
7 Rourkela-Jharsuguda 3rd Line (101 Km) 1,313
Banspani-Daitari-Tomka-Jakhapura Doubling 1,827
8
(164 Km)
9 Sambalpur-Talcher Doubling (174 Km) 1,539
10 Raipur - Titlagarh Doubling (203 Km) 1,171
11 Jharsuguda-Sardega Doubling (50 Km) 3,200
Page 3 of 5Ongoing Projects:
Further, some of the main projects falling fully/partly in Odisha which have
been taken up are as under:
S.No. Name of Project Total Cost
(In Crores of ₹)
1 Junagarh-Nabarangpur New Line (116 Km) 2,865
2 Nabarangpur-Jeypore New Line (41 Km) 748
3 Jeypore-Malkangiri New Line (130 Km) 2,344
4 Malkangiri – Pandurangapuram New Line 3,592
(174 Km)
5 Buramara-Chakulia New Line (60 Km) 1,459
6 Gunupur-Therubali New Line (74 Km) 1,166
7 Puri - Konark New Line (32 Km) 492
8 Badampahar-Kendujhargarh New Line (82 Km) 1,876
9 Bangriposi-Gorumahisani New Line (86 Km) 2,269
10 Bargarh Road-Nawapara Road New Line (138 Km) 2,622
11 Vizianagram-Titlagarh 3rd Line (265 Km) 6,996
12 Jarapada- Budhapank 3rd& 4th Line with flyover at 810
Talcher (101 Km)
13 Budhapank- Salegaon via Rajatgarh 3rd& 4th Line 2,023
(170 Km)
14 Nergundi - Vizianagaram 3rd Line (385 Km) 4,963
15 Kottavalasa-Koraput Doubling (189 Km) 2,500
16 Koraput-Singapur Road Doubling (165 Km) 2,362
17 Jagdalpur-Koraput Doubling (107 Km) 1,547
18 Jharsuguda-Bilaspur 4th line (206 Km) 2,596
19 Bondamunda-Ranchi Doubling (159 Km) 3,029
20 Narayangarh-Bhadrak 3rd line (153 Km) 2,136
21 Bhadrak-Nergundi 3rd Line (92 Km) 1,284
During last three years i.e. 2022-23, 2023-24, 2024-25 and current Financial
Year i.e. 2025-26, total 79 Nos. of Surveys (31 New Line, 48 Doubling) falling
fully/partly in the State of Odisha having a total length of 5,436 Km have
been sanctioned.
Page 4 of 5Sanction of any railway project depends upon many parameters/factors
which include the following:
Anticipated traffic projections and Remunerativeness of the proposed
route
First and last mile connectivity provided by the project
Connection of missing links and providing additional route
Augmentation of congested/saturated lines
Demands raised by State Governments/Central Ministries/Public
representatives,
Railway’s operational requirements
Socio-economic considerations
Overall availability of funds
Completion of Railway project/s depends on various factors which include
the following:
Land acquisition
Forest clearance
Shifting of infringing utilities
Statutory clearances from various authorities
Geological and topographical conditions of area
Law and order situation in the area of project site
Number of working months in a year for particular project site etc.
All these factors affect the completion time and cost of the project/s.
*****